Top > Releases ・ Announcements > Announcements > 2013 > Power Supply Facilities Failure at Fukushima Daiichi Nuclear Power Station (Follow-up Report 7)
At around 6:57 PM on March 18, there was an incident where the power supply facilities in the Main Anti-earthquake Building at Fukushima Daiichi Nuclear Power Station momentarily stopped. The updates on the incident are provided below.
At 12:36 PM on March 20, a TEPCO employee found soot at terminals and on a wall in the power panel of the Units 3/4 temporary M/C (A) during the investigation of the power supply facilities failure in Fukushima Daiichi NPS.
Then, we informed the fact to Futaba Fire Station at 12:45 PM.
We will conduct further investigations for this power supply facilities failure, and will announce soon after we find new information.