Press Release (Jul 29,2011)
Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, July 29)
On March 11 2011, Fukushima Daini Nuclear Power Station Units 1 to 4 
(Boiling Water Reactors, rated output 1,100 Megawatts each) that we had 
been operating at rated thermal output shutdown automatically at 2:48 pm, 
due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake (previously announced 
on March 11).

At 7:15 am on March 15, the reactor of Unit 4 achieved a cold shutdown. 
As a result, all the Units of Fukushima Daini Nuclear Power Station 
achieved the status of cold shutdown (previously announced on March 15).

As of 3:00 pm on July 29, Units 1 to 4 remain in a cold shutdown (please 
refer to the appendix). 

We will make our best efforts to stabilize each plant.

<Updates are underlined>
 Among monitoring post (total of 7), which are installed at site 
 boundary, we are implementing regular inspection for No. 1 - 6 from 
 today. 
 This inspection will be implemented 1 monitoring post per day until 
 August 8. 
 In the period of inspection, although it is unable to measure radiation 
 dose by such monitoring post, we will continue to measure and confirm 
 the data by using remainder of 6 monitoring post. 
 Inspection date might be changed due to the weather. 
 
 (Operation Results of Regular Inspection) 
 ○No.6: July 29, 9:31 am - in regular inspection 