Acting from the perspective of making a contribution to improving the environment in a number of different overseas countries, improving thermal efficiency and expanding measures to protect the environment, TEPCO has fully utilized its own technologies for thermal power station construction, operation and maintenance which it has assiduously accumulated to date.
Engineering Stage
1. Conceptual Plant Design
Basic Design
  • Plant Performance
  • Plant Specifications
  • Plant Operation

Plot Plan
  • Plant Layout
  • Equipment Arrangements
  • Equipment Transport and Installation Plan

2. EPC Contract (Engineering, Procurement, and Construction)
Request for Proposals for EPC
  • Scope of Work
  • Design Conditions
  • Plant Operation
  • Guarantee Items

Pre-qualifying Possible EPC Contractors
  • Evaluation of Contractors

Review of EPC Proposal
  • Specifications of Equipment
  • Manufacturing, Transport, and Installation Schedule / Procedure
  • Equipment Venders
  • Test Philosophy

Detailed Engineering
  • Overall Schedule
  • Responsibility
  • Plant Layout and Equipment Arrangements for Maintenance and Safety
  • Specifications of Equipment
  • Manufacturing, Transport, and Installation Schedule / Procedure
  • Overall Quality, Environment, and Safety Control

Estimation of EPC Contract
  • Scope of EPC
  • EPC Cost

3. Project Schedule (Engineering, Construction, and Startup)

4. Permitting
Plant Specifications for Environmental Permit
Fuel Specifications for Environmental Permit
Application for Permit
  • Environment
  • EPC Cost

5. Overseas Experience of Engineering
(1) Engineering in Vietnam
Title: Owner's Engineering Service at Phu-My 2-2 Combined Cycle Power Plant Project in Vietnam
Owner: Mekong Energy Company Ltd.
Term: February 1999 October 2004
Project Outline: Phu-My 2-2 in Vung Tau Province is a 715MW Gas-Fired Combined Cycle Power Plant Project of Electricity of Vietnam, to be developed and implemented under the Build, Own and Operate Transfer arrangement with the Ministry of Industry.
Heat Recovery Steam Boiler in the Phu-My 2-2

img01

Technical Present
  • Feasibility study
  • Environmental impact assessment study
  • Review of the plant design, drawing and document provided by the EPC
  • Assisting owner in the negotiation and finalization of the EPC contract
  • Providing technical support and assistance during negotiation with the lenders and insurers

(2) Engineering in Taiwan
Title: Owner's Engineering Service at Chang-Bin / Fong-Der Combined Cycle Power Plant Project in Taiwan
Owner: Star Energy Power Corporation / Chang-Bin Power Plant
Sun Ba Power Corporation / Fong-Der Power Plant
Term: August 2000 April 2004
Project Outline: Chang-Bin (490MW in Changhua Province) and Fong-Der (490MWx2 in Tainan Province) are Gas-Fired Combined Cycle Power Plant Projects for IPP in Taiwan, to be developed and implemented under the Build, Own and Operate arrangement.
Technical Present
  • Review of the plant design, drawing and document provided by the EPC
  • Assisting owner in the negotiation and finalization of the EPC contract
  • Providing technical support and assistance during negotiation with the lenders and insurers

img02
Chang –Bin Power Plant (Taiwan)