search



Corporate Information

 
Press Release (Jul 04,2011)
Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, July 4)
On March 11 2011, Fukushima Daini Nuclear Power Station Units 1 to 4 
(Boiling Water Reactors, rated output 1,100 Megawatts each) that we had 
been operating at rated thermal output shutdown automatically at 2:48 pm, 
due to the Tohoku-Chihou-Taiheiyou-Oki Earthquake (previously announced 
on March 11).

At 7:15 pm on March 15, the reactor of Unit 4 achieved a cold shutdown. As 
a result, all the Units of Fukushima Daini Nuclear Power Station achieved 
the status of cold shutdown (previously announced on March 15). 

As of 3:00 pm on July 4, the Units 1 to 4 remain in a cold shutdown (please 
refer to the appendix). We will make our best efforts to stabilize each 
plant.

·There is no update from the previous press release. 
Appendix: TEPCO Plant Status of Fukushima Daini Nuclear Power Station 
                                                              (PDF 17.0KB) 
back to page top


to TOP