Due to the Tohoku-Taiheiyou-Oki Earthquake which occurred on March 11th
2011, TEPCO's facilities including our nuclear power stations have been
severely damaged. We deeply apologize for the anxiety and inconvenience
caused.
Below is the status of TEPCO's major facilities.
*New items are underlined
[Nuclear Power Station]
Fukushima Daiichi Nuclear Power Station:
Units 1 to 3: shutdown due to the earthquake
(Units 4 to 6: outage due to regular inspections)
* Below is the status of TEPCO's major facilities due to the 6.3 magnitude
earthquake centered in the Fukushima-Hama-dori earthquake which occurred
at approximately 2:07 pm, April 12th 2011,
- No shutdown of the off-site power of the units 1-6
- No abnormalities in water injection to the reactor of the units 1-3,
nitrogen gas injection to the reactor containment vessel of unit 1
- No abnormalities were detected in the parameter of each of the units.
- No abnormalities in the data taken from the monitoring before as well
as after the earthquake.
- We advised workers at outdoor to evacuate in the key earthquake-proof
building after the quake We confirmed that there were no injured
workers, we cancelled the evacuate advice at 3:05 on April 12th, 2011.
* From 4:26PM, April 12th, we began spraying water to the spent fuel pool
of Unit 3 by a concrete pumping vehicle and finished at 5:16PM, April
12th.
* From 0:30AM, April 13th, we began spraying water to the spent fuel pool
of Unit 4 by a concrete pumping vehicle and finished at 6:57AM, April
13th.
* From 7:35PM, April 12th, we began transferring puddle water in the
trench of Unit 2 to the condenser of Unit 2.
* At approx. 9:30 am, April 2, we found that there was accumulated water
in the shaft (concrete product) for storing power cables near the intake
of water for Unit 2, that the spatial radioactive dose was over
1,000mSv/h and that the water spilled into the sea from the crack
(approx. 20 cm) on the side of the shaft. Since there is a joint between
the trench of Unit 2 and the shaft, based on the possibility that the
accumulated water in the turbine building of Unit 2 was spilled into the
sea through this joint, we injected fresh concrete to the shaft twice,
however, we could not observe a change in the amount of water flowing
into the sea. Therefore, we considered that a new method to stop the
water and determined to use the polymer. On April 4, we injected the
tracer from the vertical shaft to examine the flow path. We did not
observe reduction of flow or change of color of water leaked. We checked
the drawings and confirmed the route. At the same time, we checked the
situation of the pit in detail and considered the possibility that the
water was not from the pit, rather, from the joint between the piping
upstream of the pit and the duct, then the water seeped through a layer
of gravel below the piping. In order to stop that seepage from the layer
of gravel, we decided to conduct the water sealing to the bedrock around
the piping. We arranged for the specialist and gathered equipments. On
April 5, liquid glass was injected to the bedrock. Tracer was put through
the two new holes drilled near the pit to investigate the water flow. At
2:15 pm, April 5, it was observed the water with tracer came out from the
crack on the concrete wall of the pit. At 3:07 pm, April 5, injection of
coagulant from the holes was initiated and we have confirmed the outflow
from the crack on the concrete wall of the pit has stopped at 5:38 am,
April 6. We confirmed the water level has not been rising in the turbine
building of unit 2. On April 6, a countermeasure by using rubber plate
and fixer was implemented to prevent discharge of radioactive materials,
and we are continuously monitoring for any existence of leakage. From
3:00pm April 5, a construction of installing large sandbags around the
pier to prevent the outflow of the contaminated water from station's
port on the south side to the ocean was started. In order to prevent
water containing radioactive materials from spilling from a plant's port
to the sea, we installed 120 meter wide double silt fences around a
breakwater on the south of the station at 10:45 am on April 11. From
April 12th, we are working on installing an iron plate in front of the
screen of Unit 2.
Iodine and Cesium were detected from the water sampled in the pit and in
the sea near the water discharge. Other nuclide will be re-evaluated. In
addition, from April 2nd, we will implement sampling at 15km offshore
Fukushima Daiichi and Fukushima Daini Nuclear Power Stations(3 points
have been added since April 5) and will evaluate these samples
comprehensively.
* April 12th we conducted sampling water at fuel pool, to assess the
situation of spent fuel in fuel pool. We will analyze nuclide from now.
* From 3:00 pm, April 1, we started spraying anti-scattering material in
order to prevent diffusion of radioactive materials. This attempt was
conducted on a trial basis at the mountain side area of the common spent
fuel pool in the range of 500m2. The spraying finished at 4:05 pm. On
April 5, we also sprayed the anti-scattering material on a trial basis
at the east and south sides of Unit 4, and the mountain side area of the
common spent fuel pool in the range of 600m2. On April 6 we sprayed at
the mountain side area of the common spent fuel pool in the range of
approx. 600m2, Approx. 680 m2 on April 8, approx. 550 m2 on April 10,
approx. 1,200 m2 on April 11 and approx. 700 m2 on April 12 on a trial
basis.
Fukushima Daini Nuclear Power Station:
Units 1 to 4: shutdown due to the earthquake
- There was no impact from the 6.3 magnitude earthquake whose epicenter
was at Fukushima-Hama-dori which occurred at approximately 2:07 pm,
April 12th 2011.
Kashiwazaki Kariwa Nuclear Power Station:
Units 1, 5, 6, 7: normal operation
(Units 2 to 4: outage due to regular inspection)
- There was no impact from the 6.3 magnitude earthquake whose epicenter
was at Fukushima-Hama-dori which occurred at approximately 2:07 pm,
April 12th 2011.
[Thermal Power Station]
- Hirono Thermal Power Station Units 2 and 4: Shutdown due to the
earthquake
- Hitachinaka Thermal Power Station Unit 1: Shutdown due to the earthquake
- Kashima Thermal Power Station Unit 6: Shutdown due to the earthquake
[Hydro Power Station]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Impacts on Transmission Facilities]
- Power supply has returned to normal and facilities damaged by the
earthquake are now being handled in a timely manner.
[Avoidance of further Implementation on Planned Rolling Blackouts and
Request for Conserving Electricity Consumption]
Currently, we are working to restore electricity supply after our nuclear
and thermal power facilities were severely damaged by Tohoku-Taiheiyou-Oki
Earthquake. The widespread understanding and cooperation of our customers
to conserve electricity have contributed to the improvement of this tight
power supply-demand balance situation.
Amidst this backdrop, in principle, we have decided not to implement
further rolling blackouts. However, we must sincerely ask for your
continued cooperation in reducing electricity consumption due to the
possible increase in demand caused by warmer weather or unexpected trouble
at power stations that are currently being restored to service. In case
the electricity supply-demand balance becomes tighter than expected, as
stated, we may reluctantly restart the implementation of rolling blackouts.
We kindly ask for your cooperation. We will do our best to maintain this
policy of avoiding further implementation of rolling blackouts during the
summer.
Appendix: Past Progress (PDF 104KB)
* Revised past progress