*The updates from the previous announcement are underlined.
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1 (Shut down)
-Explosive sound and white smoke were confirmed after a big quake occurred at 3:36 pm on March 12, 2011. It was assumed to be hydrogen explosion.
-At 3:37 pm on March 25, 2011, we started injecting freshwater to the reactor and are now injecting fresh water by a motor driven pump powered by the off-site transmission line.
-At 10:11 am on December 10, 2011, in addition to water injection from water feeding system, we started water injection from piping of core spray system to the reactor.
The current amount of water injection from the feed water system is approx. 4.7 m3/h and that from the reactor core spray system is approx. 2 m3/h.
-At 1:31 am on April 7, 2011, we commenced injection of nitrogen gas into Primary Containment Vessel.
-At 11:22 am on August 10, 2011, we started cyclic cooling for the water in the spent fuel pool by an alternative cooling equipment of the Fuel Pool Cooling and Filtering System.
-At 4:04 pm on November 30, 2011, we started operation to inject nitrogen into the reactor pressure vessel.
-At 6:00 pm on December 19, 2011, a full-scale operation of the PCV gas management system started.
Unit 2 (Shut down)
-At approximately 6:00 am on March 15, 2011, an abnormal noise began emanating from nearby Pressure Suppression Chamber and the pressure within the chamber decreased.
-At 10:10 am on March 26, 2011, we started injecting freshwater to the reactor and are now injecting fresh water by a motor driven pump powered by the off-site transmission line.
-At 2:59 pm on September 14, 2011, in addition to water injection from feed water system, we started water injection from piping of core spray system to the reactor.
The current water injection amount from the reactor feed water system is approx. 2.8 m3/h and that from the core spray system is approx. 6m3/h.
-At 5:21 pm on May 31, 2011, we started cyclic cooling for the water in the spent fuel pool by an alternative cooling equipment of the Fuel Pool Cooling and Filtering System.
-At 8:06 pm on June 28, 2011, we started injecting nitrogen gas into the Primary Containment Vessel.
-At 6:00 pm on October 28, 2011, a full operation of the PCV gas control system started.
-On March 21, 2012, we carried out the sampling for the PCV gas control system. As the result of the analysis, we confirmed that the concentration of Xe-135 was below the detectible limit (9.1×10-2 Bq/cm3) and less than the re-criticality state judge standard (1 Bq/cm3).
-At 10:46 am on December 1, 2011, we started the nitrogen injection to the Reactor Pressure Vessel.
-At 11:50 am on January 19, 2012, we started the operation of the spent fuel pool desalting facility.
Unit 3 (Shut down)
-Explosive sound and white smoke were confirmed at approximately 11:01 am on March 14, 2011. It was assumed to be hydrogen explosion.
-At 6:02 pm on March 25, 2011, we started injecting fresh water to the reactor and are now injecting fresh water by a motor driven pump powered by the off-site transmission line.
-At 2:58 pm on September 1, 2011, we started water injection by core spray system in addition to water injection by the reactor feed water system piping arrangement.
The current water injection amount from the reactor feed water system is approx 1.8m3/h and that from the core spray system is approx. 4.9m3/h.
-At 7:47 pm on June 30, 2011, we started cyclic cooling for the water in the spent fuel pool by an alternative cooling equipment of the Fuel Pool Cooling and Filtering System. (From 1:22 pm to 3:05 pm on March 22, we injected including hydrazine [corrosion inhibitor].)
-At 8:01 pm on July 14, 2011, injection of nitrogen gas into the Primary Containment Vessel started.
-At 4:26 pm on November 30, 2011, we started operation to inject nitrogen into the reactor pressure vessel.
-At 7:00 pm on March 14, 2012, the regular operation of the PCV gas control system started.
Unit 4 (Outage due to regular inspection)
-At around 6 am on March 15, 2011, we confirmed an explosive sound and the sustained damage around the 5th floor rooftop area of Reactor Building.
