Power demand and supply outlook due to shutdown of other company's thermal power station
We have been informed by Electric Power Development Co., Ltd. that the 
units 1 and 2 owned by Isogo Thermal Power Station (Yokohama City, 
Kanagawa Prefecture, 600MW each) have been shut down due to a fire that 
broke out last night. As a result, we lost 900MW and expect that our 
supply capacity today will be 43.3GW with a 10.5% reserve capacity. 

We expect that from tomorrow we will be able to secure a stable 
electricity supply for next week.