*Updates are underlined.
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1 (Shut down)
- Explosive sound and white smoke were confirmed after the big quake
occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- From 3:37 pm on March 25, we started injecting freshwater by a motor
driven pump which is now powered by the off-site transmission line.
Water is currently injected at approx. 3.6 m3/h through reactor feed
water system piping arrangement.
- We commenced injection of nitrogen gas into Primary Containment Vessel at
1:31am on April 7.
- At 9:00 am on August 10, we started to assemble steel frame for the
Reactor Building Cover.
- At 11:22 pm on August 10, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
Unit 2 (Shut down)
- At approximately 6:00 am on March 15, an abnormal noise began emanating
from nearby Pressure Suppression Chamber and the pressure within the
chamber decreased.
- From 10:10 am on March 26, we started injecting freshwater to the reactor
and are now injecting fresh water by a motor driven pump powered by the
off-site transmission line.
- At 2:59 pm on September 14, we started injecting water to the reactor
through core spray system water injection piping arrangement in addition
to the water injection through the reactor feed water system piping
arrangement.
Water is currently injected at approx. 4 m3/h through reactor feed water
system piping arrangement, and at approx. 1 m3/h through core spray
system water injection piping arrangement.
- From 5:21 pm on May 31, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
- At 8:06 pm on June 28, we started injecting nitrogen gas into the Primary
Containment Vessel.
Unit 3 (Shut down)
- Explosive sound and white smoke were confirmed at approximately 11:01am
on March 14. It was assumed to be hydrogen explosion.
- From 6:02 pm on March 25, we started injecting fresh water to the reactor
and are now injecting fresh water by a motor driven pump powered by the
off-site transmission line.
- From 2:58 pm on September 1, we started water injection by core spray
system in addition to water injection by the reactor feed water system
piping arrangement.
Water is currently injected at approx. 4 m3/h through reactor feed water
system piping arrangement, and at approx. 3 m3/h through core spray
system water injection piping arrangement.
- From 7:47 pm on June 30, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
- At 8:01 pm on July 14, injection of nitrogen gas into the Primary
Containment Vessel started.
Unit 4 (Outage due to regular inspection)
- At approximately 6 am on March 15, we confirmed the explosive sound and
the sustained damage around the 5th floor rooftop area of Reactor
Building.
- From 12:44 pm on July 31, we started cyclic cooling for the water in the
spent fuel pool by an alternative cooling equipment of the Fuel Pool
Cooling and Filtering System.
- From 11:34 am on August 20, we started an operation of desalination
equipment in the spent fuel pool.
- At this moment, we don't think there is any reactor coolant leakage
inside the primary containment vessel.
Unit 5 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System Pump
in order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved cold shutdown.
- At 2:45 pm on July 15, we started the operation of the original Residual
Heat Removal System (System B) by its original seawater pump.
- At this time, we don't think there is any reactor coolant leakage inside
the primary containment vessel.
Unit 6 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System Pump
of Unit 6 to cool down Spent Fuel Pool.
- At 7:27 pm on March 20, the reactor achieved cold shutdown.
- At 3:12 pm on September 10, we started cooling the spent fuel pool
through the Residual Heat Removal System A using the seawater pump C. We
will conduct cooling the reactor and the spent fuel pool by turn through
the System A.
- At this time, we don't think there is any reactor coolant leakage inside
the primary containment vessel.
Others
- At around 10 am on June 13, we started the operation of the circulating
seawater purification facility installed at the screen area of Unit 2 and
3.
- At 8:00 pm on June 17, we started operation of Water Treatment Facility
against the accumulated water. At 6:00 pm on July 2, we started the
circulating injection cooling to inject the water, which was treated by
the accumulated water treatment system, to the reactors through the
buffer tank.
- At 7:41 pm on August 19, we started treatment of accumulated water by
parallel operation of one line from the cesium adsorption instrument to
the decontamination instrument and the other treatment line of the cesium
adsorption instrument No.2.
- At 10:00 am on September 11, we started transferring accumulated water
from the turbine building of Unit 3 to the High Temperature Incinerator
Building of Centralized Radiation Waste Treatment Facility. After the
temporary interruption for the confirmation of the system constitution,
we changed the transfer route and started transferring to Process
Building of Centralized Radiation Waste Treatment Facility.
- At 9:51 am on September 13, we started transferring accumulated water
from the turbine building of Unit 2 to High Temperature Incinerator
Building of Centralized Radiation Waste Treatment Facility.
- At 3:58 am on September 13, we stopped the cesium absorption instrument
and the decontamination instrument for the maintenance of the water
treatment facility. Then, after the completion of the maintenance work,
we restarted the treatment of the accumulated water at 7:20 pm on
September 14.
- At 9:53 am on September 14, we started transferring accumulated water at
Unit 1 condenser to the basement of Unit 1 turbine building.
- At 11:8 am on September 14, we stopped the operation of cooling
facilities of common pool because the common pool power center will be
moved with the replace of power panel located at the basement of the
spent fuel common pool's building.
- At approximately 12:40 pm on September 14, we found the inside of
full-face masks, which were used by 4 out of 6 partner company workers,
contaminated when we were checking the contamination of the masks used in
maintenance work of the water treatment system. Then, as a result of the
measurement by whole body counter, we have confirmed that no one took in
radioactive materials.
- At approximately 4 pm on September 14, a TEPCO employee who returned from
the patrol on the generators of Unit 1 - 4 (outdoors) to Visitors Hall of
Fukushima Daini Nuclear Power Station got decontaminated since
contamination at his chin and neck was detected. Then as a result of the
measurement by whole body counter, we have evaluated that no radioactive
materials was taken in.
- At approximately 8:18 am on September 15, we found a partner company
worker unequipped with a charcoal filter to the full-faced mask after the
worker entered the site of Fukushima Daiichi Nuclear Power Station. We
will check by whole body counter if he took in radioactive materials.
- At 10 am on September 15, we started transfer of accumulated water from
the turbine building of Unit 6 to the temporary tank.