search



Corporate Information

 
Press Release (Feb 12,2012)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:30 pm, February 12)
*The updates are underlined
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1 (Shut down) 
-Explosive sound and white smoke were confirmed after the big quake 
 occurred at 3:36 pm on March 12, 2011. It was assumed to be hydrogen 
 explosion.
-At 3:37 pm on March 25, 2011, we started injecting freshwater to the 
 reactor and are now injecting fresh water by a motor driven pump powered 
 by the off-site transmission line. 
-At 10:11 am on December 10, 2011, in addition to water injection from 
 water feeding system, we started water injection from piping of core 
 spray system to the reactor.
 The current water injection amount from the reactor feed water system is 
 approx.4.5 m3/h and that from  the core spray system is approx. 1.9 m3/h.
-At 1:31 am on April 7, 2011, we commenced injection of nitrogen gas into 
 Primary Containment Vessel.
-At 11:22 am on August 10, 2011, we started cyclic cooling for the water 
 in the spent fuel pool by an alternative cooling equipment of the Fuel 
 Pool Cooling and Filtering System. 
-On October 28, 2011, we completed installation of the cover for the 
 Reactor Building in order to contain dispersion of radioactive substances.
-At 4:04 pm on November 30, 2011, we started operation to inject nitrogen 
 into the reactor pressure vessel.
-At 6:00 pm on December 19, 2011, a full-scale operation of the PCV gas 
 management system started.
Unit 2 (Shut down) 
-At approximately 6:00 am on March 15, 2011, an abnormal noise began 
 emanating from nearby Pressure Suppression Chamber and the pressure 
 within the chamber decreased. 
-At 10:10 am on March 26, 2011, we started injecting freshwater to the 
 reactor and are now injecting fresh water by a motor driven pump powered 
 by the off-site transmission line. 
-At 2:59 pm on September 14, 2011, in addition to water injection from 
 feed water system, we started water injection from piping of core spray 
 system to the reactor. 
 Because the tendency of temperature rise at the bottom of PCV had been 
 accelerated since February 2, we increased the amount of water injected 
 to the reactor and continued monitoring the tendency of the temperature 
 fluctuation. Since the temperature increased slightly, at 10:45 pm on 
 February 11, 2012, we changed the water injection amount through the 
 reactor feed water system from approx. 6.8m3/h to 7.8m3/h (the water 
 injection amount through the core spray system is kept at approx. 6.8m3/h). 
 On February 12, 2012, we conducted a sampling of gas in the gas management 
 system in the Primary Containment Vessel of Unit 2 and the result is that 
 around the entry of the system, Xe-135 was below the detection limit 
 (9.5 x 10-2 Bq/cm3). As it is below 1 Bq/cm3, the criterion to judge 
 re-criticality, we have confirmed that it has not reached re-criticality. 
 After that, we continued monitoring the tendency of the temperature 
 fluctuation, and then found that the temperature at the bottom of PCV 
 tended to be still high. Therefore, in order to avoid a chance of the 
 re-criticality due to the increase of water density in the PCV by sudden 
 cold water injection, from 11:38 am to 1:50 pm on February 12, before 
 starting water flow rate change, we injected boric acid into the reactor 
 for the safety measures. Then, from 2:10 pm on the same day, although we 
 increased the water injection rate, the indicated temperature of the 
 bottom of PCV was confirmed to be 82°C beyond 80°C so that, At 2:20 pm, 
 we judged that it was not satisfied "the temperature is below 80°C at 
 the bottom of PCV *1", which is stipulated in "the Reactor Facility 
 safety Regulation *2" as one of the "Conditions of operation". Thereafter, 
 we continued the increased water injection, and changed the water flow 
 rate from approx. 7.2m3/h to 7.5m3/h through the reactor feed water 
 system, and from approx. 6.9m3/h to 9.9m3/h through the core spray system. 
 Currently, the temperature is approx. 79.2°C as of 3:00 pm on February 
 12 for reference. We continue to monitor the tendency of the temperature. 
 The current water injection amount from the reactor feed water system is 
 approx. 7.5 m3/h and that from the core spray system is approx. 9.9 m3/h.
-At 5:21 pm on May 31, 2011, we started cyclic cooling for the water in 
 the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-At 8:06 pm on June 28, 2011, we started injecting nitrogen gas into the 
 Primary Containment Vessel.
-At 6:00 pm on October 28, 2011, a full-scale operation of the PCV gas 
 control system started. 
-At 10:46 am on December 1, 2011, we started the nitrogen injection to the 
 Reactor Pressure Vessel.
-At 11:50 am on January 19, 2012, we started the operation of the spent 
 fuel pool desalting facility.
Unit 3 (Shut down) 
-Explosive sound and white smoke were confirmed at approximately 11:01 am 
 on March 14, 2011. It was assumed to be hydrogen explosion.
-At 6:02 pm on March 25, 2011, we started injecting fresh water to the 
 reactor and are now injecting fresh water by a motor driven pump powered 
 by the off-site transmission line.
-At 2:58 pm on September 1, 2011, we started water injection by core spray 
 system in addition to water injection by the reactor feed water system 
 piping arrangement.
 The current water injection amount from the reactor feed water system is 
 approx. 2.9 m3/h and that from the core spray system is approx. 6.1 m3/h.
 At 7:47 pm on June 30, 2011, we started cyclic cooling for the water in 
 the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-At 8:01 pm on July 14, 2011, injection of nitrogen gas into the Primary 
 Containment Vessel started. 
 Since 9:50 am on February 10, we have conducted the work to add 
 flowmeters to the nitrogen injection line at the side of Primary 
 Containment Vessel of Unit 3 in order to improve the reliability of 
 nitrogen injection activity. During this period, due to this work, we 
 suspended the nitrogen injection task temporarily.
-At 4:26 pm on November 30, 2011, we started operation to inject nitrogen 
 into the reactor pressure vessel.
-At 3:18 pm on January 14, we started operation of the radioactive 
 material removal instrument for the spent fuel pool in Unit 3.
Unit 4 (Outage due to regular inspection) 
-At around 6 am on March 15, 2011, we confirmed the explosive sound and 
 the sustained damage around the 5th floor rooftop area of Reactor 
 Building.
-At 12:44 pm on July 31, 2011, we started cyclic cooling for the water in 
 the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-At 10:58 am on November 29, 2011, in order to decrease more salinity, we 
 installed Ion exchange equipment and started the operation of such 
 equipment.
-At this moment, we don't think there is any reactor coolant leakage 
 inside the primary containment vessel.
Unit 5 (Outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 5:00 am on March 19, 2011, we started the Residual Heat Removal System 
 Pump in order to cool the spent fuel pool.
-At 2:45 pm on July 15, 2011, we started the operation of the original 
 Residual Heat Removal System (System B) by its original seawater pump.
-At 10:11 am on December 22, 2011, since we finished the recovery work of 
 seawater pump (System B) of equipment water cooling system, we made a 
 trial run. At 11:25 am on the same day, we confirmed no abnormalities and 
 restarted the operation.
-At this moment, we don't think there is any reactor coolant leakage 
 inside the primary containment vessel.
Unit 6 (Outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 10:14 pm on March 19, 2011, we started the Residual Heat Removal System 
 Pump of Unit 6 to cool down Spent Fuel Pool.
-At 2:33 pm on September 15, 2011, we started separately cooling the 
 reactor through the Residual Heat Removal System and the spent fuel pool 
 through Equipment Cooling Water System and Fuel Pool Cooling System.
-At this moment, we do not think there is any reactor coolant leakage 
 inside PCV.
Others 
-At around 10:00 am on June 13, 2011, we started the operation of the 
 circulating seawater purification facility installed at the screen area 
 of Unit 2 and 3.
-At 8:00 pm on June 17, 2011, we started operation of Water Treatment 
 Facility against the accumulated water. At 6:00 pm on July 2, we started 
 the circulating injection cooling to inject the water, which was treated 
 by the accumulated water treatment system, to the reactors through the 
 buffer tank.
-At 7:41 pm on August 19, 2011, we started treatment of accumulated water 
 by parallel operation of one line from the cesium adsorption instrument 
 to the decontamination instrument and the other treatment line of the 
 cesium adsorption instrument No.2.
-At 2:06 pm on October 7, 2011, we started to spray purified accumulated 
 water brought from Unit 5 and 6 continually in order to prevent dust 
 scattering and potential fire outbreaks from the cut down trees.
-On October 28, 2011, we started installation of the water proof wall at 
 the sea side, in front of the existing shore protection, Units 1-4, in 
 order to contain marine pollution by underground water.
-At 12:25 pm on December 13, 2011, we started the re-circulating operation 
 of desalination facility (reverse osmosis membrane type) for the purpose 
 of suppression of condensed water after desalination treatment.
-As accumulated water containing radioactive materials was found in the 
 trench between Process Main Building and Miscellaneous Solid Waste Volume 
 Reduction Treatment Building (High Temperature Incinerator Building) in 
 Centralized Radiation Waste Treatment Facility (December 18, 2011), 
 inspection of other trenches in the site was commenced from January 11.
-At 9:18 am on January 31, we started transfer of Sub-drain Water of Unit 
 6 to the temporary tank. We will conduct transferring to the temporary 
 tank appropriately.
-At 2:43 pm on February 10, we started to transfer accumulated water from 
 underground floor of turbine building of Unit 2 to centralized radiation 
 waste treatment facility (Miscellaneous Solid Waste Volume Reduction 
 Treatment Building [High Temperature Incinerator Building]).
-At 9:57 am on February 12, we started to transfer accumulated water in 
 the underground of turbine building of Unit 3 to the Centralized Radiation 
 Waste Treatment Facility (Process Main Building).