-At 12:44 pm on July 31, 2011, we started cyclic cooling for the water in the spent fuel pool by an alternative cooling equipment of the Fuel Pool Cooling and Filtering System.
-At 10:58 am on November 29, 2011, in order to decrease more salinity, we installed Ion exchange equipment and started the operation of such equipment.
-At this moment, we don't think there is any reactor coolant leakage inside the primary containment vessel.
Unit 5 (Outage due to regular inspection)
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 5:00 am on March 19, 2011, we started the Residual Heat Removal System Pump in order to cool the spent fuel pool.
-At 2:45 pm on July 15, 2011, we started the operation of the original Residual Heat Removal System (System B) by its original seawater pump.
-At 10:11 am on December 22, 2011, since we finished the recovery work of seawater pump (System B) of equipment water cooling system, we made a trial run. At 11:25 am on the same day, we confirmed no abnormalities and restarted the operation.
Unit 6 (Outage due to regular inspection)
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 10:14 pm on March 19, 2011, we started the Residual Heat Removal System Pump of Unit 6 to cool down Spent Fuel Pool.
-At 2:33 pm on September 15, 2011, we started separately cooling the reactor through the Residual Heat Removal System and the spent fuel pool through Equipment Cooling Water System and Fuel Pool Cooling System.
Others
-At around 10:00 am on June 13, 2011, we started the operation of the circulating seawater purification facility installed at the screen area of Unit 2 and 3.
-At 8:00 pm on June 17, 2011, we started operation of Water Treatment Facility against the accumulated water. At 6:00 pm on July 2, we started the circulating injection cooling to inject the water, which was treated by the accumulated water treatment system, to the reactors through the buffer tank.
-At 7:41 pm on August 19, 2011, we started treatment of accumulated water by parallel operation of one line from the cesium adsorption instrument to the decontamination instrument and the other treatment line of the cesium adsorption instrument No.2.
-At 2:06 pm on October 7, 2011, we started to spray purified accumulated water brought from Unit 5 and 6 continually in order to prevent dust scattering and potential fire outbreaks from the cut down trees.
-On October 28, 2011, we started installation of the water proof wall at the sea side, in front of the existing shore protection, Units 1-4, in order to contain marine pollution by underground water.
-At 12:25 pm on December 13, 2011, we started the re-circulating operation of desalination facility (reverse osmosis membrane type) for the purpose of suppression of condensed water after desalination treatment.
-At 10:14 am on March 20, we started transferring the accumulated water from the basement of Turbine Building of Unit 2 to the centralized radiation waste treatment facility (Miscellaneous Solid Waste Volume Reduction Treatment Building [High Temperature Incinerator Building]).
-At 8:41 am on March 19, we started transferring the accumulated water from the basement of the T/B, unit 3 to the Centralized Waste Treatment Facility (Miscellaneous Solid Waste Volume Reduction Treatment Building [High Temperature Incinerator Building]).
-From 10:00 am to 4:00 pm on March 22, regarding the water accumulated at the basement of T/B, Unit 6, we transferred to the temporary tank. At 10:00 am on March 23, 2012, we started transferring this accumulated water.
-When we were working the related thermometer of reactor pressure vessel / primary containment vessel of Unit 1, we found out that the signal cables of thermometer of VESSEL DOWN COMMER 130°(TE-263-69G2) has been connected not only the input of the correct recorder but also the input of VESSEL DOWN COMMER 15°(TE-263-69G1) and the signal cables of thermometer of VESSEL DOWN COMMER 15°(TE-263-69G1) has not been connected the input of the recorder. VESSEL DOWN COMMER 15°(TE-263-69G1) is monitor measuring instrument on the safety regulation (Article 138 and 143) but we confirmed that this thermometer was out of data in the past, so we excluded from monitor measuring instrument on the safety regulation (Article 138 and 143) after data collecting at 9:00 pm on March 22. We are monitoring by another thermometers according to the temperature monitoring of reactor pressure vessel.