search



Corporate Information

 
Press Release (Oct 28,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, Oct. 28)
 
*Updates are underlined 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1 (Shut down) 
- Explosive sound and white smoke were confirmed after the big quake
  occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- At 3:37 pm on March 25, we started injecting freshwater to the reactor
  and are now injecting fresh water by a motor driven pump powered by the
  off-site transmission line.
  Water is currently injected at approx. 3.9 m3/h through reactor feed
  water system piping arrangement. 
- We commenced injection of nitrogen gas into Primary Containment Vessel
  at 1:31 am on April 7.
- At 11:22 am on August 10, we started cyclic cooling for the water in the
  spent fuel pool by an alternative cooling equipment of the Fuel Pool
  Cooling and Filtering System. 
Unit 2 (Shut down) 
- At approximately 6:00 am on March 15, an abnormal noise began emanating
  from nearby Pressure Suppression Chamber and the pressure within the
  chamber decreased. 
- At 10:10 am on March 26, we started injecting freshwater to the reactor
  and are now injecting fresh water by a motor driven pump powered by the
  off-site transmission line. 
- At 2:59 pm on September 14, we started injecting water to the reactor
  through core spray system water injection piping arrangement in addition
  to the water injection through reactor feed water system piping
  arrangement. Water is currently injected at approx. 2.9m3/h through
  reactor feed water system piping arrangement, and at approx. 7.1 m3/h
  through core spray system water injection piping arrangement.
- At 5:21 pm on May 31, we started cyclic cooling for the water in the
  spent fuel pool by an alternative cooling equipment of the Fuel Pool
  Cooling and Filtering System.
- At 8:06 pm on June 28, we started injecting nitrogen gas into the
  Primary Containment Vessel.
- At 10:30 am on October 27, we conducted leak test of the system as a
  part of construction to settle the gas control system of Primary
  Containment Vessel at the reactor building of Unit 2. As a result, we
  confirmed in-leak volume to the system had no problem. In addition, we
  conducted tentative operation test. As a result, we confirmed
  operational aspect of electric heater and exhaust fun had no problem.
  At 12:53 pm on October 28, we activated the exhaust fan of the gas 
  management system of the reactor containment vessel in the reactor 
  building and started test operation. 
Unit 3 (Shut down) 
- Explosive sound and white smoke were confirmed at approximately 11:01 am
  on March 14. It was assumed to be hydrogen explosion.
- At 6:02 pm on March 25, we started injecting fresh water to the reactor
  and are now injecting fresh water by a motor driven pump powered by the
  off-site transmission line.
- At 2:58 pm on September 1, we started water injection by core spray
  system in addition to water injection by the reactor feed water system
  piping arrangement. 
  water system piping arrangement, and at approx. 8.0 m3/h through core
  spray system water injection piping arrangement.
- At 7:47 pm on June 30, we started cyclic cooling for the water in the
  spent fuel pool by an alternative cooling equipment of the Fuel Pool
  Cooling and Filtering System.
- At 8:01 pm on July 14, injection of nitrogen gas into the Primary
  Containment Vessel started.
Unit 4 (Outage due to regular inspection) 
- At around 6 am on March 15, we confirmed the explosive sound and the
  sustained damage around the 5th floor rooftop area of Reactor Building.
- At 12:44 pm on July 31, we started cyclic cooling for the water in the
  spent fuel pool by an alternative cooling equipment of the Fuel Pool
  Cooling and Filtering System. 
- At 11:34 am on August 20, we started an operation of desalination
  equipment in the spent fuel pool.
- At this moment, we don't think there is any reactor coolant leakage
  inside the primary containment vessel. 
Unit 5 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System Pump
  in order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved cold shutdown.
- At 2:45 pm on July 15, we started the operation of the original Residual
  Heat Removal System (System B) by its original seawater pump.
- At this time, we don't think there is any reactor coolant leakage inside
  the primary containment vessel. 
Unit 6 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System
  Pump of Unit 6 to cool down Spent Fuel Pool.
- At 7:27 pm on March 20, the reactor achieved cold shutdown. 
- At 2:33 pm on September 15, we started separately cooling the reactor
  through the Residual Heat Removal System and the spent fuel pool through
  Equipment Cooling Water System and Fuel Pool Cooling System.
- At this time, we don't think there is any reactor coolant leakage inside
  the primary containment vessel. 
Others 
- At around 10 am on June 13, we started the operation of the circulating
  seawater purification facility installed at the screen area of Unit 2
  and 3.
- At 8 pm on June 17, we started operation of Water Treatment Facility
  against the accumulated water. At 6:00 pm on July 2, we started the
  circulating injection cooling to inject the water, which was treated by
  the accumulated water treatment system, to the reactors through the
  buffer tank.
- At 7:41 pm on August 19, we started treatment of accumulated water by
  parallel operation of one line from the cesium adsorption instrument to
  the decontamination instrument and the other treatment line of the
  cesium adsorption instrument No.2. 
- At 2:06 pm on October 7, we started to spray purified accumulated water
  brought from Unit 5 and 6 continually in order to prevent dust
  scattering and potential fire outbreaks from the cut down trees.
- We transferred the accumulated water from the basement of turbine
  building of Unit 3 to the High Temperature Incinerator Building of
  Central Radioactive Waste Treatment Facility from 10:00 am on October 20
  to 9:16 am on October 28.
- At 10:12 am on October 20, we started transferring the accumulated water
  from the basement of turbine building of Unit 2 to the Process Main
  Building of Central Radioactive Waste Treatment Facility. At 9:32 am on
  October 28, we stopped transferring the accumulated water from the
  basement of turbine building of Unit 2 to the Process Main Building of
  Central Radioactive Waste Treatment Facility temporarily, and after
  checking the systematic diagram, at 9:54 am on October 28 we changed the
  destination of transferring the accumulated water to High Temperature
  Incinerator Building of Centralized Radiation Waste Treatment Facility. 
- Partner companies' worker found the crack at connection casing in
  driving shaft of ceiling crane, which is used to deal with spent fuel
  casks and located in the common spent fuel pool building, during its
  annual check out. We will check carefully the situation of the
  connection casing in greater detail. 
- At 9:30 am on October 28, we changed lines of injecting water to reactor
  of Unit 1 and Unit 2 from regular line to emergency line for the purpose
  of adding flow controlling valve to the water injection line of Unit 1
  which would upgrade the control ability of water flow.
  At 1:30 pm, after the completion of the above work, we changed lines of 
  injecting water to reactor of Unit 1 and Unit 2 from emergency line to 
  regular line. At the same time, the amount of water from the reactor 
  feed water system was adjusted to approx. 3.9 m3/h at Unit1. At Unit 2, 
  the amount of injected water was adjusted to approx. 3m3/h from the 
  reactor feed water system and approx. 7m3/h from the core spray system. 
  (The stability of the flow rate was confirmed at 2:00 pm). 
- We stopped the water desalination facilities after detecting a water
  leakage (approx. 20L) from the pump and stopped the facilities. After we
  confirmed that the leakage stopped, at 2:30 pm on the same day, we
  stopped the line connecting to the water pump and started other water
  desalinations. At 4:20 pm, the rated flow reached 50 m3/h. From October 
  27 to 28, we exchanged the pump. 
- At 2:20 pm on October 28, one of the TEPCO staff felt sick and threw up 
  while he was checking the documents in the administration office 
  building, because the full-covered mask was tied too tightly. Because he 
  put off the mask temporarily when he threw up, he will be tested with 
  the whole body counter just in case. No radioactive materials was 
  detected on his face. 
back to page top


to TOP