*Updates are underlined.
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1 (Shut down)
- Explosive sound and white smoke were confirmed after the big quake
occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- At 3:37 pm on March 25, we started injecting freshwater to the reactor
and are now injecting fresh water by a motor driven pump powered by the
off-site transmission line.
At 5:47 pm on 5 December, Amount of water injected through feed water
system was adjusted from approx. 4.0 m3/h to 4.5 m3/h. as the decrease
of such amount was observed.
The current water injection volume is approx 4.5m3/h from the reactor
feed water system.
- We commenced injection of nitrogen gas into Primary Containment Vessel
at 1:31 am on April 7.
- At 11:22 am on August 10, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
- On October 28, we completed installation of the cover for the Reactor
Building in order to contain dispersion of radioactive substances.
- At 4:04 pm on November 30, we started operation to inject nitrogen into
the reactor pressure vessel.
Unit 2 (Shut down)
- At approximately 6:00 am on March 15, an abnormal noise began emanating
from nearby Pressure Suppression Chamber and the pressure within the
chamber decreased.
- At 10:10 am on March 26, we started injecting freshwater to the reactor
and are now injecting fresh water by a motor driven pump powered by the
off-site transmission line.
- At 2:59 pm on September 14, we started injecting water to the reactor
through core spray system water injection piping arrangement in addition
to the water injection through reactor feed water system piping
arrangement.
Water is currently injected at approx. 3.1m3/h through reactor feed
water system piping arrangement, and at approx. 4.2m3/h through core
spray system water injection piping arrangement.
- At 5:21 pm on May 31, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
- At 8:06 pm on June 28, we started injecting nitrogen gas into the
Primary Containment Vessel.
- From 6:00 pm on October 28, we put the gas management system of the
reactor containment vessel in operation.
At 11:04 am on November 6, we started operation of radioactive material
decontamination instrument of spent fuel pool. After its continuous
operation for a month, the concentration of radioactive materials is
expected to go below the level of 102, the facilities finished its
operation on December 5. Sampling analysis of water in the spent fuel
pool thereafter confirmed that the concentration of radioactive material
actually decreased to the level of 102 from the level of 105 before the
removal operation.
- At 10:46 am on December 1, we started the nitrogen injection to the
Reactor Pressure Vessel.
- At 8:25 am on 6 December, dust sampling at opening part (blow out panel)
of Reactor Building in Unit 2 was started. At 10:25 am, the dust
sampling was completed.
Unit 3 (Shut down)
- Explosive sound and white smoke were confirmed at approximately 11:01 am
on March 14. It was assumed to be hydrogen explosion.
- At 6:02 pm on March 25, we started injecting fresh water to the reactor
and are now injecting fresh water by a motor driven pump powered by the
off-site transmission line.
At 2:58 pm on September 1, we started water injection by core spray
system in addition to water injection by the reactor feed water system
piping arrangement.
At 5:47 pm on 5 December, Amount of water injected through feed water
system was adjusted from approx. 2.0 m3/h to 2.2 m3/h. as the decrease
of such amount was observed. Water is currently injected at approx.
2.1 m3/h through reactor feed water system piping arrangement, and at
approx. 6.0 m3/h through core spray system water injection piping
arrangement.
- At 7:47 pm on June 30, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
- At 8:01 pm on July 14, injection of nitrogen gas into the Primary
Containment Vessel started.
- At 4:26 pm on November 30, we started operation to inject nitrogen into
the reactor pressure vessel.
Unit 4 (Outage due to regular inspection)
- At around 6 am on March 15, we confirmed the explosive sound and the
sustained damage around the 5th floor rooftop area of Reactor Building.
- At 12:44 pm on July 31, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
- Regarding spent fuel pool for unit 4, from August 20 to November 8, we
had decreased salinity by using the desalting facility. In order to
decrease more salinity, we installed Ion exchange equipment and started
the equipment at 10:58 am on November 29.
- At this moment, we don't think there is any reactor coolant leakage
inside the primary containment vessel.
Unit 5 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System Pump
in order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved cold shutdown.
- At 2:45 pm on July 15, we started the operation of the original Residual
Heat Removal System (System B) by its original seawater pump.
- From November 28, for the purpose of the cleaning by sucking up sands
etc. accumulated at the bottom of the inlet canal pump room in order to
avoid the performance deterioration of pumps, we stopped the pump (D) of
the residual heat removal system and suspended cooling the reactor, We
also stopped the pump (C) of the cooling water system and suspended
cooling the spent fuel pool. When each pump was stopped, the
temperatures of the water in the reactor and the spent fuel pool were
25.7°C and 20.4°C respectively. The planned suspension of cooling is
between 7:00 am to 5:00 pm everyday, and the temperature increases of
the water in the reactor and the spent fuel pool due to the suspension
are expected to be approx. 17°C and approx. 4°C per day respectively (we
plan to do the cleaning work for approx. 1 week).
On December 6, after the completion of such cleaning work, at 2:06 pm,
we reactivated the pump (C) of the cooling water system in Unit 5 in
order to restart the cooling of the spent fuel pool.(The temperature of
the spent fuel pool was 23.3°C). At 2:24 pm, we reactivated the pump (D)
of the residual heat removal system in Unit 5 in order to restart the
cooling of the spent fuel pool.(The temperature of the spent fuel pool
was 35°C).
- At this moment, we don't think there is any reactor coolant leakage
inside the primary containment vessel.
