We have reported the results of the comprehensive safety evaluation
(primary evaluation) to the Nuclear and Industrial Safety Agency (NISA) on
January 16, 2012, per instructions received from NISA on July 22, 2011,
titled, "Comprehensive Evaluation of Existing Nuclear Power Reactor
Facilities after the Accident at Fukushima Daiichi Nuclear Power Station,
Tokyo Electric Power Co., Inc., (Instruction)".
(Announced on July 22, 2011, and January 16, 2012)
Currently, while in the process of preparing documentation for an
inspection we came across some incorrect data (5 inaccuracies) * in the
report.
However, we also confirmed that these 5 inaccuracies do not affect the
evaluation results.
We will continue to verify whether there is any other incorrect data, and
take careful measures to maintain accuracy in future reports.
○ Attachment
List of corrigenda regarding the "Report of Results of the Comprehensive
Evaluation (Primary Evaluation) regarding the Safety of Units 1 and 7 at
Kashiwazaki-Kariwa Nuclear Power Station ". (PDF 242KB)
* Confirmation of 5 pieces of incorrect data in some parts of the report
On January 23, 2012, we announced the Correction in "Report of Results of
Comprehensive Evaluation (Primary Evaluation) regarding Safety on Unit 1
and Unit 7 of Kashiwazaki-Kariwa Nuclear Power Station to NISA", however,
the announcement was made due to the correction of the attachments. This
is the first announcement concerning the corrections made to the report.