search



Corporate Information

 
Press Release (Mar 16,2012)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, March 16)
 
*Updates from previous press release are underlined.
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1 (Shut down) 
-Explosive sound and white smoke were confirmed after the big quake 
 occurred at 3:36 pm on March 12, 2011. It was assumed to be hydrogen 
 explosion.
-At 3:37 pm on March 25, 2011, we started injecting freshwater to the 
 reactor and are now injecting fresh water by a motor driven pump powered 
 by the off-site transmission line. 
-At 10:11 am on December 10, 2011, in addition to water injection from 
 water feeding system, we started water injection from piping of core 
 spray system to the reactor.
 The current water injection amount from the reactor feed water system is 
 approx. 4.7 m3/h and that from the core spray system is approx. 1.7 m3/h.
-At 1:31 am on April 7, 2011, we commenced injection of nitrogen gas into 
 Primary Containment Vessel.
-At 11:22 am on August 10, 2011, we started cyclic cooling for the water 
 in the spent fuel pool by an alternative cooling equipment of the Fuel 
 Pool Cooling and Filtering System. 
-At 4:04 pm on November 30, 2011, we started operation to inject nitrogen 
 into the reactor pressure vessel.
-At 6:00 pm on December 19, 2011, a full-scale operation of the PCV gas 
 management system started.
Unit 2 (Shut down) 
-At approximately 6:00 am on March 15, 2011, an abnormal noise began 
 emanating from nearby Pressure Suppression Chamber and the pressure 
 within the chamber decreased. 
-At 10:10 am on March 26, 2011, we started injecting freshwater to the 
 reactor and are now injecting fresh water by a motor driven pump powered 
 by the off-site transmission line. 
-At 2:59 pm on September 14, 2011, in addition to water injection from 
 feed water system, we started water injection from piping of core spray 
 system to the reactor. 
 The current water injection amount from the reactor feed water system is 
 approx. 2.7 m3/h and that from the core spray system is approx. 6 m3/h.
-With regard to the water injection volume for Unit 2 reactor, which was 
 increased with temperature figure raising, we have gradually adjusted it 
 to the original volume before temperature increasing (Feed water system: 
 approx. 3.0m3/h, core spray system: approx. 6.0m3/h). During our 
 observing the plant parameter after decreasing the flow rate of feed 
 water system on February 22, we found that one thermometer in the lower 
 part of the RPV (top of the lower head 135°) indicated the different 
 movement from others. From 12:21 pm to 2:48 pm on February 23, we 
 investigated the concerned device. As the result of the measurement of DC 
 resistance, we found no breaking wire and availability of the thermometer. 
 But we confirmed that the DC resistance of it became higher than the 
 previous measurement test data. We will evaluate the soundness of the 
 concerned device and examine correspondence in future. We make sure no 
 re-criticality state because there were no significant changes at the 
 monitoring post and as the result of the sampling for the Gas Control 
 System of the Unit 2; we confirmed that the concentration of Xe-135 was 
 below the detectible limit. Through the investigation, we confirmed the 
 concerned device is soundness. We submitted the report on the soundness 
 of concerned device and the alternative method for monitoring temperature 
 inside the Reactor of Unit 2 at Fukushima Daiichi Nuclear Power Station 
 to NISA on March 1. We continue the observation of the concerned device.
 ·At 5:00 am on March 16, the temperature of the lower part of the RPV 
  (top of the lower head 135°) : approximately 40.8 °C 
 ·At 5:00 am on March 16, the temperature of the lower part of the RPV 
  (top of the lower head 270°) : approximately 41.1 °C (Reference)
-At 5:21 pm on May 31, 2011, we started cyclic cooling for the water in 
 the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-At 8:06 pm on June 28, 2011, we started injecting nitrogen gas into the 
 Primary Containment Vessel.
-At 6:00 pm on October 28, 2011, a full operation of the PCV gas control 
 system started. On March 14, 
-At 10:46 am on December 1, 2011, we started the nitrogen injection to the 
 Reactor Pressure Vessel.
-At 11:50 am on January 19, 2012, we started the operation of the spent 
 fuel pool desalting facility.
-At 10:31 am on March 13, 2012, because the suction pressure of the 
 primary system Circulating Water Pump had a tendency to decrease in the 
 substitute cooling system of spent fuel pool, we stopped the cooling of 
 spent fuel pool in order to change the primary system Strainer to manual 
 cleaning system and conduct the check of valves etc. until March 16. The 
 temperature rise on this period is expected approx. 21 °C. (Temperature 
