search



Corporate Information

 
Press Release (Jun 09,2011)
Status of TEPCO's Facilities and its services after the Tohoku-Chihou-Taiheiyou-Oki Earthquake (as of 4:00 PM, June 9)
 
Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March 
11th 2011, TEPCO's facilities including our nuclear power stations have 
been severely damaged. We deeply apologize for the anxiety and 
inconvenience caused. 
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on 
April 17th, we have compiled the roadmap towards restoration from the 
accident and then we updated the roadmap considering the current situation, 
on May 17th. By bringing the reactors and spent fuel pools to a stable 
cooling condition and mitigating the release of radioactive materials, we 
will make every effort to enable evacuees to return to their homes and for 
all citizens to be able to secure a sound life. 
 
Below is the status of TEPCO's major facilities. 
*Updates from previous press release are underlined.
 
[Nuclear Power Station] Fukushima Daiichi Nuclear Power Station: Units 1 to 3: shutdown due to the earthquake (Units 4 to 6: outage due to regular inspections) - At 6:26 pm on June 5, transfer of accumulated water in the Unit 3 turbine building to condenser was initiated. At 10:44 am on June 9, the transfer was completed. - At 1:42 pm on June 9, freshwater injection to Unit 3 spent fuel pool using fuel pool cooling and filtering system was initiated(from 1:45 pm to 2:40 pm, hydrazine was also injected). Injection was completed at 3:31 pm. - At 9:00 am on June 9, transfer of accumulated water in Unit 6 turbine building underground was resumed. - From 11:47 am to 12:14 pm on June 9, TEPCO employees entered into Unit 3 reactor building and conducted radiation dose survey by Γ camera as a preparation for the nitrogen injection into the PCV. - On June 9, using a concrete pumping vehicle, we have been spraying dust inhibitor, which prevents the radioactive materials from dispersing, to the roof and the wall of Unit 1 and 3 turbine building. On June 9, workers have been spraying the dust inhibitor near the main gate. - At 10:30 on June 9, water flow test of circulating seawater purification facility located in the Unit 2 and 3 screen area was initiated. The test was completed at 3:00 pm.
 
Fukushima Daini Nuclear Power Station: Units 1 to 4: shutdown due to the earthquake - At around 6:10 pm on June 8, during the work of draining water stored in the tank, for the purpose of inspection of emergency underground tanks of High-voltage Start-up Transformer, TEPCO employee verified the presence of oil that had leaked to the sea surface around the water discharge canal of Unit 3 and 4, Fukushima Daini Nuclear Power Station. Draining stored water was suspended and oil adsorption mattresses were utilized to prevent the spread of oil. At 9:50 pm on June 8, oil fence barriers were installed and extremely thin oil layer inside the oil fence was observed. Maximum amount of leaked oil was estimated to be 0.5 m3. The cause of leakage is under investigation. Discharged water is all rain water, and discharge was done through a duct, thus there is no discharge of radioactive materials to the sea.
 
Kashiwazaki Kariwa Nuclear Power Station: Units 1, 5, 6, 7: normal operation (Units 2 to 4: outage due to regular inspection)
 
[Thermal Power Station] - Hirono Thermal Power Station Unit 2 and 4: Shutdown due to the earthquake
 
[Hydro Power Station] - Power supply has returned to normal and facilities damaged by the earthquake are now being handled in a timely manner.
 
[Impacts on Transmission Facilities] - Power supply has returned to normal and facilities damaged by the earthquake are now being handled in a timely manner.
 
[Perspective of Power Supply and Demand Balance in this Summer] We have worked to restore electricity supply after our nuclear and thermal power facilities were severely damaged by Tohoku-Chihou-Taiheiyou-Oki Earthquake. This time, we revised that the supply capacity in this summer would increase because we could plan to secure an additional capacity. However, in order to maintain the policy of avoiding further implementation of rolling blackouts during the summer, in addition to the above increase of the supply capacity, we sincerely ask for your continued cooperation in reducing electricity consumption. Now we are creating concrete measures considering "Outline of Countermeasures for Power Supply and Demand During Summertime" presented by the Electricity Supply-Demand Emergency Response Headquarters of the Japanese government. (Previously Announced) It seems that planned outage could be escaped thanks to your understanding for brownout. However In the event that an unplanned outage such as excessive continuous operation in old plants and a sudden increase of power demand due to unusual hot temperature occur, there is a possibility to affect a stable power supply. In order to maintain the policy of avoiding rolling blackouts, we steadily implement to install additional power capacity we have planed, and we continuously do our best efforts to secure supply capacity. We apologize for the inconvenience this may cause and appreciate for your cooperation for brownout.
Appendix: Past Progress (PDF 343KB)
 
* Revised past progress
back to page top


to TOP