search



Corporate Information

 
Press Release (Dec 29,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, December 29)
*Updates are underlined.
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1 (Shut down) 
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- At 3:37 pm on March 25, we started injecting freshwater to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line. 
- At 10:11 am on December 10, in addition to water injection from water 
  feeding system, we started water injection from piping of core spray 
  system to the reactor.
  The current water injection volume is approx. 4.3 m3/h from the reactor 
  feed water system and approx. 2 m3/h from the core spray system.
- We commenced injection of nitrogen gas into Primary Containment Vessel 
  at 1:31 am on April 7.
- At 11:22 am on August 10, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- On October 28, we completed installation of the cover for the Reactor 
  Building in order to contain dispersion of radioactive substances.
- At 4:04 pm on November 30, we started operation to inject nitrogen into 
  the reactor pressure vessel.
- At 6:00 pm on December 19, a full-scale operation of the PCV gas 
  management system started.
Unit 2 (Shut down) 
- At approximately 6:00 am on March 15, an abnormal noise began emanating 
  from nearby Pressure Suppression Chamber and the pressure within the 
  chamber decreased. 
- At 10:10 am on March 26, we started injecting freshwater to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line. 
- At 2:59 pm on September 14, in addition to water injection from water 
  feeding system, we started water injection from piping of core spray 
  system to the reactor.
  The current water injection volume is approx. 1.8 m3/h from the reactor 
  feed water system and approx. 7.0 m3/h from the core spray system.
- At 5:21 pm on May 31, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System.
- At 8:06 pm on June 28, we started injecting nitrogen gas into the Primary 
  Containment Vessel.
- At 6:00 pm on October 28, we put the gas management system of the reactor 
  containment vessel in operation.
- At 10:46 am on December 1, we started the nitrogen injection to the 
  Reactor Pressure Vessel.
Unit 3 (Shut down) 
- Explosive sound and white smoke were confirmed at approximately 11:01 am 
  on March 14. It was assumed to be hydrogen explosion.
- At 6:02 pm on March 25, we started injecting fresh water to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.
- At 2:58 pm on September 1, we started water injection by core spray 
  system in addition to water injection by the reactor feed water system 
  piping arrangement. 
  The current water injection volume is approx 3.1 m3/h from the reactor 
  feed water system and approx. 6 m3/h from the core spray system.
- At 7:47 pm on June 30, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System.
- At 10:23 am on December 29, due to the declining tendency of the suction 
  pressure of the primary system circulating pump of the spent fuel pool 
  alternative cooling system of Unit 3, we stopped the pump and then 
  stopped cooling of the spent fuel pool temporarily to conduct flushing 
  of the intake side strainer of the pump (water temperature at the 
  stoppage: approx. 12.4°C). After that we conducted flushing and the 
  suction pressure of the pump recovered, therefore at 0:09 pm on the same 
  day, we restarted the pump and resumed cooling of the spent fuel pool 
  (water temperature at resuming: approx. 12.5°C). 
- At 8:01 pm on July 14, injection of nitrogen gas into the Primary 
  Containment Vessel started. 
- At 4:26 pm on November 30, we started operation to inject nitrogen into 
  the reactor pressure vessel.
Unit 4 (Outage due to regular inspection) 
- At around 6 am on March 15, we confirmed the explosive sound and the 
  sustained damage around the 5th floor rooftop area of Reactor Building.
- At 12:44 pm on July 31, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. (From 1:28 pm to 3:07 pm on December 28, 
  we conducted injection of hydrazine to spent fuel pool of Unit 4 through 
  the circulating cooling system.)
- At 10:58 am on November 29, in order to decrease more salinity, we 
  installed Ion exchange equipment and started the operation of such 
  equipment.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel.
Unit 5 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System Pump 
  in order to cool the spent fuel pool.
- At 2:45 pm on July 15, we started the operation of the original Residual 
