search



Corporate Information

 
Press Release (Jan 26,2012)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, January 26)
*The updates are underlined  
 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.  
 
Unit 1 (Shut down)  
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12, 2011. It was assumed to be hydrogen 
  explosion.
- At 3:37 pm on March 25, 2011, we started injecting freshwater to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
  At 10:11 am on December 10, 2011, in addition to water injection from 
  water feeding system, we started water injection from piping of core 
  spray system to the reactor.
  The Current water injection volume is approx. 4.4 m3/h from the reactor 
  feed water system and approx. 2 m3/h from the core spray system.
- At 1:31 am on April 7, 2011, we commenced injection of nitrogen gas into 
  Primary Containment Vessel.
- At 11:22 am on August 10, 2011, we started cyclic cooling for the water 
  in the spent fuel pool by an alternative cooling equipment of the Fuel 
  Pool Cooling and Filtering System. 
- On October 28, 2011, we completed installation of the cover for the 
  Reactor Building in order to contain dispersion of radioactive 
  substances.
- At 4:04 pm on November 30, 2011, we started operation to inject nitrogen 
  into the reactor pressure vessel.
- At 6:00 pm on December 19, 2011, a full-scale operation of the PCV gas 
  management system started.  
 
Unit 2 (Shut down)  
- At approximately 6:00 am on March 15, 2011, an abnormal noise began 
  emanating from nearby Pressure Suppression Chamber and the pressure 
  within the chamber decreased. 
- At 10:10 am on March 26, 2011, we started injecting freshwater to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
  At 2:59 pm on September 14, 2011, in addition to water injection from 
  water feeding system, we started water injection from piping of core 
  spray system to the reactor.
- At 5:10 pm on January 25, regarding the reactor injection from the feed 
  water system at the Unit 2, we changed the injection line from the pump 
  located uphill to the T/B reactor injecting pump. 
- At 9:47 am on January 26, due to the change of injection duct owned by 
  the pump located uphill, the volume from the feed water system increased 
  from approx. 7.9m3/h to 8.7 m3/h, and the volume from the reactor core 
  system decreased from approx. 1.0m3/h to 0m3/h.
  The current water injection amount from the reactor feed water system is 
  approx. 8.7 m3/h and that from the core spray system is approx. 0 m3/h.
- At 5:21 pm on May 31, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 8:06 pm on June 28, 2011, we started injecting nitrogen gas into the 
  Primary Containment Vessel.
- At 6:00 pm on October 28, 2011, a full-scale operation of the PCV gas 
  management system started. On January 25 2012, we conducted sampling of 
  the gas of the PCV gas management system. As a result of the analysis, 
  we confirmed that at the entrance of the system Xenon 135 was below 
  detection limit (1.1 x 10-1Bq/cm3), and below the re-criticality 
  criterion which is 1Bq/ cm3.  
- At 10:46 am on December 1, 2011, we started the nitrogen injection to 
  the Reactor Pressure Vessel.
- At 11:50 am on January 19, 2012, we started the operation of the spent 
  fuel pool desalting facility.  
 
Unit 3 (Shut down)  
- Explosive sound and white smoke were confirmed at approximately 11:01 am 
  on March 14, 2011. It was assumed to be hydrogen explosion. 
- At 6:02 pm on March 25, 2011, we started injecting fresh water to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
  At 2:58 pm on September 1, 2011, we started water injection by core 
  spray system in addition to water injection by the reactor feed water 
  system piping arrangement.  
  For the reliability enhancement of water injection into the reactor, the 
  water discharge line of the reactor water injection pump on the hill is 
  planned to be changed from pressure hose to polyethylene pipe. Therefore, 
  there is the necessity of the temporary stopping of water injection from 
  the reactor water injection pump for it. At 11:50 am January 26, the 
  water injection to the reactor from the feed water injection system was 
  switched from the reactor water injection pump to the reactor water 
  injection pump in the turbine building. 
  The current water injection amount from the reactor feed water system is 
  approx. 8.1 m3/h and that from the core spray system is approx. 1 m3/h.
- At 7:47 pm on June 30, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System.
- At 8:01 pm on July 14, 2011, injection of nitrogen gas into the Primary 
  Containment Vessel started. 
- At 4:26 pm on November 30, 2011, we started operation to inject nitrogen 
  into the reactor pressure vessel.
- At 3:18 pm on January 14, we started operation of the radioactive 
  material removal instrument for the spent fuel pool in Unit 3  
 
