* Updates are underlined.
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down
Unit 1 (Shut down)
- Explosive sound and white smoke were confirmed after the big quake
occurred at 3:36 pm on March 12. It was assumed to be hydrogen
explosion.
- At 3:37 pm on March 25, we started injecting freshwater to the reactor
and are now injecting fresh water by a motor driven pump powered by the
off-site transmission line.
- At 10:11 am on December 10, in addition to water injection from water
feeding system, we started water injection from piping of core spray
system to the reactor.
The current water injection volume is approx 4.8 m3/h from the reactor
feed water system and approx. 2.0 m3/h from the core spray system.
- We commenced injection of nitrogen gas into Primary Containment Vessel
at 1:31 am on April 7.
- At 11:22 am on August 10, we started cyclic cooling for the water in
the spent fuel pool by an alternative cooling equipment of the Fuel
Pool Cooling and Filtering System.
- On October 28, we completed installation of the cover for the Reactor
Building in order to contain dispersion of radioactive substances.
- At 4:04 pm on November 30, we started operation to inject nitrogen into
the reactor pressure vessel.
Unit 2 (Shut down)
- At approximately 6:00 am on March 15, an abnormal noise began emanating
from nearby Pressure Suppression Chamber and the pressure within the
chamber decreased.
- At 10:10 am on March 26, we started injecting freshwater to the reactor
and are now injecting fresh water by a motor driven pump powered by the
off-site transmission line.
- At 2:59 pm on September 14, in addition to water injection from water
feeding system, we started water injection from piping of core spray
system to the reactor.
The current water injection volume is approx. 2.8 m3/h from the reactor
feed water system and approx. 5.9 m3/h from the core spray system.
- At 5:21 pm on May 31, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
6:54 am on December 14, the alert that indicates the flow difference is
big at the inlet and outlet of primary pump was issued on the
alternative cooling system of sent fuel pool. No abnormalities such as
leaking etc. were found by field inspection. Then, as we sounded the
instrument piping, we confirmed that alert stopped. Hereafter we will
check flow rate once an hour. In addition to this, keeping operation of
spent fuel pool alternative cooling system so there is no problem on
cooling
- At 8:06 pm on June 28, we started injecting nitrogen gas into the
Primary Containment Vessel.
- From 6:00 pm on October 28, we put the gas management system of the
reactor containment vessel in operation.
- At 10:46 am on December 1, we started the nitrogen injection to the
Reactor Pressure Vessel.
Unit 3 (Shut down)
- Explosive sound and white smoke were confirmed at approximately 11:01
am on March 14. It was assumed to be hydrogen explosion.
- At 6:02 pm on March 25, we started injecting fresh water to the reactor
and are now injecting fresh water by a motor driven pump powered by the
off-site transmission line.
- At 2:58 pm on September 1, we started water injection by core spray
system in addition to water injection by the reactor feed water system
piping arrangement.
The current water injection volume is approx 2.8 m3/h from the reactor
feed water system and approx. 5.8 m3/h from the core spray system.
- At 7:47 pm on June 30, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
- At 8:01 pm on July 14, injection of nitrogen gas into the Primary
Containment Vessel started.
- At 4:26 pm on November 30, we started operation to inject nitrogen into
the reactor pressure vessel.
Unit 4 (Outage due to regular inspection)
- At around 6 am on March 15, we confirmed the explosive sound and the
sustained damage around the 5th floor rooftop area of Reactor Building.
- At 12:44 pm on July 31, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
- At 10:58 am on November 29, in order to decrease more salinity, we
installed Ion exchange equipment and started the operation of such
equipment.
- At this moment, we don't think there is any reactor coolant leakage
inside the primary containment vessel.
Unit 5 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System
Pump in order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved cold shutdown.
- At 2:45 pm on July 15, we started the operation of the original
Residual Heat Removal System (System B) by its original seawater pump.
- At this moment, we don't think there is any reactor coolant leakage
inside the primary containment vessel.
Unit 6 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System
Pump of Unit 6 to cool down Spent Fuel Pool.
- At 7:27 pm on March 20, the reactor achieved cold shutdown.
- At 2:33 pm on September 15, we started separately cooling the reactor
through the Residual Heat Removal System and the spent fuel pool
through Equipment Cooling Water System and Fuel Pool Cooling System.
