search



Corporate Information

 
Press Release (Nov 13,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, November 13)
  
* Updates are underlined. 
 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
 
Unit 1 (Shut down) 
-Explosive sound and white smoke were confirmed after the big quake 
 occurred at 3:36 pm on March 12. It was assumed to be hydrogen 
 explosion. 
-At 3:37 pm on March 25, we started injecting freshwater to the reactor 
 and are now injecting fresh water by a motor driven pump powered by the 
 off-site transmission line. 
 The current water injection volume is approx 7.8 m3/h from the reactor 
 feed water system. 
-We commenced injection of nitrogen gas into Primary Containment Vessel 
 at 1:31 am on April 7. 
-At 11:22 am on August 10, we started cyclic cooling for the water in the 
 spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-On October 28, we completed installation of the cover for the Reactor 
 Building in order to contain dispersion of radioactive substances. 
 
Unit 2 (Shut down) 
-At approximately 6:00 am on March 15, an abnormal noise began emanating 
 from nearby Pressure Suppression Chamber and the pressure within the 
 chamber decreased. 
-At 10:10 am on March 26, we started injecting freshwater to the reactor 
 and are now injecting fresh water by a motor driven pump powered by the 
 off-site transmission line. 
-At 2:59 pm on September 14, we started injecting water to the reactor 
 through core spray system water injection piping arrangement in 
 addition to the water injection through reactor feed water system 
 piping arrangement. 
 Water is currently injected at approx. 2.9 m3/h through reactor feed 
 water system piping arrangement, and at approx. 7.3 m3/h through core 
 spray system water injection piping arrangement. 
-At 5:21 pm on May 31, we started cyclic cooling for the water in the 
 spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-At 8:06 pm on June 28, we started injecting nitrogen gas into the 
 Primary Containment Vessel. 
-From 6:00 pm on October 28, we put the gas management system of the 
 reactor containment vessel in operation. 
-At 11:04 am on November 6, we started operation of radioactive material 
 decontamination instrument of spent fuel pool. 
 
Unit 3 (Shut down) 
-Explosive sound and white smoke were confirmed at approximately 11:01 am 
 on March 14. It was assumed to be hydrogen explosion. 
-At 6:02 pm on March 25, we started injecting fresh water to the reactor 
 and are now injecting fresh water by a motor driven pump powered by the 
 off-site transmission line. 
-At 2:58 pm on September 1, we started water injection by core spray 
 system in addition to water injection by the reactor feed water system 
 piping arrangement. 
 Water is currently injected at approx. 2.7 m3/h through reactor feed 
 water system piping arrangement, and at approx. 8.1 m3/h through core 
 spray system water injection piping arrangement. 
-At 7:47 pm on June 30, we started cyclic cooling for the water in the 
 spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-At 8:01 pm on July 14, injection of nitrogen gas into the Primary 
 Containment Vessel started. 
 
Unit 4 (Outage due to regular inspection) 
-At around 6 am on March 15, we confirmed the explosive sound and the 
 sustained damage around the 5th floor rooftop area of Reactor Building. 
-At 12:44 pm on July 31, we started cyclic cooling for the water in the 
 spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-At 11:34 am on August 20, we started an operation of desalination 
 equipment in the spent fuel pool. 
-At this moment, we don't think there is any reactor coolant leakage 
 inside the primary containment vessel. 
 
Unit 5 (Outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained. 
-At 5:00 am on March 19, we started the Residual Heat Removal System Pump 
 in order to cool the spent fuel pool. 
-At 2:30 pm on March 20, the reactor achieved cold shutdown. 
-At 2:45 pm on July 15, we started the operation of the original Residual 
 Heat Removal System (System B) by its original seawater pump. 
-At this moment, we don't think there is any reactor coolant leakage 
 inside the primary containment vessel. 
 
Unit 6 (Outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained. 
-At 10:14 pm on March 19, we started the Residual Heat Removal System 
 Pump of Unit 6 to cool down Spent Fuel Pool. 
-At 7:27 pm on March 20, the reactor achieved cold shutdown. 
-At 2:33 pm on September 15, we started separately cooling the reactor 
 through the Residual Heat Removal System and the spent fuel pool through 
 Equipment Cooling Water System and Fuel Pool Cooling System. 
-At this time, we don't think there is any reactor coolant leakage 
 inside the primary containment vessel. 
 
Others 
-At around 10 am on June 13, we started the operation of the circulating 
 seawater purification facility installed at the screen area of Unit 2 
 and 3. 
-At 8 pm on June 17, we started operation of Water Treatment Facility 
 against the accumulated water. At 6:00 pm on July 2, we started the 
 circulating injection cooling to inject the water, which was treated by 
 the accumulated water treatment system, to the reactors through the 
 buffer tank. 
-At 7:41 pm on August 19, we started treatment of accumulated water by 
 parallel operation of one line from the cesium adsorption instrument to 
 the decontamination instrument and the other treatment line of the 
 cesium adsorption instrument No.2. 
-At 2:06 pm on October 7, we started to spray purified accumulated water 
 brought from Unit 5 and 6 continually in order to prevent dust 
 scattering and potential fire outbreaks from the cut down trees. 
-On October 28, we started installation of the water proof wall at the 
 sea side, in front of the existing shore protection, Units 1-4, in 
 order to contain marine pollution by underground water. 
-At 9:10 am on November 10, we started transfer of accumulated water 
 from the basement of Unit 2 turbine building to Centralized Radiation 
 Waste Treatment Facility High Temperature Incinerator Building. 
-At 3:42 pm on November 11, we started to transfer the accumulated water 
 from the basement of Unit 1 turbine building to the basement of Unit 2 
 turbine building. At 10:45 am on November 13, we stopped the transfer. 
-At 10:00 am on November 13, we started to transfer the accumulated water 
 from Unit 6 turbine building to the temporary tank. 
back to page top


to TOP