Due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake which occurred on March
11th 2011, TEPCO's facilities including our nuclear power stations have
been severely damaged. We deeply apologize for the anxiety and
inconvenience caused.
Below is the status of TEPCO's major facilities.
*New items are underlined
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
*At 5:00 pm, on April 15th, we had completed transferring emergency power
sources to spray water to reactors of Unit 1 to 3 to the upland.
*From 2:30 pm on April 15th, water spray to the spent fuel pool of Unit 4
was started with the concrete pumping vehicle and the water spray was
finished at 6:29 pm, on April 15th.
*On March 20th and 21st and from March 23rd to April 14th, we have
detected radioactive materials in the air which were collected at the
site. The data of detected three nuclides (Iodine-131, Cesium-134 and
Cesium-137) are released as fixed figures. Other nuclide figures are to
be re-evaluated based on improved measures for recurrence prevention
which have been prepared in accordance with a strong warning by NISA
on April 1st.
*On March 21st and from March 23rd to April 14th, we have detected
radioactive materials in the seawater around the water discharge
canal of the plant. The data of detected three nuclides (Iodine-131,
Cesium-134 and Cesium-137) are released as fixed figures. Other nuclide
figures are to be re-evaluated based on improved measures for recurrence
prevention which have been prepared in accordance with a strong warning
by NISA on April 1st.
*From 3:00 pm April 5th, a construction of installing large sandbags
around the pier to prevent the outflow of the contaminated water from
station's port on the south side to the ocean was started. From April
15, we started to throw in sandbags including zeolite in front of the
screen room of Unit 1 to 4. In order to prevent water containing
radioactive materials from spilling from a plant's port to the sea, we
installed approximately 120 meter wide double silt fences around a
breakwater on the south of the station at 10:45 am on April 11th. On
April 12th, 13th and 15th, we installed a total of 7 iron plates in front
of the screen of Unit 2. At 1:50 pm, April 13th, double silt fences were
installed in front of the screen of Unit 3 and 4. At 12:20 pm, silt
fences were installed in front of the screen of Unit 1 and 2 and the
water intake canal.
*From 7:03 pm, April 4th, we started discharging the low level radioactive
wastewater stored in the Centralized Radiation Waste Treatment Facility
to the ocean from the south of the water discharge canal. The discharge
was finished at 5:40 pm, April 10. Total amount of discharged water is
approximately 9,070 tons. Also, from 9:00 pm, April 4th, we started
discharging the low level radioactive subsurface wastewater stored in the
sub drain pits of Unit 5 and 6 by using one pump to the ocean from the
water discharge canal of Units 5 and 6. At 6:52 pm, April 9th we finished
discharging water. The amount of discharged water was approximately 1,323
tons.
The total amount of emitted radioactivity is approximately 1.5*1011
Becquerel. We evaluate approximately 0.6 mSv of effective radioactive
doses per year per an adult as the impact on the discharge of the low
radioactive stored water to the ocean if an adult eats adjacent fish and
seaweeds every day. The amount (0.6 mSv of effective radioactive doses
per year) is one-forth of annual radioactive dose (2.4 mSv) to which the
general public is exposed from nature and equivalent to that when we
evaluated before discharging the water to the ocean.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
Kashiwazaki Kariwa Nuclear Power Station:
Units 1, 5, 6, 7: normal operation
(Units 2 to 4: outage due to regular inspection)
[Thermal Power Station]
-Hirono Thermal Power Station Units 2 and 4: Shutdown due to the
earthquake
-Hitachinaka Thermal Power Station Unit 1: Shutdown due to the
earthquake
-Kashima Thermal Power Station Unit 6: Shutdown due to the earthquake
[Hydro Power Station]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
-Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Avoidance of further Implementation on Planned Rolling Blackouts and
Request for Conserving Electricity Consumption]
Currently, we are working to restore electricity supply after our nuclear
and thermal power facilities were severely damaged by
Tohoku-Chihou-Taiheiyou-Oki Earthquake. The widespread understanding and
cooperation of our customers to conserve electricity have contributed to
the improvement of this tight power supply-demand balance situation.
Amidst this backdrop, since the electricity supply will be able to
balance with the demand for the time being, we have decided not to
implement further rolling blackouts in principle.
However, we must sincerely ask for your continued cooperation in
reducing electricity consumption due to the possible increase in demand
caused by warmer weather or unexpected trouble at power sta tions that
are currently being restored to service. In case the electricity
supply-demand balance becomes tighter than expected, as stated, we may
reluctantly restart the implementation of rollin g blackouts. We kindly
ask for your cooperation.
We will do our best to maintain this policy of avoiding further
implementation of rolling blackouts during the summer.
Appendix: Past Progress (PDF 140KB)
* Revised past progress