- At this moment, we do not think there is any reactor coolant leakage
inside PCV.
Others
- At around 10 am on June 13, we started the operation of the circulating
seawater purification facility installed at the screen area of Unit 2
and 3.
- At 8 pm on June 17, we started operation of Water Treatment Facility
against the accumulated water. At 6:00 pm on July 2, we started the
circulating injection cooling to inject the water, which was treated by
the accumulated water treatment system, to the reactors through the
buffer tank.
- At 7:41 pm on August 19, we started treatment of accumulated water by
parallel operation of one line from the cesium adsorption instrument to
the decontamination instrument and the other treatment line of the
cesium adsorption instrument No.2.
- At 2:06 pm on October 7, we started to spray purified accumulated water
brought from Unit 5 and 6 continually in order to prevent dust
scattering and potential fire outbreaks from the cut down trees.
- On October 28, we started installation of the water proof wall at the
sea side, in front of the existing shore protection, Units 1-4, in
order to contain marine pollution by underground water.
- At 6:03 pm on November 30, we started transfer of the accumulated water
from the basement of Unit 2 turbine building to Centralized Radiation
Waste Treatment Facility High Temperature Incinerator Building. At 7:51
am on December 13, we stopped the transfer of the accumulated water
from the basement of Turbine Building of Unit 2 to the centralized
radiation waste treatment facility (miscellaneous solid waste Volume
reduction treatment building [high temperature incinerator building])
in order to stop power supply to Unit 2 accumulated water transfer pump
for power supply enhancing work. With the stoppage of the water
transfer, the 2nd Cesium adsorption apparatus was shutdowned for
replacing vessels at 8:44 am on December 12, and will be kept outage
until December 14 in order to adjust the water level of the centralized
radiation waste treatment facility (miscellaneous solid waste Volume
reduction treatment building [high temperature incinerator building]).
The Cesium adsorption apparatus is continued its operation. Water
injection to the Reactors will not be affected since the cooling is
continued by using processed water in the buffer tank.
- At 12:25 pm on December 13, we started the re-circulating operation of
desalination facility (reverse osmosis membrane type) for the purpose
of suppression of condensed water after desalination treatment.
- We plan to establish the system injecting water into the reactor in
Unit 1 to 3 using the condensate storage tank of Unit 3. In preparation
of such establishment, the stored water in the tank was transferred to
the basement of turbine building of Unit 3 from 10:22 am on November 21
to 9:45 am on November 24. As the calibration of water level gauge is
required if all the water is transferred, approx. 200 ton was left in
the tank. During the measurement of salt concentration in the left
water, it turned out that concentration was high. In order to secure
the space for additional water injection to decrease such concentration,
at 10:00 am on December 6, the left water was transferred from the tank
to the basement of the turbine building of Unit 3.
At 8:54 on December 7, we stopped transferring, and at approx. 9:19 am
on the same day, we started filling water in the tank, but afterwards,
we confirmed water leakage (approx. 5 liter) at the joint section of
hose connecting to the tank, at approx. 9:52 am, we stopped filling
water and confirmed the leakage has stopped. We plan to consider such
measures as repair etc. in future. The leaked water was treated as to
be free of radioactive materials and desalinated. At 9:05 am on
December 9, we restarted filling the water in the tank after completing
the replacement of the transfer hose. At 7:00 pm on the same day, we
finished the filing. At 9:30 am on December 12, we started transferring
of the accumulated water in the condensate storage tank of Unit 3 to
the basement of Turbine Building of Unit 3 before feeding water to
reduce salt level in the tank. After that we confirmed decrease of
transferring quantity of water from the water level fluctuation, at 0:
00 pm on December 14, we stopped transferring of the accumulated water
in the tank. Also we confirmed that there was no water leakage at the
site. Currently we are investigating the cause.
At 0:30 pm on December 15, we flushed the pipe and started the system.
Then, as we confirmed the system was operating normally, as we presume
that the cause is stuck of dust in the pipe. At 4:00 pm on December 16,
we stopped transferring the accumulated water in the tank.
- From 10:00 am on December 15 to 4:00 pm on December 16, we transferred
accumulated water from the Turbine Building of Unit 6 to the temporary
tank.
- At 2:22 pm on December 15, we started transferring accumulated water
from the basement of Unit 3 turbine building to Centralized Radiation
Waste Facility (Process Main Building).