search



Corporate Information

 
Press Release (Feb 19,2012)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 11:00 am, February 19)
 *The updates are underlined 
 
 All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
 
 Unit 1 (Shut down) 
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12, 2011. It was assumed to be hydrogen 
  explosion. 
- At 3:37 pm on March 25, 2011, we started injecting freshwater to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
- At 10:11 am on December 10, 2011, in addition to water injection from 
  water feeding system, we started water injection from piping of core 
  spray system to the reactor. 
  The current water injection amount from the reactor feed water system is 
  approx. 4.5 m3/h and that from the core spray system is approx. 1.7 m3/h. 
- At 1:31 am on April 7, 2011, we commenced injection of nitrogen gas into 
  Primary Containment Vessel. 
- At 11:22 am on August 10, 2011, we started cyclic cooling for the water 
  in the spent fuel pool by an alternative cooling equipment of the Fuel 
  Pool Cooling and Filtering System. 
- On October 28, 2011, we completed installation of the cover for the 
  Reactor Building in order to contain dispersion of radioactive 
  substances. 
- At 4:04 pm on November 30, 2011, we started operation to inject nitrogen 
  into the reactor pressure vessel. 
- At 6:00 pm on December 19, 2011, a full-scale operation of the PCV gas 
  management system started. 
 
 Unit 2 (Shut down) 
- At approximately 6:00 am on March 15, 2011, an abnormal noise began 
  emanating from nearby Pressure Suppression Chamber and the pressure 
  within the chamber decreased. 
- At 10:10 am on March 26, 2011, we started injecting freshwater to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
- At 2:59 pm on September 14, 2011, in addition to water injection from 
  feed water system, we started water injection from piping of core spray 
  system to the reactor. 
  The current water injection amount from the reactor feed water system is 
  approx.7.6m3/h and that from the core spray system is approx.10 m3/h. 
- At 5:21 pm on May 31, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 7:05 am on February 18, within the Unit 2 SFP alternative cooling 
  system, an alarm sounded showing that the water flow difference was 
  large at the gateway of primary system pump and the system automatically 
  shutdown. After that, we confirmed there was no abnormalities such as 
  leakage at the location where the primary system shutdown. However, as 
  temperature decreased in the outer temperature, the secondary system 
  cooing water temperature also decreased and it may freeze, with a view 
  toward facility protection, we resumed it so as to prevent the primary 
  and secondary system from freezing. Upon resumption, we made sure there 
  was no leakage or parameter abnormalities, and by releasing the alarm at 
  11:54 pm on February 18, we activated the system. Since we do not see 
  any abnormalities, operation of the system is still continuing. 
- At 8:06 pm on June 28, 2011, we started injecting nitrogen gas into the 
  Primary Containment Vessel. 
- At 6:00 pm on October 28, 2011, a full-scale operation of the PCV gas 
  control system started. 
- At 10:46 am on December 1, 2011, we started the nitrogen injection to 
  the Reactor Pressure Vessel. 
- At 11:50 am on January 19, 2012, we started the operation of the spent 
  fuel pool desalting facility. 
- At around 5:00 am on February 8, the alarm which indicates the 
  abnormally low suction pressure of the high pressure RO pump in the 
  desalination apparatus of Unit 2 spent fuel pool went off and the device 
  was automatically shut down. The interlock closed all the isolation 
  valves in the system and the alternative cooling system for the spent 
  fuel pool was activated so there was no interruption to the cooling 
  process. We also confirmed that there was no leakage from the apparatus. 
  Due to the investigation afterwards we assumed that an instantaneous 
  fall in the pressure had caused this shut down. After we confirmed that 
  certain measures have been taken to prevent this we restarted the 
  operation at 3:20 pm of February 18, but at 7:05 pm on the same day 
  another alarm which indicates that the difference of the water flow 
  between the entrance and the exit of the primary line pump of the 
  substitutive cooling system of the spent fuel pool of unit 2 went off 
  and the system shut had down automatically. Due to this the desalting 
  facility has also shut down, but later we reactivated the system and at 
  10:44 am on February 19 we restarted the operation of the desalting 
  facility. 
 
