search



Corporate Information

 
Press Release (Nov 01,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, November 1)
 
*Updates are underlined 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1 (Shut down) 
-Explosive sound and white smoke were confirmed after the big quake 
 occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
-At 3:37 pm on March 25, we started injecting freshwater to the reactor 
 and are now injecting fresh water by a motor driven pump powered by the 
 off-site transmission line.
 At 2:59 pm on October 31, we adjusted the amount of water injection to 
 the reactor to approximately 7.5㎥/h in order to improve the working 
 environment inside the covering, making it sure to mitigate the steam 
 emission at the reactor building of Unit 1
 The current water injection volume is approx 7.5 ㎥/h from the reactor 
 feed water system.
-We commenced injection of nitrogen gas into Primary Containment Vessel 
 at 1:31 am on April 7.
-At 11:22 am on August 10, we started cyclic cooling for the water in the 
 spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-On October 28, we completed installation of the cover for the Reactor 
 Building in order to contain dispersion of radioactive substances. 
Unit 2 (Shut down) 
-At approximately 6:00 am on March 15, an abnormal noise began emanating 
 from nearby Pressure Suppression Chamber and the pressure within the 
 chamber decreased. 
-At 10:10 am on March 26, we started injecting freshwater to the reactor
 and are now injecting fresh water by a motor driven pump powered by the 
 off-site transmission line. 
-At 2:59 pm on September 14, we started injecting water to the reactor 
 through core spray system water injection piping arrangement in addition 
 to the water injection through reactor feed water system piping 
 arrangement.
 Water is currently injected at approx. 2.4㎥/h through reactor feed water 
 system piping arrangement, and at approx. 6.9 ㎥/h through core spray 
 system water injection piping arrangement.
-At 5:21 pm on May 31, we started cyclic cooling for the water in the 
 spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System (From 10:12 am to 11:50 am on Octorber 31, 
 hydrazine [corrosion preventive] was also injected) .
-At 8:06 pm on June 28, we started injecting nitrogen gas into the Primary
 Containment Vessel.
-At 12:53 pm on October 28, we activated the exhaust fan of the gas 
 management system of the reactor containment vessel in the reactor 
 building and started test operation. As we confirmed stable operation of 
 the system, from 6:00 pm on the same day, we put the system in operation. 
 Regarding the hydrogen concentration of the gas management system of the 
 reactor containment vessel in Unit 2, we confirmed that it increased to 
 approx. 2.7vol% at 5:00pm on October 30, which was approx. 1vol% at the 
 beginning of the operation. Therefore we adjusted the amount of injecting 
 nitrogen gas to the Primary Containment Vessel from approx.16.5 N ㎥/h to 
 21 N ㎥/h at 6:10 pm on October 30 in order to avoid exceeding the 
 combustible threshold concentration (4vol%) of hydrogen. 
-From 11:23 am to 1:23 pm on November 1, we conducted a dust sampling 
 around the blowout panel of the reactor building. 
Unit 3 (Shut down) 
-Explosive sound and white smoke were confirmed at approximately 11:01 am 
 on March 14. It was assumed to be hydrogen explosion.
-At 6:02 pm on March 25, we started injecting fresh water to the reactor 
 and are now injecting fresh water by a motor driven pump powered by the 
 off-site transmission line.
-At 2:58 pm on September 1, we started water injection by core spray 
 system in addition to water injection by the reactor feed water system 
 piping arrangement. 
 Water is currently injected at approx. 2.5 ㎥/h through reactor feed 
 water system piping arrangement, and at approx. 8.1 ㎥/h through core 
 spray system water injection piping arrangement.
-At 7:47 pm on June 30, we started cyclic cooling for the water in the 
 spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System.
-At 8:01 pm on July 14, injection of nitrogen gas into the Primary 
 Containment Vessel started. 
Unit 4 (Outage due to regular inspection) 
-At around 6 am on March 15, we confirmed the explosive sound and the 
 sustained damage around the 5th floor rooftop area of Reactor Building.
-At 12:44 pm on July 31, we started cyclic cooling for the water in the 
 spent fuel pool by an alternative cooling equipment of the Fuel Pool 
 Cooling and Filtering System. 
-At 11:34 am on August 20, we started an operation of desalination 
 equipment in the spent fuel pool.
-At this moment, we don't think there is any reactor coolant leakage 
 inside the primary containment vessel. 
Unit 5 (Outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 5:00 am on March 19, we started the Residual Heat Removal System Pump
 in order to cool the spent fuel pool.
-At 2:30 pm on March 20, the reactor achieved cold shutdown.
-At 2:45 pm on July 15, we started the operation of the original Residual
 Heat Removal System (System B) by its original seawater pump.
-At this moment, we don't think there is any reactor coolant leakage 
 inside the primary containment vessel. 
Unit 6 (Outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 10:14 pm on March 19, we started the Residual Heat Removal System Pump
 of Unit 6 to cool down Spent Fuel Pool.
-At 7:27 pm on March 20, the reactor achieved cold shutdown. 
-At 2:33 pm on September 15, we started separately cooling the reactor
 through the Residual Heat Removal System and the spent fuel pool through
 Equipment Cooling Water System and Fuel Pool Cooling System.
-At this time, we don't think there is any reactor coolant leakage inside
 the primary containment vessel. 
Others 
-At around 10 am on June 13, we started the operation of the circulating
 seawater purification facility installed at the screen area of Unit 2 and
 3.
-At 8 pm on June 17, we started operation of Water Treatment Facility 
 against the accumulated water. At 6:00 pm on July 2, we started the 
 circulating injection cooling to inject the water, which was treated by 
 the accumulated water treatment system, to the reactors through the 
 buffer tank.
-At 7:41 pm on August 19, we started treatment of accumulated water by 
 parallel operation of one line from the cesium adsorption instrument to
 the decontamination instrument and the other treatment line of the cesium
 adsorption instrument No.2. 
-At 2:06 pm on October 7, we started to spray purified accumulated water
 brought from Unit 5 and 6 continually in order to prevent dust scattering
 and potential fire outbreaks from the cut down trees.
-At 10:12 am on October 20, we started transferring the accumulated water
 from the basement of turbine building of Unit 2 to the Process Main 
 Building of Central Radioactive Waste Treatment Facility. At 9:32 am on
 October 28, we stopped transferring the accumulated water from the 
 basement of turbine building of Unit 2 to the Process Main Building of 
 Central Radioactive Waste Treatment Facility temporarily, and after 
 checking the systematic diagram, from 9:54 am on October 28 to 10:02 am 
 on October 31, the accumulated water has been transferred from Unit 2 
 turbine building basement to High Temperature Incinerator Building of 
 Centralized Radiation Waste Treatment Facility. 
-On October 28, we started installation of the water proof wall at the 
 sea side, in front of the existing shore protection, Units 1-4, in order
 to contain marine pollution by underground water.
-From 10:00 am to 4:00 pm on October 31, we transferred accumulated water
 from the temporarily built tank to Mega-float.
-From 10:00 am on November 1, we started transferring accumulated water 
 from the temporarily built tank to the Mega-float.
-At 11:45 am on October 9, we confirmed that the test runs of the three 
 evaporative concentration apparatus (3A, 3B, 3C) that were additionally 
 installed in the water desalination were successfully completed. On 
 November 1, we started full operation of these three evaporative 
 concentration apparatus (3A, 3B, 3C) considering the balance of both the 
 accumulated water and the coolant injection to the reactor. 
back to page top


to TOP