Press Release (Mar 22,2012)
Completion of Transport of Spent Fuel from Unit 1, Kashiwazaki-Kariwa Nuclear Power Station

We have been transporting spent fuel from Unit 1 of Kashiwazaki-Kariwa Nuclear Power Station. Today, we have completed the transport as follows:

1. Date : March 22, 2012 15:27

2. Transport :  quantity BWR fuels 152 units · approx. 26 tonU
                       (Transportation container:NFT-38B type 4 casks)

3.Receiving facility : Japan Nuclear Fuel Limited  Spent fuel receiving・storage facility

4.Carrier : Rokueimaru

<Reference : Transport schedule>
(1)Kashiwazaki-Kariwa Nuclear Power Station Quay
   Arrival : March 20  6:50
   Start of loading : March 20 9:45
   Finish of loading : March 20 14:07
   Departure : March 20 15:50

(2)Port, spent fuel receiving・storage facility
   Arrival : March 22  7:45
   Start of loading : March 22 11:50
   Finish of loading : March 22 13:14
   Start of land transport : March 22 14:35
   End of land transport(Arrival in receiving facility) : March 22 15:27