The following is the current operational status of Fukushima Daini
Nuclear Power Station subsequent to the earthquake that occurred at 3:51 am,
July 25, 2011:
The maximum seismic acceleration was observed to be 18.8 gal at the
basement mat of the reactor building of Unit 1.
Influence of radioactivity outside: None
The figures of the exhaust stack monitors for radiation monitoring and the
monitoring posts at the station boundary are within the usual range, and
there is no outside radioactive influence as of now.