Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11th 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
With regard to the accident at Fukushima Daiichi Nuclear Power Station, on
April 17th, we have put together the roadmap towards restoration from the
accident. By bringing the reactors and spent fuel pools to a stable
cooling condition and mitigating the release of radioactive materials, we
will make every effort to enable evacuees to return to their homes and for
all citizens to be able to secure a sound life.
Below is the status of TEPCO's major facilities.
*Updates from previous press release are underlined.
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
- Installation work of exhauster was initiated in order to improve the
work environment in the reactor building of Unit 1
- At 10:05 am on May 2nd, water injection to spent fuel pool of Unit 2 by
motor driven pump was initiated. Injection was finished at 11:40 am.
- At 2:00 pm on May 1st, transfer of accumulated water in Unit 6 turbine
building to a temporary tank was initiated. At 5:00 pm, transfer pump
was stopped (approximately 120 m3). At 10:00 am on May 2nd, transfer was
restarted.
- On May 2nd, unmanned crawler dump truck has sprayed dust inhibitor in
the south and west side of the reactor building of Unit 4. We have also
sprayed dust inhibitor to the slope surrounding the former
Administration Office building by conventional method.
In previous announcements, we described the building as "the turbine
building of Unit 4," but it was an error. We meant "the reactor building
of Unit 4." We would like to apologize for the error and correct it.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
Kashiwazaki Kariwa Nuclear Power Station:
Units 1, 5, 6, 7: normal operation
(Units 2 to 4: outage due to regular inspection)
[Thermal Power Station]
- Hirono Thermal Power Station Units 2 and 4: Shutdown due to the
earthquake
- Hitachinaka Thermal Power Station Unit 1: Shutdown due to the earthquake
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Avoidance of further Implementation on Planned Rolling Blackouts and
Request for Conserving Electricity Consumption]
Currently, we are working to restore electricity supply after our nuclear
and thermal power facilities were severely damaged by Tohoku-Chihou-
Taiheiyou-Oki Earthquake. The widespread understanding and cooperation of
our customers to conserve electricity have contributed to the improvement
of this tight power supply-demand balance situation.
Amidst this backdrop, since the electricity supply will be able to balance
with the demand for the time being, we have decided not to implement
further rolling blackouts in principle.
However, we sincerely ask for your continued cooperation in reducing
electricity consumption due to the possible increase in demand caused by
warmer weather or unexpected trouble at power stations that are currently
being restored to service. In case the electricity supply-demand balance
becomes tighter than expected, we may regrettably need to restart the
implementation of rolling blackouts, with prior notice. We kindly ask for
your cooperation.
We will do our best to maintain this policy of avoiding further
implementation of rolling blackouts during the summer.
*We partially corrected on May 3.
Appendix: Past Progress (PDF 275KB)
* Revised past progress