search



Corporate Information

 
Press Release (Feb 17,2012)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, February 17)
 *The updates are underlined 
 
 All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
 
 Unit 1 (Shut down) 
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12, 2011. It was assumed to be hydrogen 
  explosion. 
- At 3:37 pm on March 25, 2011, we started injecting freshwater to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
- At 10:11 am on December 10, 2011, in addition to water injection from 
  water feeding system, we started water injection from piping of core 
  spray system to the reactor. 
  The current water injection amount from the reactor feed water system is 
  approx. 4.3 m3/h and that from the core spray system is approx. 1.7 m3/h. 
- At 1:31 am on April 7, 2011, we commenced injection of nitrogen gas into 
  Primary Containment Vessel. 
- At 11:22 am on August 10, 2011, we started cyclic cooling for the water 
  in the spent fuel pool by an alternative cooling equipment of the Fuel 
  Pool Cooling and Filtering System. 
- On October 28, 2011, we completed installation of the cover for the 
  Reactor Building in order to contain dispersion of radioactive 
  substances. 
- At 4:04 pm on November 30, 2011, we started operation to inject nitrogen 
  into the reactor pressure vessel. 
- At 6:00 pm on December 19, 2011, a full-scale operation of the PCV gas 
  management system started. 
 
 Unit 2 (Shut down) 
- At approximately 6:00 am on March 15, 2011, an abnormal noise began 
  emanating from nearby Pressure Suppression Chamber and the pressure 
  within the chamber decreased. 
- At 10:10 am on March 26, 2011, we started injecting freshwater to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
  At 2:59 pm on September 14, 2011, in addition to water injection from 
  feed water system, we started water injection from piping of core spray 
  system to the reactor. 
  The current water injection amount from the reactor feed water system is 
  approx.7.7m3/h and that from the core spray system is approx.10 m3/h. 
- At 5:21 pm on May 31, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 8:06 pm on June 28, 2011, we started injecting nitrogen gas into the 
  Primary Containment Vessel. 
- At 6:00 pm on October 28, 2011, a full-scale operation of the PCV gas 
  control system started. 
- At 10:46 am on December 1, 2011, we started the nitrogen injection to 
  the Reactor Pressure Vessel. 
- At 11:50 am on January 19, 2012, we started the operation of the spent 
  fuel pool desalting facility. 
- Because the tendency of temperature rise at the bottom of the PCV had 
  been accelerated since February 2 and it continued, we have increased 
  the amount of water injection to the reactor since 14:10 on February 12.*1 
  We confirmed that the meter indicated 82°C exceeding 80°C which is the 
  maximum temperature limit at the bottom of the PCV for the safety 
  operation defined in the safety regulation*2 and evaluated that it 
  violated the regulation at 14:20 on February 12. In order to satisfy the 
  limit of the safety operation, we increased the amount of water 
  injection. After the countermeasure was taken, the temperature continued 
  to rise and we conducted an investigation of the meter which monitors 
  the temperature at the bottom of the PCV. As a result of the 
  investigation, we evaluated that the thermocouple has been out of order 
  due to disconnection, because the DC resistance was higher than normal 
  level. After the inspection of the soundness of thermocouple, we 
  evaluated that it has been out of order. At 2:00 pm on February 17, we 
  evaluated that the temperature at the bottom of the PCV was not actually 
  risen and it didn't exceed the limit of the safety operation. Our 
  evaluation of violation of the safety operation was corrected 
  retroactive to February 12. The meter was deleted from the list of the 
  meters to monitor the temperature of the bottom of the PVC. The 
  temperature is monitored with the other meters. 
*1) Based on the management of facilities stipulated at the Article 12 
    "Mid-term safety securing" of Act of the Regulation of Nuclear Source 
    Material, Nuclear Fuel Material and Reactors, it provides "Operational 
    Limit" and "measures required in the case that does not satisfy the 
    Operational Limit", it is required to respond based on the measures 
    required in the case that does not satisfy the Operational Limit. In 
    our case, in order to implement the preservation work, it was shifted 
    to outside of operational limit condition[the rate of the increase in 
    the water injection volume is less than 1.0m3/h in any 24 hour period] 
    as planned (from 1:55 pm on February 12), we changed the water 
    injection amount into the reactor of Unit 2. At 2:00 pm, we judged 
    that it was not satisfied "the temperature is below 80 °C at the 
    bottom of PCV", which is stipulated in "the Reactor Facility safety 
    Regulation" as one of the "Conditions of operation". We continue to 
    change the water injection amount accordingly. 
*2) Reactor Facility Safety Regulation provides necessary conditions such 
    as the numbers of the permitted machines etc. or criteria of 
    temperatures and pressures for securing multiple safety function for 
    operating reactors and for keeping nuclear power stations stable and 
    these are treated as conditions for operation. When there happen some 
    malfunctions of equipment provided in the regulation and a nuclear 
    power station can not clear the conditions temporarily, operators have 
    to take required countermeasures. 
 
