Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of July12)

We are announcing the status of major inspections and restoration works and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/ Restoration Status

◇ Inspection and restoration completed between July 6 and July 12, 2012 
(Completed on the following date)

- No notable activity during this week.

◇ Inspection and restoration to be commenced between July 13 and July 19, 2012 
(To be commenced on the following date)

- No notable activity during this week.

◇ Work Schedule of Major Inspection and Restoration from July 8 to August 4, 2012 

- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) ...Appendix

◇ Other Findings

- Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; Grades GI, GII, GIII; and non-graded) 
(including nonconformances related to: the Chuetsu-Oki Earthquake; Grades As, A, B, C, D; and non-graded)

Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake(during 4 Weeks) (PDF 15.4KB)
Appendix: Processing Status of Nonconformances of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (PDF 15.2KB)
* The attached file titled "Processing Status of Nonconformances of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake" is only available in Japanese.
We apologize for any inconvenience this may cause.