We are announcing the status of major inspections and restoration works
and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station
after the Niigata-Chuetsu-Oki Earthquake.
Inspection/Restoration Status
◇ Inspection and restoration completed between March 2 to March 8, 2012
(Completed on the following date)
- No notable activity during this week.
◇ Inspection and restoration to be commenced between March 9 to March 15,
2012
(To be commenced on the following date)
- No notable activity during this week.
◇ Work Schedule of Major Inspection and Restoration from March 4 to March
31, 2012
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) ...Appendix
◇ Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki
Earthquake; Grades GI, GII, GIII; and non-graded)
(including nonconformances related to: the Chuetsu-Oki Earthquake;
Grades As, A, B, C, D; and non-graded)
 |
* By close reexamination of past nonconformance incidents, 1 of them
is identified as not related to the Chuetsu-Oki Earthquake, so the
total number of them has been corrected.

Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) (PDF 15.5KB)