 Unit 3 (Shut down) 
- Explosive sound and white smoke were confirmed at approximately 11:01 am 
  on March 14, 2011. It was assumed to be hydrogen explosion. 
- At 6:02 pm on March 25, 2011, we started injecting fresh water to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
- At 2:58 pm on September 1, 2011, we started water injection by core 
  spray system in addition to water injection by the reactor feed water 
  system piping arrangement. 
  At 11:33am on February 17, since the current amount of the water 
  injection has enough margin against the water injection for decay heat, 
  the water injection from the core spray system has been reduced from 
  approx. 6.0m3/h to approx. 5.0m3/h in order to alleviate transfer and 
  treatment of accumulated water increased by the water injection increase 
  into Unit 2. And we confirmed the change of the water injection. The 
  water from the reactor feed water system was adjusted from approx. 
  2.9m3/h to approx. 3.0m3/h. 
  The current water injection amount from the reactor feed water system is 
  approx. 3 m3/h and that from the core spray system is approx. 5 m3/h. 
  At 7:47 pm on June 30, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 8:01 pm on July 14, 2011, injection of nitrogen gas into the Primary 
  Containment Vessel started. 
  Since 9:50 am on February 10, we have conducted the work to add flow 
  meters to the nitrogen injection line at the side of Primary Containment 
  Vessel of Unit 3 in order to improve the reliability of nitrogen 
  injection activity. During this period, due to this work, we suspended 
  the nitrogen injection task temporarily. 
- At 4:26 pm on November 30, 2011, we started operation to inject nitrogen 
  into the reactor pressure vessel. 
- At 3:18 pm on January 14, we started operation of the radioactive 
  material removal instrument for the spent fuel pool in Unit 3 
 
 Unit 4 (Outage due to regular inspection) 
- At around 6 am on March 15, 2011, we confirmed the explosive sound and 
  the sustained damage around the 5th floor rooftop area of Reactor 
  Building. 
- At 12:44 pm on July 31, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 10:58 am on November 29, 2011, in order to decrease more salinity, we 
  installed Ion exchange equipment and started the operation of such 
  equipment. 
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel. 
 
 Unit 5 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained. 
- At 5:00 am on March 19, 2011, we started the Residual Heat Removal 
  System Pump in order to cool the spent fuel pool. 
- At 2:45 pm on July 15, 2011, we started the operation of the original 
  Residual Heat Removal System (System B) by its original seawater pump. 
- At 10:11 am on December 22, 2011, since we finished the recovery work of 
  seawater pump (System B) of equipment water cooling system, we made a 
  trial run. At 11:25 am on the same day, we confirmed no abnormalities 
  and restarted the operation. 
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel. 
 
 Unit 6 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained. 
- At 10:14 pm on March 19, 2011, we started the Residual Heat Removal 
  System Pump of Unit 6 to cool down Spent Fuel Pool. 
- At 2:33 pm on September 15, 2011, we started separately cooling the 
  reactor through the Residual Heat Removal System and the spent fuel pool 
  through Equipment Cooling Water System and Fuel Pool Cooling System. 
- In order to conduct inspection of the strainer changeover valve of the 
  pump of the reactor sea water system of Unit 6 from February 14 to 
  February 17, at 10:02 am on February 14, we stopped cooling of the spent 
  fuel pool by the spent fuel pool cooling system (B) and at 10:06 am on 
  the same day, we stopped the pump of the reactor sea water system (A) 
  (spent fuel pool water temperature during the stoppage: approx. 23°C). 
  Because the spent fuel pool cooling system isn't in operation during the 
  inspection, we conduct alternating cooling of the reactor and the spent 
  fuel pool by the residual heat removal system. At 2:07pm on February 17, 
  since the inspection was completed ,the auxiliary cooling seawater 
  system pump (A) was activated. At 2:53pm on the same day, we restarted 
  the cooling of the spent fuel pool by the spent fuel pool cooling system 
  (B) and the system was back to the normal operating condition. (The 
  maximum temperature during alternate cooling period :Reactor Water: 
  33.6°C, Spent Fuel Pool Water: 29°C). 
 
 Others 
- At around 10:00 am on June 13, 2011, we started the operation of the 
  circulating seawater purification facility installed at the screen area 
  of Unit 2 and 3. 
- At 8:00 pm on June 17, 2011, we started operation of Water Treatment 
  Facility against the accumulated water. At 6:00 pm on July 2, we started 
  the circulating injection cooling to inject the water, which was treated 
  by the accumulated water treatment system, to the reactors through the 
  buffer tank. 
- At 7:41 pm on August 19, 2011, we started treatment of accumulated water 
  by parallel operation of one line from the cesium adsorption instrument 
  to the decontamination instrument and the other treatment line of the 
  cesium adsorption instrument No.2. 
- At 2:06 pm on October 7, 2011, we started to spray purified accumulated 
  water brought from Unit 5 and 6 continually in order to prevent dust 
  scattering and potential fire outbreaks from the cut down trees. 
- On October 28, 2011, we started installation of the water proof wall at 
  the sea side, in front of the existing shore protection, Units 1-4, in 
  order to contain marine pollution by underground water. 
- At 12:25 pm on December 13, 2011, we started the re-circulating 
  operation of desalination facility (reverse osmosis membrane type) for 
  the purpose of suppression of condensed water after desalination 
  treatment. 
- At 9:18 am on January 31, we started transfer of Sub-drain Water of Unit 
  6 to the temporary tank. We will conduct transferring to the temporary 
  tank appropriately. 
- At 2:43 pm on February 10, we started to transfer accumulated water from 
  underground floor of turbine building of Unit 2 to centralized radiation 
  waste treatment facility (Miscellaneous Solid Waste Volume Reduction 
  Treatment Building [High Temperature Incinerator Building]). 
- At 8:46 am on February 17, since the treatment capacity of the 2nd 
  Cesium adsorption apparatus was declining gradually, we stopped it and 
  cleaned the filters. At 10:59 am on the same day, we started this 
  apparatus, at 11:05 am ,we confirmed steady flow quantity (36.4 m3/h). 
- At 10:00 am on February 17, we started to transfer accumulated water 
  from underground floor of turbine building of Unit 6 to the temporary 
  tank.  
back to page top


to TOP