search



Corporate Information

 
Press Release (Aug 13,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, Aug 13)
 
*No Updates from Previous Announcement 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1 (Shut down) 
-Explosive sound and white smoke were confirmed after the big quake
 occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
-At approximately 2:30 am on March 23, seawater injection to the reactor
 through the reactor feed water system was initiated.
-From 3:37 pm on March 25, we started injecting freshwater by a motor
 driven pump which is now powered by the off-site transmission line. 
 Water is currently injected at approx. 3.9 m3/h through reactor feed
 water system piping arrangement.
-We commenced injection of nitrogen gas into Primary Containment Vessel
 at 1:31am on April 7.
-At 9:00 am on August 10, we started to assemble steel frame for the
 Reactor Building Cover. 
Unit 2 (Shut down) 
-At approximately 6:00 am on March 15, an abnormal noise began emanating
 from nearby Pressure Suppression Chamber and the pressure within the
 chamber decreased. 
-From 10:10 am on March 26, we started injecting freshwater to the reactor
 and are now injecting fresh water by a motor driven pump powered by the
 off-site transmission line.
 Water is currently injected at approx. 3.9 m3/h through reactor feed
 water system piping arrangement.
-At 8:06 pm on June 28, we started injecting nitrogen gas into the Primary
 Containment Vessel. 
Unit 3 (Shut down) 
-Explosive sound and white smoke were confirmed at approximately 11:01am
 on March 14. It was assumed to be hydrogen explosion.
-From 6:02 pm on March 25, we started injecting fresh water to the reactor
 and are now injecting fresh water by a motor driven pump powered by the
 off-site transmission line.
 Water is currently injected at approx. 9.1 m3/h through reactor feed
 water system piping arrangement.
-At 8:01 pm on July 14, injection of nitrogen gas into the Primary
 Containment Vessel started. 
Unit 4 (Outage due to regular inspection) 
-At approximately 6 am on March 15, we confirmed the explosive sound and
 the sustained damage around the 5th floor rooftop area of Reactor
 Building.
-At this moment, we don't think there is any reactor coolant leakage
 inside the primary containment vessel. 
Unit 5 (Outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 5 am on March 19, we started the Residual Heat Removal System Pump in
 order to cool the spent fuel pool.
-At 2:30 pm on March 20, the reactor achieved cold shutdown.
-At 2:45 pm on July 15, we started the operation of the original Residual
 Heat Removal System Pump (B).
-At this time, we don't think there is any reactor coolant leakage inside
 the primary containment vessel. 
Unit 6 (Outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 10:14 pm on March 19, we started the Residual Heat Removal System Pump
 of Unit 6 to cool down Spent Fuel Pool.
-At 7:27 pm on March 20, the reactor achieved cold shutdown. 
-At this time, we don't think there is any reactor coolant leakage inside
 the primary containment vessel. 
Operation for cooling the Spent Fuel Pools 
-At 5:21 pm on May 31, we started cyclic cooling of Spent Fuel Pool of
 Unit 2 by using alternative cooling system of the Pool's cooling and
 filtering system.
-At 7:47 pm on June 30, we started cyclic cooling of Spent Fuel Pool of
 Unit 3 by using alternative cooling system of the Pool's cooling and
 filtering system.
-At 0:44 am on July 31, we started cyclic cooling of Spent Fuel Pool of
 Unit 4 by using alternative cooling system of the Pool's cooling and
 filtering system.
-At 11:22 am on Aug 10, we started cyclic cooling of Spent Fuel Pool of
 Unit 1 by using alternative cooling system of the Pool's cooling and
 filtering system. 
Others 
-At 11:00 am on May 10, we started transferring accumulated water from the
 underground level of reactor building to the radiation waste treatment
 facility of Unit 6.
-At around 10 am on June 13, we started the operation of the circulating
 seawater purification facility installed at the screen area of Unit 2 and
 3.
-At 8:00 pm on June 17, we started operation of Water Treatment Facility
 against the accumulated water. 
-At 6:00 pm on July 2, we started the circulating injection cooling to
 inject the water, which was treated by the accumulated water treatment
 system, to the reactors through the buffer tank.
-At 8:42 am on August 5, we started transferring accumulated water at
 Unit 3 turbine building to Centralized Radiation Waste Treatment Facility.
-At 4:47 pm on August 10, we started transferring accumulated water at
 Unit 2 turbine building to Centralized Radiation Waste Treatment Facility. 
back to page top


to TOP