*The updates are underlined
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1 (Shut down)
- Explosive sound and white smoke were confirmed after the big quake
occurred at 3:36 pm on March 12, 2011. It was assumed to be hydrogen
explosion.
- At 3:37 pm on March 25, 2011, we started injecting freshwater to the
reactor and are now injecting fresh water by a motor driven pump powered
by the off-site transmission line.
- At 10:11 am on December 10, 2011, in addition to water injection from
water feeding system, we started water injection from piping of core
spray system to the reactor.
The current water injection amount from the reactor feed water system is
approx.4.4 m3/h and that from the core spray system is approx. 1.8 m3/h.
- At 1:31 am on April 7, 2011, we commenced injection of nitrogen gas into
Primary Containment Vessel.
- At 11:22 am on August 10, 2011, we started cyclic cooling for the water
in the spent fuel pool by an alternative cooling equipment of the Fuel
Pool Cooling and Filtering System.
- On October 28, 2011, we completed installation of the cover for the
Reactor Building in order to contain dispersion of radioactive
substances.
- At 4:04 pm on November 30, 2011, we started operation to inject nitrogen
into the reactor pressure vessel.
- At 6:00 pm on December 19, 2011, a full-scale operation of the PCV gas
management system started.
Unit 2 (Shut down)
- At approximately 6:00 am on March 15, 2011, an abnormal noise began
emanating from nearby Pressure Suppression Chamber and the pressure
within the chamber decreased.
- At 10:10 am on March 26, 2011, we started injecting freshwater to the
reactor and are now injecting fresh water by a motor driven pump powered
by the off-site transmission line.
- At 2:59 pm on September 14, 2011, in addition to water injection from
feed water system, we started water injection from piping of core spray
system to the reactor.
Because the tendency of temperature rise at the bottom of PCV had been
accelerated since February 2, we increased the amount of water injected
to the reactor and continued monitoring the tendency of the temperature
fluctuation. Since the temperature increased slightly, at 3:30 pm on
February 12, 2012, we changed the water injection amount through the
reactor feed water system from approx. 7.2m3/h to 7.5m3/h and the water
injection amount through the core spray system from approx. 6.9m3/h to
9.9m3/h. At 5:01 pm on February 12, we sampled the gas of the gas
control system of Unit 2 Primary Containment Vessel. The density of
Xenon 135 at the entrance of the system was below the detection limit
(9.3X10-2Bq/cm3). Since it is below 1Bq/cm3, which is the threshold for
judging re-criticality, we confirmed the reactor didn't go re-critical.
After that, since we confirmed a change in the amount of water injection
to the Unit 2 nuclear reactor, at 7:30 pm on February 12, we changed the
amount of the water injection from the feed water system from 7.1m3/h to
7.5m3/h and water injection from the core spray system from 10.0m3/h to
9.9m3/h. Later we again confirmed a change in the amount of water
injection to the Unit 2 nuclear reactor, and at 9:50 am on February 13,
we changed the amount of the water injection from the feed water system
from 7.0m3/h to 7.5m3/h (water injection from the core spray system
maintained at 9.9m3/h).
Currently, the temperature is approx. 93.3 °C (reference) as of 1:00 pm
on February 13. We are now investigating the measuring instrument. We
will continue to monitor the tendency of the temperature.
The current water injection amount from the reactor feed water system is
approx. 7.5 m3/h and that from the core spray system is approx. 9.9 m3/h.
- At 5:21 pm on May 31, 2011, we started cyclic cooling for the water in
the spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System. At 1:29 pm on February 13, we started
injection of hydrazine [corrosion inhibitor].
- At 8:06 pm on June 28, 2011, we started injecting nitrogen gas into the
Primary Containment Vessel.
- At 6:00 pm on October 28, 2011, a full-scale operation of the PCV gas
control system started.
- At 10:46 am on December 1, 2011, we started the nitrogen injection to
the Reactor Pressure Vessel.
- At 11:50 am on January 19, 2012, we started the operation of the spent
fuel pool desalting facility.
Unit 3 (Shut down)
- Explosive sound and white smoke were confirmed at approximately 11:01 am
on March 14, 2011. It was assumed to be hydrogen explosion.
- At 6:02 pm on March 25, 2011, we started injecting fresh water to the
reactor and are now injecting fresh water by a motor driven pump powered
by the off-site transmission line.
- At 2:58 pm on September 1, 2011, we started water injection by core
spray system in addition to water injection by the reactor feed water
system piping arrangement.
The current water injection amount from the reactor feed water system is
approx. 3 m3/h and that from the core spray system is approx. 6 m3/h.