Unit 6 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System
Pump of Unit 6 to cool down Spent Fuel Pool.
- At 7:27 pm on March 20, the reactor achieved cold shutdown.
- At 2:33 pm on September 15, we started separately cooling the reactor
through the Residual Heat Removal System and the spent fuel pool through
Equipment Cooling Water System and Fuel Pool Cooling System.
- At this moment, we do not think there is any reactor coolant leakage
inside PCV.
Others
- At around 10 am on June 13, we started the operation of the circulating
seawater purification facility installed at the screen area of Unit 2
and 3.
- At 8 pm on June 17, we started operation of Water Treatment Facility
against the accumulated water. At 6:00 pm on July 2, we started the
circulating injection cooling to inject the water, which was treated by
the accumulated water treatment system, to the reactors through the
buffer tank.
- At 7:41 pm on August 19, we started treatment of accumulated water by
parallel operation of one line from the cesium adsorption instrument to
the decontamination instrument and the other treatment line of the
cesium adsorption instrument No.2.
- At 2:06 pm on October 7, we started to spray purified accumulated water
brought from Unit 5 and 6 continually in order to prevent dust
scattering and potential fire outbreaks from the cut down trees.
- On October 28, we started installation of the water proof wall at the
sea side, in front of the existing shore protection, Units 1-4, in order
to contain marine pollution by underground water.
- At 6:03 pm on November 30, we started transfer of the accumulated water
from the basement of Unit 2 turbine building to Centralized Radiation
Waste Treatment Facility High Temperature Incinerator Building.
- At 11:33 am on December 4, workers of cooperative company found that
there was puddle water inside the barrier around the evaporative
condensation apparatus (the estimated volume of water was approx. 45 m3).
At 11:52 am, we stopped the evaporative condensation apparatus 3A, and
at 12:14 pm, workers made visual inspection of the apparatus and the
leakage seemed stopped. After that, we conducted investigation and at
2:30 pm, we found that there is a crack in the barrier made of concrete,
that water was leaking to the gutter (surface dose rate of leaked water:
beta ray 110 mSv/h, gamma ray 1.8 mSv/h) and that leaked water was
distilled through the gap between the barrier and base concrete. We are
considering emergency response to stop leakage of water to the outside
of the barrier. In the meantime, the water desalination apparatus
(reverse osmosis membrane type) is continuing operation. As we have
sufficient volume of desalinated water, there is no impact on the
Reactor water injection. We piled sandbags around the gap and in the
gutter and, at 3:30 pm, we confirmed the leakage was stopped. In
addition, the accumulated water inside the barrier was transferred to
waste liquid RO tank by under water pump etc. from 6:10 pm to 10:20 pm.
Meanwhile, because the gutter is connected to general drainage canal in
the power station, water in general drainage canal around the
evaporative condensation apparatus and seawater around south discharge
channel, which is located the exit of general drainage canal, was
sampled. As a result of nuclide analysis, the result was similar extent
of or slightly higher than the latest one of published daily analysis.
On 5 December we again sampled the water of the channel near the water
desalination (evaporative concentration apparatus) and the south drain
(exit of the channel) and conducted a nuclide analysis, and the results
of the south drain showed the same level as the results we are
announcing daily.
- At 10:00 am on December 5, accumulated water in the turbine building of
Unit 6 was started to be transferred to a temporary tank. At 4:00 pm on
December 6, the transfer was stopped.
- We plan to establish the system injecting water into the reactor in Unit
1 to 3 using the condensate storage tank of Unit 3. In preparation of
such establishment, the stored water in the tank was transferred to the
basement of turbine building of Unit 3 from 10:22 am on November 21 to
9:45 am on November 24. As the calibration of water level gauge is
required if all the water is transferred, approx. 200 ton was left in
the tank. During the measurement of salt concentration in the left water,
it turned out that concentration was high. In order to secure the space
for additional water injection to decrease such concentration, at 10:00
am on December 6, the left water was transferred from the tank to the
basement of the turbine building of Unit 3.
- At approx. 11:00 am on December 6, leakage at a pin hole on the transfer
hose from a buffer tank to a desalination facility (leakage was a drop
per second). It was confirmed that leakage stopped after the temporary
repair with the water proof tape. The impact on the environment is
minimal as the leaked water is desalinated after the treatment by the
radioactive material removal facility and the leaked amount is little
- At 0:20 pm on December 6, it was confirmed that the measurement data for
0:00 pm in the monitoring post set at the main gate was missing. The
data for 1:00 pm, 1:30 pm, and 2:00 pm were manually measured at the
location and the measured data was in the same level as the data before
0:00 pm. Thereafter, we have removed the water accumulated in the cable
connector portion of the monitoring post and restarted the measurement
by the monitoring post at 2:30 pm.
- At 5:48 pm on December 3, the display malfunction of the No.8 monitoring
post measuring the radiation dose in the site was observed. As we could
not identify the cause and thus not make repair, alternative measurement
was conducted by the dosimeter located near the No.7 and 8 monitoring
post, which was installed to reinforce the surveillance along with the
nitrogen injection operation into the Reactor Pressure Vessel. Measured
data indicates no change from the previous day (No.7 monitoring post:
92μSv/h, No. 8 monitoring post: 42μSv/h as of 8:00 am)
On December 6, the display function of No. 8 monitoring post was
retrieved when its board was reinserted.
Thereafter, we have restarted the measurement with No. 8 monitoring post
as no sign of reoccurrence was confirmed.