search



Corporate Information

 
Press Release (Nov 30,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, November 30)
 
*Updates are underlined. 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1 (Shut down) 
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- At 3:37 pm on March 25, we started injecting freshwater to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.
  The current water injection volume is approx 4.3m3/h from the reactor 
  feed water system.
- We commenced injection of nitrogen gas into Primary Containment Vessel 
  at 1:31 am on April 7.
- In order to construct the nitrogen injection line direct to the reactor 
  branched by the nitrogen injection line into the primary containment 
  vessel of Unit 1, at 11:40 am on November 30, we temporarily stopped 
  Nitrogen injection into the primary containment vessel. Then, we 
  restarted Nitrogen injection into the primary containment vessel. At 
  12:23 pm on the same day, we confirmed the nitrogen injection amount 
  (28m3/h) into the primary containment vessel was stable. 
- At 11:22 am on August 10, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- On October 28, we completed installation of the cover for the Reactor 
  Building in order to contain dispersion of radioactive substances. 
Unit 2 (Shut down) 
- At approximately 6:00 am on March 15, an abnormal noise began emanating 
  from nearby Pressure Suppression Chamber and the pressure within the 
  chamber decreased. 
- At 10:10 am on March 26, we started injecting freshwater to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line. 
- At 2:59 pm on September 14, we started injecting water to the reactor 
  through core spray system water injection piping arrangement in addition 
  to the water injection through reactor feed water system piping 
  arrangement.
  Water is currently injected at approx. 3.1m3/h through reactor feed water 
  system piping arrangement, and at approx. 4.4 m3/h through core spray 
  system water injection piping arrangement.
- At 5:21 pm on May 31, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. (At 1:26 pm on November 30, we started 
  injection of hydrazine).
- At 8:06 pm on June 28, we started injecting nitrogen gas into the Primary 
  Containment Vessel.
- From 6:00 pm on October 28, we put the gas management system of the 
  reactor containment vessel in operation.
- At 11:04 am on November 6, we started operation of radioactive material 
  decontamination instrument of spent fuel pool.
- On November 29, sampling survey of gas at the gas management system of 
  Unit 2 primary containment vessel was implemented. As a result of the 
  analysis, we regarded the situation was not erratically because the 
  radioactive density at the gas management system of Unit 2 primary
  containment vessel was under ND (1.1x10-1Bq/cm3), the criteria of 
  erratically is 1 Bq/cc. Regarding Xe-135, its radioactive density was 
  detected by charcoal filter* (we regarded spontaneous fission). According 
  to the Report with regard to "Policy on the mid term security" for the 
  Units 1 to 4 of Fukushima Daiichi Nuclear Power Station to Nuclear and 
  Industrial Safety Agency at the Ministry of Economy, Trade and Industry 
  (1) (revision) (for public on November 9), the situation of erratically 
  therefore should be regarded by the sampling survey of gas at the gas 
  management system of Unit 2 primary containment vessel by vial.
  * Detection Limit Charcoal filter: 10-6 level, Vial: 10-1 level
- At 1:45 pm on November 30, we started nitrogen injection to the Reactor 
  Pressure Vessel. At 2:47 on the same day, as we confirmed nitrogen 
  injection had not increased, we temporally stopped the operation. The 
  cause is under investigation. We are continuing nitrogen injection into 
  the primary containment vessel. 
Unit 3 (Shut down) 
- Explosive sound and white smoke were confirmed at approximately 11:01 am 
  on March 14. It was assumed to be hydrogen explosion.
- At 6:02 pm on March 25, we started injecting fresh water to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.
- At 2:58 pm on September 1, we started water injection by core spray 
  system in addition to water injection by the reactor feed water system 
  piping arrangement. 
  Water is currently injected at approx. 2.1 m3/h through reactor feed 
  water system piping arrangement, and at approx. 6.0 m3/h through core 
  spray system water injection piping arrangement.
- At 7:47 pm on June 30, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System.
- At 8:01 pm on July 14, injection of nitrogen gas into the Primary 
  Containment Vessel started. 
- In order to construct the nitrogen injection line direct to the reactor 
  branched by the nitrogen injection line into the primary containment 
  vessel of Unit 3, at 11:33 am on November 30, we temporarily stopped 
  Nitrogen injection into the primary containment vessel. Then, we 
  restarted Nitrogen injection into the primary containment vessel. At 
  1:20 pm on the same day, we confirmed the nitrogen injection amount 
  (28m3/h) into the primary containment vessel was stable. 
- At 9:00 am on November 30, we started dust sampling above the reactor 
  building of Unit 3 with a large crane. At 12:30 pm on the same day, we 
  finished the sampling. 
- At 10:00 am on November 30, we started dust sampling by a robot near the 
  equipment hatch of ground floor, reactor building unit 3. At 10:30 am on 
  the same day, we finished sampling. 
Unit 4 (Outage due to regular inspection) 
- At around 6 am on March 15, we confirmed the explosive sound and the 
  sustained damage around the 5th floor rooftop area of Reactor Building.
- At 12:44 pm on July 31, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System.
- Regarding spent fuel pool for unit 4, from August 20 to November 8, we 
  had decreased salinity by using the desalting facility. In order to 
  decrease more salinity, we installed Ion exchange equipment and started 
  the equipment at 10:58 am on November 29.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel. 
Unit 5 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System Pump 
  in order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved cold shutdown.
- At 2:45 pm on July 15, we started the operation of the original Residual 
  Heat Removal System (System B) by its original seawater pump.
- From November 28, we started cleaning to avoid the performance 
  deterioration of pumps by sucking up sands etc. accumulated at the 
  bottom of the inlet canal pump room.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel. 
Unit 6 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System 
  Pump of Unit 6 to cool down Spent Fuel Pool.
- At 7:27 pm on March 20, the reactor achieved cold shutdown. 
- At 2:33 pm on September 15, we started separately cooling the reactor 
  through the Residual Heat Removal System and the spent fuel pool through 
  Equipment Cooling Water System and Fuel Pool Cooling System.
- At this moment, we do not think there is any reactor coolant leakage 
  inside PCV. 
Others 
- At around 10 am on June 13, we started the operation of the circulating 
  seawater purification facility installed at the screen area of Unit 2 
  and 3.
- At 8 pm on June 17, we started operation of Water Treatment Facility 
  against the accumulated water. At 6:00 pm on July 2, we started the 
  circulating injection cooling to inject the water, which was treated by 
  the accumulated water treatment system, to the reactors through the 
  buffer tank.
- At 7:41 pm on August 19, we started treatment of accumulated water by 
  parallel operation of one line from the cesium adsorption instrument to 
  the decontamination instrument and the other treatment line of the cesium 
  adsorption instrument No.2. 
- At 2:06 pm on October 7, we started to spray purified accumulated water 
  brought from Unit 5 and 6 continually in order to prevent dust scattering 
  and potential fire outbreaks from the cut down trees.
- On October 28, we started installation of the water proof wall at the 
  sea side, in front of the existing shore protection, Units 1-4, in order 
  to contain marine pollution by underground water.
- At 9:25 am on November 15, we started transfer of accumulated water from 
  basement of Unit 3 turbine building to Centralized Radiation Waste 
  Treatment Facility Building. 
back to page top


to TOP