On March 11 2011, Fukushima Daini Nuclear Power Station Units 1 to 4
(Boiling Water Reactors, rated output 1,100 Megawatts each) that we had
been operating at rated thermal output shutdown automatically at 2:48 pm,
due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake (previously announced
on March 11).
At 7:15 am on March 15, the reactor of Unit 4 achieved a cold shutdown.
As a result, all the Units of Fukushima Daini Nuclear Power Station
achieved the status of cold shutdown (previously announced on March 15).
As of 3:00 pm on August 1, Units 1 to 4 remain in a cold shutdown (please
refer to the appendix).
We will make our best efforts to stabilize each plant.
○Regular inspection of monitoring post
Among monitoring post (total of 7), which are installed at site
boundary, we are implementing regular inspection for No. 1 - 6
(1 monitoring post per day) from July 29 to August 8.
In the period of inspection, although it is unable to measure radiation
dose by such monitoring post, we will continue to measure and confirm the
data by using remainder of 6 monitoring post.
Inspection date might be changed due to the weather.
(Operation Results of Regular Inspection)
○No. 6: July 29, 9:31 am - 6:30 pm in regular inspection
* No significant changes in the data were confirmed before and after
the inspection of monitoring posts.
·There are no updates from the previous press release.
Appendix: TEPCO Plant Status of Fukushima Daini Nuclear Power Station
(PDF 16.7KB)