At 7:47 pm on June 30, 2011, we started cyclic cooling for the water in
the spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
At 10:07 am on February 8, we stopped the operation of the secondary
cooling tower in order to prevent overcooling of alternative cooling
system of spent fuel pool of Unit 3. Afterward the temperature of the
water of the pool was increased so we operate the secondary cooling
tower at 10:08 am on February 13.
- At 8:01 pm on July 14, 2011, injection of nitrogen gas into the Primary
Containment Vessel started.
Since 9:50 am on February 10, we have conducted the work to add
flowmeters to the nitrogen injection line at the side of Primary
Containment Vessel of Unit 3 in order to improve the reliability of
nitrogen injection activity. During this period, due to this work, we
suspended the nitrogen injection task temporarily.
- At 4:26 pm on November 30, 2011, we started operation to inject nitrogen
into the reactor pressure vessel.
- At 3:18 pm on January 14, we started operation of the radioactive
material removal instrument for the spent fuel pool in Unit 3
Unit 4 (Outage due to regular inspection)
- At around 6 am on March 15, 2011, we confirmed the explosive sound and
the sustained damage around the 5th floor rooftop area of Reactor
Building.
- At 12:44 pm on July 31, 2011, we started cyclic cooling for the water in
the spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
- At 10:58 am on November 29, 2011, in order to decrease more salinity, we
installed Ion exchange equipment and started the operation of such
equipment.
- At this moment, we don't think there is any reactor coolant leakage
inside the primary containment vessel.
Unit 5 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, 2011, we started the Residual Heat Removal
System Pump in order to cool the spent fuel pool.
- At 2:45 pm on July 15, 2011, we started the operation of the original
Residual Heat Removal System (System B) by its original seawater pump.
- At 10:11 am on December 22, 2011, since we finished the recovery work of
seawater pump (System B) of equipment water cooling system, we made a
trial run. At 11:25 am on the same day, we confirmed no abnormalities
and restarted the operation.
- At this moment, we don't think there is any reactor coolant leakage
inside the primary containment vessel.
Unit 6 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, 2011, we started the Residual Heat Removal
System Pump of Unit 6 to cool down Spent Fuel Pool.
- At 2:33 pm on September 15, 2011, we started separately cooling the
reactor through the Residual Heat Removal System and the spent fuel pool
through Equipment Cooling Water System and Fuel Pool Cooling System.
- At this moment, we do not think there is any reactor coolant leakage
inside PCV.
Others
- At around 10:00 am on June 13, 2011, we started the operation of the
circulating seawater purification facility installed at the screen area
of Unit 2 and 3.
- At 8:00 pm on June 17, 2011, we started operation of Water Treatment
Facility against the accumulated water. At 6:00 pm on July 2, we started
the circulating injection cooling to inject the water, which was treated
by the accumulated water treatment system, to the reactors through the
buffer tank.
- At 7:41 pm on August 19, 2011, we started treatment of accumulated water
by parallel operation of one line from the cesium adsorption instrument
to the decontamination instrument and the other treatment line of the
cesium adsorption instrument No.2.
- At 2:06 pm on October 7, 2011, we started to spray purified accumulated
water brought from Unit 5 and 6 continually in order to prevent dust
scattering and potential fire outbreaks from the cut down trees.
- On October 28, 2011, we started installation of the water proof wall at
the sea side, in front of the existing shore protection, Units 1-4, in
order to contain marine pollution by underground water.
- At 12:25 pm on December 13, 2011, we started the re-circulating
operation of desalination facility (reverse osmosis membrane type) for
the purpose of suppression of condensed water after desalination
treatment.
- As accumulated water containing radioactive materials was found in the
trench between Process Main Building and Miscellaneous Solid Waste
Volume Reduction Treatment Building (High Temperature Incinerator
Building) in Centralized Radiation Waste Treatment Facility (December 18,
2011), inspection of other trenches in the site was commenced from
January 11.
- At 9:18 am on January 31, we started transfer of Sub-drain Water of Unit
6 to the temporary tank. We will conduct transferring to the temporary
tank appropriately.
- At 2:43 pm on February 10, we started to transfer accumulated water from
underground floor of turbine building of Unit 2 to centralized radiation
waste treatment facility (Miscellaneous Solid Waste Volume Reduction
Treatment Building [High Temperature Incinerator Building]).
- At 9:57 am on February 12, we started to transfer accumulated water in
the underground of turbine building of Unit 3 to the Centralized
Radiation Waste Treatment Facility (Process Main Building).