We are announcing the status of major inspections and restoration works and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station after the Niigata-Chuetsu-Oki Earthquake.
Inspection / Restoration Status
◇Inspection and restoration completed between April 6 to April 12, 2012
(Completed on the following date)
- No notable activity during this week.
◇Inspection and restoration to be commenced between April 13 to April 19, 2012
(To be commenced on the following date)
- No notable activity during this week.
◇Work Schedule of Major Inspection and Restoration from April 8 to May 5, 2012
- Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) ...Appendix
◇Other Findings
- Information on Nonconformances (those related to: the Chuetsu-Oki Earthquake; Grades GI, GII, GIII; and non-graded)
(including nonconformances related to: the Chuetsu-Oki Earthquake; Grades As, A, B, C, D; and non-graded)
Appendix:
Work Schedule of the Main Inspection/Restoration of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) (PDF 14.6KB)
Appendix:
Processing Status of Nonconformances of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake
*The attached file titled "Processing Status of Nonconformances of the Kashiwazaki-Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki Earthquake" is only available in Japanese.
We apologize for any inconvenience this may cause.