Press Release (Feb 09,2012)
Status of the Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki Earthquake (as of February 9)
We are announcing the status of major inspections and restoration works 
and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station 
after the Niigata-Chuetsu-Oki Earthquake. 

Inspection/Restoration Status 

 ◇ Inspection and restoration completed between February 3 to February 
    9, 2012 
    (Completed on the following date) 

   - No notable activity during this week. 

 ◇ Inspection and restoration to be commenced between February 10 to 
    February 16, 2012 
    (To be commenced on the following date) 

   - No notable activity during this week. 

 ◇ Work Schedule of Major Inspection and Restoration from February 5 to 
    March 3, 2012 

   - Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-
     Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki 
     Earthquake (during 4 Weeks)                              ...Appendix 

 ◇ Other Findings

   - Information on Nonconformances (those related to: the Chuetsu-Oki 
     Earthquake; Grades GI, GII, GIII; and non-graded) 
     (including nonconformances related to: the Chuetsu-Oki Earthquake; 
     Grades As, A, B, C, D; and non-graded) 
Other Findings
Appendix: Work Schedule of the Main Inspection/Restoration of the Kashiwazaki- 
          Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki 
          Earthquake (during 4 Weeks) (PDF 68.3KB) 