On March 11 2011, turbines and reactors of Fukushima Daini Nuclear Power
Station Units 1 to 4 (Boiling Water Reactors, rated output 1,100 Megawatts)
that we had been constantly operating at rated thermal output were
automatically shut down at 2:48 pm due to the Tohoku-Chihou-Taiheiyou-Oki
Earthquake (previously announced on March 11).
At 7:15 am on March 15, the reactor of Unit 4 achieved cold shutdown. As a
result, all reactors of Units 1 to 4 at Fukushima Daini Nuclear Power
Station achieved cold shutdown (previously announced on March 15).
As of 4:00 pm on October 4, the reactors of Units 1 to 4 are in cold
shutdown (please refer to the appendix). We will continue to make our
endeavors to further stabilize each plant of cold shutdown.
·Updates are underlined.
Appendix: TEPCO Plant Status of Fukushima Daini Nuclear Power Station
(PDF 48.5KB)