We are announcing the status of major inspections and restoration works and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection/ Restoration Status
○ Inspection and restoration completed between August 24 to August 30, 2012
(Completed on the following date)
- No notable activity during this week.
○ Inspection and restoration to be commenced between August 31 to September 6, 2012
(To be commenced on the following date)
- No notable activity during this week.
○ Work Schedule of Major Inspection and Restoration from August 26 to September 22, 2012
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) ...Appendix
Appendix:
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) (PDF 14.7KB)