search



Corporate Information

 
Press Release (Jun 25,2011)
Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 25)
 
On March 11 2011, turbines and reactors of Fukushima Daini Nuclear Power 
Station Units 1 to 4 (Boiling Water Reactors, rated output 1,100 Megawatts) 
that we had been constantly operating at rated thermal output were 
automatically shut down at 2:48 pm due to the Tohoku-Chihou-Taiheiyou-Oki 
Earthquake (previously announced on March 11).

At 7:15 pm on March 15, the reactor of Unit 4 achieved cold shutdown. As a 
result, all reactors of Units 1 to 4 at Fukushima Daini Nuclear Power 
Station achieved cold shutdown (previously announced on March 15). 

As of 3:00 pm on June 25, the reactors of Unit 1 to 4 are in cold shutdown 
(please refer to the appendix). We continue to make our endeavors to 
stabilize each plant.

·There is no update from the previous press release. 
Appendix: TEPCO Plant Status of Fukushima Daini Nuclear Power Station 
                                                         (PDF 17.0KB) 
back to page top


to TOP