 Unit 3 (Shut down) 
- Explosive sound and white smoke were confirmed at approximately 11:01 am 
  on March 14, 2011. It was assumed to be hydrogen explosion. 
- At 6:02 pm on March 25, 2011, we started injecting fresh water to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
- At 2:58 pm on September 1, 2011, we started water injection by core 
  spray system in addition to water injection by the reactor feed water 
  system piping arrangement. 
- On 9:57 am on February 19, with regard to the water injection volume 
  for Unit 3 reactor, as there was latitude of the current water injection 
  volume against the equivalent decay heat, for the purpose of reducing 
  the transfer and treatment works of the increased accumulated water due 
  to the increase in water injection to Unit 2, we changed the water 
  injection volume by feed water system from approx. 3.0 m3/h to 2.0 m3/h. 
  (The water injection level from reactor core system is continuing at 5.0 
   m3/h.) 
  The current water injection amount from the reactor feed water system is 
  approx. 2 m3/h and that from the core spray system is approx. 5 m3/h. 
- At 7:47 pm on June 30, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 8:01 pm on July 14, 2011, injection of nitrogen gas into the Primary 
  Containment Vessel started. 
- At 4:26 pm on November 30, 2011, we started operation to inject nitrogen 
  into the reactor pressure vessel. 
- At 3:18 pm on January 14, we started operation of the radioactive 
  material removal instrument for the spent fuel pool in Unit 3 
 
 Unit 4 (Outage due to regular inspection) 
- At around 6 am on March 15, 2011, we confirmed the explosive sound and 
  the sustained damage around the 5th floor rooftop area of Reactor 
  Building. 
- At 12:44 pm on July 31, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 10:58 am on November 29, 2011, in order to decrease more salinity, we 
  installed Ion exchange equipment and started the operation of such 
  equipment. 
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel. 
 
 Unit 5 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained. 
- At 5:00 am on March 19, 2011, we started the Residual Heat Removal 
  System Pump in order to cool the spent fuel pool. 
- At 2:45 pm on July 15, 2011, we started the operation of the original 
  Residual Heat Removal System (System B) by its original seawater pump. 
- At 10:11 am on December 22, 2011, since we finished the recovery work of 
  seawater pump (System B) of equipment water cooling system, we made a 
  trial run. At 11:25 am on the same day, we confirmed no abnormalities 
  and restarted the operation. 
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel. 
 
 Unit 6 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained. 
- At 10:14 pm on March 19, 2011, we started the Residual Heat Removal 
  System Pump of Unit 6 to cool down Spent Fuel Pool. 
- At 2:33 pm on September 15, 2011, we started separately cooling the 
  reactor through the Residual Heat Removal System and the spent fuel pool 
  through Equipment Cooling Water System and Fuel Pool Cooling System. 
 
 Others 
- At around 10:00 am on June 13, 2011, we started the operation of the 
  circulating seawater purification facility installed at the screen area 
  of Unit 2 and 3. 
- At 8:00 pm on June 17, 2011, we started operation of Water Treatment 
  Facility against the accumulated water. At 6:00 pm on July 2, we started 
  the circulating injection cooling to inject the water, which was treated 
  by the accumulated water treatment system, to the reactors through the 
  buffer tank. 
- At 7:41 pm on August 19, 2011, we started treatment of accumulated water 
  by parallel operation of one line from the cesium adsorption instrument 
  to the decontamination instrument and the other treatment line of the 
  cesium adsorption instrument No.2. 
- At 2:06 pm on October 7, 2011, we started to spray purified accumulated 
  water brought from Unit 5 and 6 continually in order to prevent dust 
  scattering and potential fire outbreaks from the cut down trees. 
- On October 28, 2011, we started installation of the water proof wall at 
  the sea side, in front of the existing shore protection, Units 1-4, in 
  order to contain marine pollution by underground water. 
- At 12:25 pm on December 13, 2011, we started the re-circulating 
  operation of desalination facility (reverse osmosis membrane type) for 
  the purpose of suppression of condensed water after desalination 
  treatment. 
- At 9:18 am on January 31, we started transfer of Sub-drain Water of Unit 
  6 to the temporary tank. We will conduct transferring to the temporary 
  tank appropriately. 
- At 2:43 pm on February 10, we started to transfer accumulated water from 
  underground floor of turbine building of Unit 2 to centralized radiation 
  waste treatment facility (Miscellaneous Solid Waste Volume Reduction 
  Treatment Building [High Temperature Incinerator Building]). 
- From 10:00 am to 4:00 pm on February 18, we transferred accumulated 
  water from the turbine building of Unit 6 to the temporary tank. 
- At 10:00 am on February 19, as for the accumulated water at the Unit 6 
  Turbine Building basement, transfer to the temporary tank commenced.  
back to page top


to TOP