Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11th 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17th, we have compiled the roadmap towards restoration from the
accident and then we updated the roadmap considering the current situation,
on May 17th. By bringing the reactors and spent fuel pools to a stable
cooling condition and mitigating the release of radioactive materials, we
will make every effort to enable evacuees to return to their homes and for
all citizens to be able to secure a sound life.
Below is the status of TEPCO's major facilities.
*Updates from previous press release are underlined.
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
- At 10:38 am on June 3, installation work of temporary reactor pressure
meter at Unit 1 was initiated. At 12:21 pm, the installation work was
completed.
- At 1:16 pm on June 3, freshwater injection was suspended in Unit 3 due
to re-routing of the water supply line to the reactor. At 1:32 pm on
June 3, freshwater injection was resumed.
- At 1:49 pm on June 3, freshwater injection was suspended in Unit 2 due
to re-routing of the water supply line to the reactor. At 2:09 pm on
June 3, freshwater injection was resumed.
- At 2:35 pm on June 3, water spray to Unit 4 spent fuel pool was
initiated by a concrete pumping vehicle (at 2:44pm, hydrazine [corrosion
inhibitor] injection was initiated).
- On June 3, we sprayed dust inhibitor to prevent discharge of radioactive
materials to the roof and exterior wall of the reactor building of Unit
3 using a bending spray tower vehicle (approximately 4,800 m2).
On June 3, we have been spraying dust inhibitor to areas including
observation point.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
Kashiwazaki Kariwa Nuclear Power Station:
Units 1, 5, 6, 7: normal operation
(Units 2 to 4: outage due to regular inspection)
[Thermal Power Station]
- Hirono Thermal Power Station Unit 2 and 4: Shutdown due to the
earthquake
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Perspective of Power Supply and Demand Balance in this Summer]
We have worked to restore electricity supply after our nuclear and thermal
power facilities were severely damaged by Tohoku-Chihou-Taiheiyou-Oki
Earthquake. This time, we revised that the supply capacity in this summer
would increase because we could plan to secure an additional capacity.
However, in order to maintain the policy of avoiding further
implementation of rolling blackouts during the summer, in addition to the
above increase of the supply capacity, we sincerely ask for your continued
cooperation in reducing electricity consumption. Now we are creating
concrete measures considering "Outline of Countermeasures for Power Supply
and Demand During Summertime" presented by the Electricity Supply-Demand
Emergency Response Headquarters of the Japanese government.
(Previously Announced)
In the event that an unplanned outage such as excessive continuous
operation in old plants and a sudden increase of power demand due to
unusual hot temperature occur, there is a possibility to affect a stable
power supply. In order to maintain the policy of avoiding rolling
blackouts, we steadily implement to install additional power capacity we
have planed, and we continuously do our best efforts to secure supply
capacity.
Appendix: Past Progress (PDF 155KB)
* Revised past progress