 of water in spent fuel pool when we stopped: approx. 14.1 °C)
Unit 3 (Shut down) 
-Explosive sound and white smoke were confirmed at approximately 11:01 am 
 on March 14, 2011. It was assumed to be hydrogen explosion.
-At 6:02 pm on March 25, 2011, we started injecting fresh water to the 
 reactor and are now injecting fresh water by a motor driven pump powered 
 by the off-site transmission line.
-At 2:58 pm on September 1, 2011, we started water injection by core spray 
 system in addition to water injection by the reactor feed water system 
 piping arrangement. 
 The current water injection amount from the reactor feed water system is 
 approx 1.7 m3/h and that from the core spray system is approx. 5.4 m3/h.
-At 7:47 pm on June 30, 2011, we started cyclic cooling for the water in 
 the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System.
-At 8:01 pm on July 14, 2011, injection of nitrogen gas into the Primary 
 Containment Vessel started. 
-At 4:26 pm on November 30, 2011, we started operation to inject nitrogen 
 into the reactor pressure vessel.
-At 7:00 pm on March 14, 2012, the regular operation of the PCV gas 
 control system started.
Unit 4 (Outage due to regular inspection) 
-At around 6 am on March 15, 2011, we confirmed the explosive sound and 
 the sustained damage around the 5th floor rooftop area of Reactor 
 Building.
-At 12:44 pm on July 31, 2011, we started cyclic cooling for the water in 
 the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-At 10:58 am on November 29, 2011, in order to decrease more salinity, we 
 installed Ion exchange equipment and started the operation of such 
 equipment.
-At this moment, we don't think there is any reactor coolant leakage 
 inside the primary containment vessel.
Unit 5 (Outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 5:00 am on March 19, 2011, we started the Residual Heat Removal System 
 Pump in order to cool the spent fuel pool.
-At 2:45 pm on July 15, 2011, we started the operation of the original 
 Residual Heat Removal System (System B) by its original seawater pump.
-At 10:11 am on December 22, 2011, since we finished the recovery work of 
 seawater pump (System B) of equipment water cooling system, we made a 
 trial run. At 11:25 am on the same day, we confirmed no abnormalities and 
 restarted the operation.
Unit 6 (Outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 10:14 pm on March 19, 2011, we started the Residual Heat Removal 
 System Pump of Unit 6 to cool down Spent Fuel Pool.
-At 2:33 pm on September 15, 2011, we started separately cooling the 
 reactor through the Residual Heat Removal System and the spent fuel pool 
 through Equipment Cooling Water System and Fuel Pool Cooling System.
Others 
-At around 10:00 am on June 13, 2011, we started the operation of the 
 circulating seawater purification facility installed at the screen area 
 of Unit 2 and 3.
-At 8:00 pm on June 17, 2011, we started operation of Water Treatment 
 Facility against the accumulated water. At 6:00 pm on July 2, we started 
 the circulating injection cooling to inject the water, which was treated 
 by the accumulated water treatment system, to the reactors through the 
 buffer tank.
-At 7:41 pm on August 19, 2011, we started treatment of accumulated water 
 by parallel operation of one line from the cesium adsorption instrument 
 to the decontamination instrument and the other treatment line of the 
 cesium adsorption instrument No.2.
-At 2:06 pm on October 7, 2011, we started to spray purified accumulated 
 water brought from Unit 5 and 6 continually in order to prevent dust 
 scattering and potential fire outbreaks from the cut down trees.
-On October 28, 2011, we started installation of the water proof wall at 
 the sea side, in front of the existing shore protection, Units 1-4, in 
 order to contain marine pollution by underground water.
-At 12:25 pm on December 13, 2011, we started the re-circulating operation 
 of desalination facility (reverse osmosis membrane type) for the purpose 
 of suppression of condensed water after desalination treatment.
-At 8:47 am on March 11, 2012we started transferring the accumulated water 
 from the basement of Turbine Building of Unit 2 to the centralized 
 radiation waste treatment facility (Miscellaneous Solid Waste Volume 
 Reduction Treatment Building [High Temperature Incinerator Building]).
-At 8:46 am on March 15, 2012, we started transferring the accumulated 
 water from the basement floor of the turbine building of Unit 3 to the 
 centralized radiation waste treatment facility (Miscellaneous Solid Waste 
 Volume Reduction Treatment Building [High Temperature Incinerator 
 Building]).
-From 10:00 am to 4:00 pm on March 15, 2012, we transferred water from the 
 basement floor of the turbine building of Unit 6 to the temporary tank. 
 At 10:00 am on March 16, 2012, we resumed it. 
back to page top


to TOP