Unit 4 (Outage due to regular inspection)  
- At around 6 am on March 15, 2011, we confirmed the explosive sound and 
  the sustained damage around the 5th floor rooftop area of Reactor 
  Building.
- At 12:44 pm on July 31, 2011, we started cyclic cooling for the water in 
  the spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System (from 1:30 pm to 3:14 pm on January 12, 
  2012, we injected hydrazine [corrosion inhibitor] in conjunction with 
  the cyclic cooling). At 1:31 pm on January 26, we started injection of 
  hydrazine to the spent fuel pool.  
- At 10:58 am on November 29, 2011, in order to decrease more salinity, we 
  installed Ion exchange equipment and started the operation of such 
  equipment.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel.  
 
Unit 5 (Outage due to regular inspection)  
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, 2011, we started the Residual Heat Removal 
  System Pump in order to cool the spent fuel pool.
- At 2:45 pm on July 15, 2011, we started the operation of the original 
  Residual Heat Removal System (System B) by its original seawater pump.
- At 10:11 am on December 22, 2011, since we finished the recovery work of 
  seawater pump (System B) of equipment water cooling system, we made a 
  trial run. At 11:25 am on the same day, we confirmed no abnormalities 
  and restarted the operation.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel.  
 
Unit 6 (Outage due to regular inspection)  
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, 2011, we started the Residual Heat Removal 
  System Pump of Unit 6 to cool down Spent Fuel Pool.
- At 2:33 pm on September 15, 2011, we started separately cooling the 
  reactor through the Residual Heat Removal System and the spent fuel pool 
  through Equipment Cooling Water System and Fuel Pool Cooling System.
- At this moment, we do not think there is any reactor coolant leakage 
  inside PCV.  
 
Others  
- At around 10:00 am on June 13, 2011, we started the operation of the 
  circulating seawater purification facility installed at the screen area 
  of Unit 2 and 3.
- At 8:00 pm on June 17, 2011, we started operation of Water Treatment 
  Facility against the accumulated water. At 6:00 pm on July 2, we started 
  the circulating injection cooling to inject the water, which was treated 
  by the accumulated water treatment system, to the reactors through the 
  buffer tank.
- At 7:41 pm on August 19, 2011, we started treatment of accumulated water 
  by parallel operation of one line from the cesium adsorption instrument 
  to the decontamination instrument and the other treatment line of the 
  cesium adsorption instrument No.2.
- At 2:06 pm on October 7, 2011, we started to spray purified accumulated 
  water brought from Unit 5 and 6 continually in order to prevent dust 
  scattering and potential fire outbreaks from the cut down trees.
- On October 28, 2011, we started installation of the water proof wall at 
  the sea side, in front of the existing shore protection, Units 1-4, in 
  order to contain marine pollution by underground water.
- At 12:25 pm on December 13, 2011, we started the re-circulating 
  operation of desalination facility (reverse osmosis membrane type) for 
  the purpose of suppression of condensed water after desalination 
  treatment.
- As finding of accumulated water containing radioactive materials at the 
  trench between the Process Main Building and the Miscellaneous Solid 
  Waste Volume Reduction Treatment Building [High Temperature Incinerator 
  Building] (December 18, 2011), we started the inspection of other 
  trenches at the site on January 11. 
back to page top


to TOP