On August 2, 2011, we received an instruction document* titled "Submission
request for report on the measures to continue water injection into
reactors of Unit 1 to 3 at Fukushima Daiichi Nuclear Power Station" from
Nuclear and Industrial Safety Agency (NISA) of Ministry of Economy, Trade
and Industry.
Based on the instruction, we will summarize all materials with regard to
the situation of the equipment and procedures for continuous water
injection into reactors of Unit 1 to 3 at Fukushima Daiichi Nuclear Power
Station and safety assessment, then submit the report to NISA immediately.
END
* Instruction document
Submission request for report on the measures to continue water injection
into reactors of Unit 1 to 3 at Fukushima Daiichi Nuclear Power Station
(August 2, 2011, NISA)
We have provided a Japanese press release version of the instruction
document received from NISA. However, at this time we have reserved the
right not to provide an English version due to potential misunderstandings
that may arise from an inaccurate rendering of the original Japanese text.
We may provide the English translation that NISA releases in our press
releases. However, in principle we would advise you to visit the NISA
website for timely and accurate information.