Press Release (Jun 30,2011)
(Announcement)Status of flood prevention measures from tsunami at Kashiwazaki Kariwa Nuclear Power Station
Taking into consideration the accident at Fukushima Daiichi Nuclear Power 
Station due to the impact of tsunami after Tohoku - Pacific Ocean Earthquake 
on March 11th 2011, we have implemented emergency safety measures to prevent 
reactor core and spent fuel damage, and to quickly restore cooling function, 
as well as implement a water stoppage measure at Unit 1 reactor building.
Furthermore, in order to secure reliability and safety against tsunamis, we 
are in continuous discussion on the construction of tide barriers of Units 
1 to 4, and tide embankment etc in front of the power station. 

Today, we announce that we have put together a basic design of tide barriers 
and tide prevention plates to be implemented at Units 1 to 4, which are 
designed to prevent building from flooding by tsunamis. 

Based on the basic design of tide barriers and tide prevention plates put 
together this time, we will proceed with making detailed designs, as well 
as explaining this to the government and Niigata Prefecture Technical 
Committee.

We will continuously work on measures to further secure the reliability and 
safety of tide embankment etc.  