search



Corporate Information

 
Press Release (Nov 21,2011)
Plant Status of Fukushima Daini Nuclear Power Station (As at 3:00 pm on November 21)
 
On March 11 2011, turbines and reactors of Fukushima Daini Nuclear Power
Station Units 1 to 4 (Boiling Water Reactors, rated output 1,100
Megawatts) that we had been constantly operating at rated thermal output
were automatically shut down at 2:48 pm due to the Tohoku-Chihou-
Taiheiyou-Oki Earthquake.                 (March 11 Previously announced)

At 7:15 am on March 15, the reactor of Unit 4 achieved cold shutdown. As
a result, all reactors of Units 1 to 4 at Fukushima Daini Nuclear Power
Station achieved cold shutdown.
                                          (March 15 Previously announced)

As of 3:00 pm on November 21, the reactors of Units 1 to 4 are in cold
shutdown (please refer to the appendix for each reactor status).
We will continue to make our endeavors to further stabilize each plant of
cold shutdown.

· No updates from the previous announcement 
Appendix: TEPCO Plant Status of Fukushima Daini Nuclear Power Station 
                                                         (PDF 16.0KB) 
back to page top


to TOP