search



Corporate Information

 
Press Release (Aug 12,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, Aug 12)
 
*New items are underlined 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1 (Shut down) 
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- At approximately 2:30 am on March 23, seawater injection to the reactor 
  through the reactor feed water system was initiated.
- From 3:37 pm on March 25, we started injecting freshwater by a motor 
  driven pump which is now powered by the off-site transmission line. 
- At 3:52 am on August 12, as we observed decline in the volume of water 
  injected into the reactor through reactor feed water system piping 
  arrangement. 
  Water is currently injected at approx. 3.9 m3/h through reactor feed 
  water system piping arrangement.
- We commenced injection of nitrogen gas into Primary Containment Vessel 
  at 1:31am on April 7.
- At 9:00 am on August 10, we started to assemble steel frame for the 
  Reactor Building Cover. 
Unit 2 (Shut down) 
- At approximately 6:00 am on March 15, an abnormal noise began emanating 
  from nearby Pressure Suppression Chamber and the pressure within the 
  chamber decreased. 
- From 10:10 am on March 26, we started injecting freshwater to the reactor  
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.
  Water is currently injected at approx. 3.8 m3/h through reactor feed 
  water system piping arrangement.
- At 8:06 pm on June 28, we started injecting nitrogen gas into the Primary 
  Containment Vessel. 
Unit 3 (Shut down) 
- Explosive sound and white smoke were confirmed at approximately 11:01am 
  on March 14. It was assumed to be hydrogen explosion.
- From 6:02 pm on March 25, we started injecting fresh water to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line. However at 4:22 pm on August 10, we adjusted 
  the flow rate of injection water to the reactor.
  Water is currently injected at approx. 9.1 m3/h through reactor feed water 
  system piping arrangement.
- At 8:01 pm on July 14, injection of nitrogen gas into the Primary 
  Containment Vessel started. 
Unit 4 (Outage due to regular inspection) 
- At approximately 6 am on March 15, we confirmed the explosive sound and 
  the sustained damage around the 5th floor rooftop area of Reactor Building.
- At this moment, we don't think there is any reactor coolant leakage inside 
  the primary containment vessel. 
Unit 5 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5 am on March 19, we started the Residual Heat Removal System Pump in 
  order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved cold shutdown.
- At 2:45 pm on July 15, we started the operation of the original Residual 
  Heat Removal System Pump (B).
- At this time, we don't think there is any reactor coolant leakage inside 
  the primary containment vessel. 
Unit 6 (Outage due to regular inspection) 
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System Pump 
  of Unit 6 to cool down Spent Fuel Pool.
- At 7:27 pm on March 20, the reactor achieved cold shutdown. 
- At this time, we don't think there is any reactor coolant leakage inside 
  the primary containment vessel.
- From 9:30 am to 1:40 pm on August 9, we conducted plumbing between 
  temporary pump and residual heat removal system pump (A) to enforce the 
  connection method. We stopped the power source of residual heat removal 
  system pump (B) during this work. Even though cooling of a reactor and a 
  spent fuel pool were temporarily suspended, there are no safety issues 
  regarding this. 
Operation for cooling the Spent Fuel Pools 
- At 5:21 pm on May 31, we started cyclic cooling of Spent Fuel Pool of 
  Unit 2 by using alternative cooling system of the Pool's cooling and 
  filtering system.
- At 7:47 pm on June 30, we started cyclic cooling of Spent Fuel Pool of 
  Unit 3 by using alternative cooling system of the Pool's cooling and 
  filtering system.
- At 0:44 am on July 31, we started cyclic cooling of Spent Fuel Pool of 
  Unit 4 by using alternative cooling system of the Pool's cooling and 
  filtering system.
- At 11:22 am on Aug 10, we started cyclic cooling of Spent Fuel Pool of 
  Unit 1 by using alternative cooling system of the Pool's cooling and 
  filtering system. 
Injured 
- Around 12:05 pm on August 10, one partner company worker who was mowing 
  for curing of water treatment hose at west side of Centralized Radiation 
  Waste Treatment Facility (outside) was injured his right leg by sickle 
  and was transferred to the Fukushima Rosai Hospital by the ambulance. 
  Diagnose was given as contusion of right leg. 
Others 
- At 11:00 am on May 10, we started transferring accumulated water from 
  the underground level of reactor building to the radiation waste treatment 
  facility of Unit 6.
- At around 10 am on June 13, we started the operation of the circulating 
  seawater purification facility installed at the screen area of Unit 2 
  and 3.
- At 8:00 pm on June 17, we started operation of Water Treatment Facility 
  against the accumulated water. 
- At 6:00 pm on July 2, we started the circulating injection cooling to 
  inject the water, which was treated by the accumulated water treatment 
  system, to the reactors through the buffer tank.
- At 8:42 am on August 5, we started transferring accumulated water at 
  Unit 3 turbine building to Centralized Radiation Waste Treatment Facility.
- At 10:00 am on August 9, we started transferring low level accumulated 
  water from outdoor temporary tanks to Mega Float. However, at 10:12 am, 
  since leakage was confirmed from the transferring pipes cabled at outside, 
  we stopped transferring. Thereafter, such pipes were replaced and at 1:35 
  pm, we resumed transferring.
- At 11:00 am on August 9, we started transferring of accumulated water 
  from inside the Unit 6 turbine building to temporary tanks and finished 
  on 5:00 pm on August 10.
- At 4:47 pm on August 10, we started transferring of accumulated water 
  from turbine building of unit 2 to Centralized Radiation Waste Treatment 
  Facility.
- From 10:00 am to 4:00 pm on August 11, we transferred accumulated water 
  from inside the Unit 6 turbine building to temporary tanks. At 10:00 am 
  on August 12, we restarted transferring accumulated water. 
- At around 3:00 pm on August 11, we confirmed opening the breaker which 
  supply power to the battery charger of the power source for controlling 
  the temporary metal clad of Units 1 and 2. At 4:00 pm, we observed decline 
  in the voltage of the back-up battery of the power source for controlling, 
  at 1:21 pm on August 12, we replaced the battery and the battery charger 
  and restarted receiving power. 
- At around 3:22 on August 12, a 6-magnitude earthquake centered in off the 
  coast of Fukushima prefecture occurred. There were no abnormalities 
  observed in the status of water injection into the reactors of Units 1 to 
  3, nitrogen gas injection into the primary containment vessels of Units 
  1 to 3, operation of water treatment facilities, circulating cooling of 
  pool water by the substitute pool cooling and filtering system, etc. 
  There was no influence on the operation of water treatment system, 
  however, the boiler of concentrating device of the desalination instrument 
  stopped and we reset it at 3:42 pm. Later during a patrol, there was no 
  influence found on the important facilities, however, at 5:06 am, we found 
  one of the two temporary air compressors for instrumentation stopped. As 
  we could not restart it, we started a back-up diesel-powered compressor 
  at 6:44 am. At 5:27 am, we observed a slight amount of bleeding at the 
  surface of a hose of a spent fuel pool circulating cooling facility in the 
  waste treatment building of Unit 4. We are planning to replace it later. 
  There is neither abnormality in the major parameters of each unit, nor 
  injuries to the staff. The readings of the monitoring posts stay in the 
  normal fluctuation range. 
back to page top


to TOP