*1) Reactor Facility Safety Regulation provides necessary conditions such 
    as the numbers of the permitted machines etc. or criteria of 
    temperatures and pressures for securing multiple safety function for 
    operating reactors and for keeping nuclear power stations stable and 
    these are treated as conditions for operation. When there happen some 
    malfunctions of equipment provided in the regulation and a nuclear 
    power station can not clear the conditions temporarily, operators have 
    to take required countermeasures.
*2) Based on the management of facilities stipulated at the Article 12 
    "Mid-term safety securing" of Act of the Regulation of Nuclear Source 
    Material, Nuclear Fuel Material and Reactors, it provides "Operational 
    Limit" and "measures required in the case that does not satisfy the 
    Operational Limit", it is required to respond based on the measures 
    required in the case that does not satisfy the Operational Limit. In 
    our case, in order to implement the preservation work, it was shifted 
    to outside of operational limit condition as planned (from 1:55 pm on 
    February 12), we change the water injection amount into the reactor of 
    Unit 2. At 2:20 pm, we judged that it was not satisfied "the 
    temperature is below 80 °C at the bottom of PCV ", which is stipulated 
    in "the Reactor Facility safety Regulation" as one of the "Conditions 
    of operation". as the indicated temperature was 82 °C beyond 80 °C. We 
    continue to change the water injection amount accordingly. 
back to page top


to TOP