search



Corporate Information

 
Press Release (Nov 02,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, November 2)
 
*Updates are underlined 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1 (Shut down) 
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- At 3:37 pm on March 25, we started injecting freshwater to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.
  At 4:14 am on November 2, we adjusted the amount of water injection to 
  the reactor to approximately 7.5m3/h. 
  The current water injection volume is approx 7.6 m3/h from the reactor 
  feed water system.
- We commenced injection of nitrogen gas into Primary Containment Vessel 
  at 1:31 am on April 7.
- At 11:22 am on August 10, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- On October 28, we completed installation of the cover for the Reactor 
  Building in order to contain dispersion of radioactive substances. 
Unit 2 (Shut down) 
- At approximately 6:00 am on March 15, an abnormal noise began emanating 
  from nearby Pressure Suppression Chamber and the pressure within the 
  chamber decreased. 
- At 10:10 am on March 26, we started injecting freshwater to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line. 
- At 2:59 pm on September 14, we started injecting water to the reactor 
  through core spray system water injection piping arrangement in addition 
  to the water injection through reactor feed water system piping 
  arrangement.
  At 4:14 am on November 2, we adjusted the amount of water injection to 
  the reactor to approximately 3 m3/h through reactor feed water system 
  piping arrangement, and 7 m3/h core spray system water injection piping 
  arrangement. 
  Water is currently injected at approx. 3 m3/h through reactor feed water 
  system piping arrangement, and at approx. 7 m3/h through core spray 
  system water injection piping arrangement.
- At 5:21 pm on May 31, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System (From 10:12 am to 11:50 am on Octorber 31, 
  hydrazine [corrosion preventive] was also injected) .
- At 8:06 pm on June 28, we started injecting nitrogen gas into the Primary 
  Containment Vessel.
- At 12:53 pm on October 28, we activated the exhaust fan of the gas 
  management system of the reactor containment vessel in the reactor 
  building and started test operation. As we confirmed stable operation of 
  the system, from 6:00 pm on the same day, we put the system in operation. 
- On November 1, we conducted a nuclide analysis of emitted gas sampled by 
  the gas management system of the reactor containment vessel. It was found 
  out that there was a possibility that short-half-life radionuclide (xenon 
  133, 135) was detected. There has been no significant variation as a 
  result of our continuous monitoring of the temperature and the pressure 
  in the reactor, and the figures of the monitoring posts. However, just to 
  be safe we injected boric-acid solution through reactor water injection 
  line from 2:48 am to 3:47 am on November 2, since we can not deny the 
  possibility that fission reaction had occurred. 
Unit 3 (Shut down) 
- Explosive sound and white smoke were confirmed at approximately 11:01 am 
  on March 14. It was assumed to be hydrogen explosion.
- At 6:02 pm on March 25, we started injecting fresh water to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.
- At 2:58 pm on September 1, we started water injection by core spray 
  system in addition to water injection by the reactor feed water system 
  piping arrangement. 
  Water is currently injected at approx. 2.5 m3/h through reactor feed 
  water system piping arrangement, and at approx. 8.1 m3/h through core 
  spray system water injection piping arrangement.
- At 7:47 pm on June 30, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System.
- At 8:01 pm on July 14, injection of nitrogen gas into the Primary 
  Containment Vessel started. 
Unit 4 (Outage due to regular inspection) 
- At around 6 am on March 15, we confirmed the explosive sound and the 
  sustained damage around the 5th floor rooftop area of Reactor Building.
- At 12:44 pm on July 31, we started cyclic cooling for the water in the 
  spent fuel pool by an alternative cooling equipment of the Fuel Pool 
  Cooling and Filtering System. 
- At 11:34 am on August 20, we started an operation of desalination 
  equipment in the spent fuel pool.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel. 
Unit 5 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System Pump 
  in order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved cold shutdown.
- At 2:45 pm on July 15, we started the operation of the original Residual 
  Heat Removal System (System B) by its original seawater pump.
- At this moment, we don't think there is any reactor coolant leakage 
  inside the primary containment vessel. 
Unit 6 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System Pump 
  of Unit 6 to cool down Spent Fuel Pool.
- At 7:27 pm on March 20, the reactor achieved cold shutdown. 
- At 2:33 pm on September 15, we started separately cooling the reactor 
  through the Residual Heat Removal System and the spent fuel pool through 
  Equipment Cooling Water System and Fuel Pool Cooling System.
- At this time, we don't think there is any reactor coolant leakage inside 
  the primary containment vessel. 
Others 
- At around 10 am on June 13, we started the operation of the circulating 
  seawater purification facility installed at the screen area of Unit 2 
  and 3.
- At 8 pm on June 17, we started operation of Water Treatment Facility 
  against the accumulated water. At 6:00 pm on July 2, we started the 
  circulating injection cooling to inject the water, which was treated by 
  the accumulated water treatment system, to the reactors through the 
  buffer tank.
- At 7:41 pm on August 19, we started treatment of accumulated water by 
  parallel operation of one line from the cesium adsorption instrument to 
  the decontamination instrument and the other treatment line of the cesium 
  adsorption instrument No.2. 
- At 2:06 pm on October 7, we started to spray purified accumulated water 
  brought from Unit 5 and 6 continually in order to prevent dust scattering 
  and potential fire outbreaks from the cut down trees.
- At 10:12 am on October 20, we started transferring the accumulated water 
  from the basement of turbine building of Unit 2 to the Process Main 
  Building of Central Radioactive Waste Treatment Facility. At 9:32 am on 
  October 28, we stopped transferring the accumulated water from the 
  basement of turbine building of Unit 2 to the Process Main Building of 
  Central Radioactive Waste Treatment Facility temporarily, and after 
  checking the systematic diagram, from 9:54 am on October 28 to 10:02 am 
  on October 31, the accumulated water has been transferred from Unit 2 
  turbine building basement to High Temperature Incinerator Building of 
  Centralized Radiation Waste Treatment Facility. 
- On October 28, we started installation of the water proof wall at the 
  sea side, in front of the existing shore protection, Units 1-4, in order 
  to contain marine pollution by underground water.
- From 10:00 am to 4:00 pm on November 1, we transferred accumulated water 
  from the temporarily built tank to Mega-float. At 10:00 am On November 2, 
  we started transferring accumulated water from the temporarily built tank 
  to the Mega-float. 
back to page top


to TOP