search



Corporate Information

 
Press Release (Mar 18,2012)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, March 18)
 
*Updates from previous press release are underlined.
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1 (Shut down) 
- Explosive sound and white smoke were confirmed after the big quake
  occurred at 3:36 pm on March 12, 2011. It was assumed to be hydrogen
  explosion.
- At 3:37 pm on March 25, 2011, we started injecting freshwater to the
  reactor and are now injecting fresh water by a motor driven pump powered
  by the off-site transmission line. 
- At 10:11 am on December 10, 2011, in addition to water injection from
  water feeding system, we started water injection from piping of core
  spray system to the reactor.
  Current water injection amount from the reactor feed water system is
  approx. 4.7m3/h and that from the core spray system is approx. 1.6m3/h.
- At 1:31 am on April 7, 2011, we commenced injection of nitrogen gas into
  Primary Containment Vessel.
- At 11:22 am on August 10, 2011, we started cyclic cooling for the water
  in the spent fuel pool by an alternative cooling equipment of the Fuel
  Pool Cooling and Filtering System. 
- At 4:04 pm on November 30, 2011, we started operation to inject nitrogen
  into the reactor pressure vessel.
- At 6:00 pm on December 19, 2011, a full-scale operation of the PCV gas
  management system started.
Unit 2 (Shut down) 
- At approximately 6:00 am on March 15, 2011, an abnormal noise began
  emanating from nearby Pressure Suppression Chamber and the pressure
  within the chamber decreased. 
- At 10:10 am on March 26, 2011, we started injecting freshwater to the
  reactor and are now injecting fresh water by a motor driven pump powered
  by the off-site transmission line. 
- At 2:59 pm on September 14, 2011, in addition to water injection from
  feed water system, we started water injection from piping of core spray
  system to the reactor. 
  The current water injection amount from the reactor feed water system is
  approx. 2.7 m3/h and that from the core spray system is approx. 6.1m3/h.
- At 5:21 pm on May 31, 2011, we started cyclic cooling for the water in
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool
  Cooling and Filtering System. 
- At 8:06 pm on June 28, 2011, we started injecting nitrogen gas into the
  Primary Containment Vessel.
- At 6:00 pm on October 28, 2011, a full operation of the PCV gas control
  system started. On March 14, 
- At 10:46 am on December 1, 2011, we started the nitrogen injection to
  the Reactor Pressure Vessel.
- At 11:50 am on January 19, 2012, we started the operation of the spent
  fuel pool desalting facility.
Unit 3 (Shut down) 
- Explosive sound and white smoke were confirmed at approximately 11:01 am
  on March 14, 2011. It was assumed to be hydrogen explosion.
- At 6:02 pm on March 25, 2011, we started injecting fresh water to the
  reactor and are now injecting fresh water by a motor driven pump powered
  by the off-site transmission line.
- At 2:58 pm on September 1, 2011, we started water injection by core
  spray system in addition to water injection by the reactor feed water
  system piping arrangement. 
  The current water injection amount from the reactor feed water system is
  approx 1.9m3/h and that from the core spray system is approx. 4.9m3/h.
- At 7:47 pm on June 30, 2011, we started cyclic cooling for the water in
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool
  Cooling and Filtering System.
  At 9:38 am on March 18, 2012, such system and cooling of the pool was 
  temporarily suspended in order to implement the disassemble inspection 
  of valve in the primary coolant system (Temperature of the pool at the 
  time of the operation stoppage: approx. 15.0°C). The operation is 
  schedule to be under halt till March 21 and no major concern is expected 
  for the temperature of the pool (The temperature of the pool is expected 
  to increase approx 20°C during the stoppage).  
- At 8:01 pm on July 14, 2011, injection of nitrogen gas into the Primary
  Containment Vessel started. 
- At 4:26 pm on November 30, 2011, we started operation to inject nitrogen
  into the reactor pressure vessel.
- At 7:00 pm on March 14, 2012, the regular operation of the PCV gas
  control system started.
Unit 4 (Outage due to regular inspection) 
- At around 6 am on March 15, 2011, we confirmed the explosive sound and
  the sustained damage around the 5th floor rooftop area of Reactor
  Building.
- At 12:44 pm on July 31, 2011, we started cyclic cooling for the water in
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool
  Cooling and Filtering System. 
- At 10:58 am on November 29, 2011, in order to decrease more salinity, we
  installed Ion exchange equipment and started the operation of such
  equipment.
- At this moment, we don't think there is any reactor coolant leakage
  inside the primary containment vessel.
Unit 5 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, 2011, we started the Residual Heat Removal
  System Pump in order to cool the spent fuel pool.
- At 2:45 pm on July 15, 2011, we started the operation of the original
  Residual Heat Removal System (System B) by its original seawater pump.
- At 10:11 am on December 22, 2011, since we finished the recovery work of
  seawater pump (System B) of equipment water cooling system, we made a
  trial run. At 11:25 am on the same day, we confirmed no abnormalities
  and restarted the operation.
Unit 6 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, 2011, we started the Residual Heat Removal
  System Pump of Unit 6 to cool down Spent Fuel Pool.
- At 2:33 pm on September 15, 2011, we started separately cooling the
  reactor through the Residual Heat Removal System and the spent fuel pool
  through Equipment Cooling Water System and Fuel Pool Cooling System.
Others 
- At around 10:00 am on June 13, 2011, we started the operation of the
  circulating seawater purification facility installed at the screen area
  of Unit 2 and 3.
- At 8:00 pm on June 17, 2011, we started operation of Water Treatment
  Facility against the accumulated water. At 6:00 pm on July 2, we started
  the circulating injection cooling to inject the water, which was treated
  by the accumulated water treatment system, to the reactors through the
  buffer tank.
- At 7:41 pm on August 19, 2011, we started treatment of accumulated water
  by parallel operation of one line from the cesium adsorption instrument
  to the decontamination instrument and the other treatment line of the
  cesium adsorption instrument No.2.
- At 2:06 pm on October 7, 2011, we started to spray purified accumulated
  water brought from Unit 5 and 6 continually in order to prevent dust
  scattering and potential fire outbreaks from the cut down trees.
- On October 28, 2011, we started installation of the water proof wall at
  the sea side, in front of the existing shore protection, Units 1-4, in
  order to contain marine pollution by underground water.
- At 12:25 pm on December 13, 2011, we started the re-circulating
  operation of desalination facility (reverse osmosis membrane type) for
  the purpose of suppression of condensed water after desalination
  treatment.
- From 8:47 am on March 11, 2012 to 9:37 am on March 18, we transferred 
  the accumulated water from the basement of Turbine Building of Unit 2 to
  the centralized radiation waste treatment facility (Miscellaneous Solid
  Waste Volume Reduction Treatment Building [High Temperature Incinerator
  Building]).
- From 8:46 am on March 15, 2012 to 10:00 am on March 18, we transferred 
  the accumulated water from the basement floor of the turbine building of
  Unit 3 to the centralized radiation waste treatment facility
  (Miscellaneous Solid Waste Volume Reduction Treatment Building [High
  Temperature Incinerator Building]).
- At 10:13 am on March 18, 2012, we started transferring the accumulated 
  water from the basement of Turbine Building of Unit 2 to the centralized 
  radiation waste treatment facility process main building.  
back to page top


to TOP