  Heat Removal System (System B) by its original seawater pump.
- At 10:11 am on December 22, since we finished the recovery work of 
  seawater pump (System B) of equipment water cooling system, we made a 
  trial run. At 11:25 am on the same day, we confirmed no abnormalities 
  and restarted the operation.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel.
Unit 6 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System 
  Pump of Unit 6 to cool down Spent Fuel Pool.
- At 2:33 pm on September 15, we started separately cooling the reactor 
  through the Residual Heat Removal System and the spent fuel pool through 
  Equipment Cooling Water System and Fuel Pool Cooling System.
- At this moment, we do not think there is any reactor coolant leakage 
  inside PCV.
Others 
- At around 10 am on June 13, we started the operation of the circulating 
  seawater purification facility installed at the screen area of Unit 2 
  and 3.
- At 8 pm on June 17, we started operation of Water Treatment Facility 
  against the accumulated water. At 6:00 pm on July 2, we started the 
  circulating injection cooling to inject the water, which was treated by 
  the accumulated water treatment system, to the reactors through the 
  buffer tank.
- At 7:41 pm on August 19, we started treatment of accumulated water by 
  parallel operation of one line from the cesium adsorption instrument to 
  the decontamination instrument and the other treatment line of the 
  cesium adsorption instrument No.2.
- At 2:06 pm on October 7, we started to spray purified accumulated water 
  brought from Unit 5 and 6 continually in order to prevent dust scattering 
  and potential fire outbreaks from the cut down trees.
- On October 28, we started installation of the water proof wall at the 
  sea side, in front of the existing shore protection, Units 1-4, in order 
  to contain marine pollution by underground water.
- At 12:25 pm on December 13, we started the re-circulating operation of 
  desalination facility (reverse osmosis membrane type) for the purpose of 
  suppression of condensed water after desalination treatment.
- Since December 22, one of the atmospheric temperatures of Unit 1 Primary 
  Containment Vessel (PCV) monitored by the Containment Atmospheric 
  Monitoring System had risen (the atmospheric temperature of the PCV on 
  December 22 was approx. 38°C, at 7 pm on December 27 was approx. 49°C). 
  The other temperatures had not risen, so we conducted a survey from 9 am 
  to 10 am on December 28, and we confirmed that there are no problems. 
  From 11:00am to 12:15pm on the same date, to identify cause with 
  monitoring, we adjusted the volume of Nitrogen injection, from approx. 
  8 Nm3/h to approx.18 Nm3/h, and emission of the gas management system, 
  from approx. 23 Nm3/h to approx.30 Nm3/h, as of before December 22. The 
  temperature, the maximum went up to approx. 54.6°C at 6 pm on December 
  28, fell to approx. 52.3°C at 10 am and 1 pm on December 29. 
  Other two temperature indicators were in gradual increases, but now the 
  two are stable. 
    The second: (Maximum) approx. 34.9°C at 9:00 pm on December 28 → 
    approx. 34.8°C at 1:00 pm on December 29. 
    The third: (Maximum) approx. 39.2°C at 1:00 am on December 29 → 
    approx. 39.2°C at 1:00 pm on December 29. 
  We are planning to identify cause with monitoring continuously. 
- At 3:22 pm on December 28, we started to transfer accumulated water from 
  the basement of turbine building of Unit 2 to the Centralized Radiation 
  Waste Treatment Facility (Miscellaneous Solid Waste Volume Reduction 
  Treatment Building [High Temperature Incinerator Building] and the 
  Process Main Building).
- At 10:12 am on December 29, TEPCO staff observed a water leakage from 
  the imperceptive leak in a hose around the concentrated water storage 
  area of water desalinations (reverse osmosis membrane) while on patrol. 
  We confirmed that filtrate water*, transferred with the hose from the 
  filtrate tank to the boiler tank of the evaporative concentration 
  apparatus, leaked from the water leakage. Just to be safe, we 
  investigated nuclide analysis for the water, and the nuclide was bellow 
  measurable limit. After that, we stopped transferring filtrate water, 
  and filled the hole with tape, and the leaked water is now an average of 
  a drop every two minutes. We are planning to replace the hose. The leaked 
  filtrate water will not expand around there because there are no street 
  gutters. 
    * filtrate water (freshwater): Water from Sakashita Dam 
back to page top


to TOP