Press Release (Jun 24,2011)
Regarding the report on installing the Reactor Building Cover for Unit 1 of Fukushima Daiichi Nuclear Power Station
 
In accordance with "Roadmap towards Restoration from the Accident at
Fukushima Daiichi Nuclear Power Station", we have decided to install a
cover for the reactor building of Unit 1 of Fukushima Daiichi Nuclear
Power Station in order to prevent the diffusion of radioactive substances
and are going to commence main construction in the site on June 27th.
                          (Previously announced on May 13th and June 14th)

On June 22nd, from Nuclear and Industrial Safety Agency of Ministry of
Economy, Trade and Industry (NISA), we have received an instruction
document* entitled "Instruction to report on installing the reactor
building cover and ancillary facilities for Unit 1 of Fukushima Daiichi
Nuclear Power Station of Tokyo Electric Power Company"
                                     (Previously announced on June 22nd)

Afterward, with regards to the installation of Reactor Building Cover of
Unit 1 of Fukushima Daiichi Nuclear Power Station, we have summarized
detail of the plan and assessment of inhibitory effectiveness for
discharge of radioactive material and safety and reported to NISA yesterday.

Attachment
·Installation of Reactor Building Cover and adjacent facilities of Unit 1 
                     of Fukushima Daiichi Nuclear Power Station(PDF 320KB) 
*Instruction document
Instruction to report on installing the reactor building cover and
ancillary facilities for Unit 1 of Fukushima Daiichi Nuclear Power Station
of Tokyo Electric Power Company

We have provided a Japanese press release version of the instruction
document received from NISA.  However, at this time we have reserved the
right to not provide an English version due to potential misunderstandings
that may arise from an inaccurate rendering of the original Japanese text.
We may provide the English translation that NISA releases in our press
releases. However, in principle we would advise you to visit the NISA
website for timely and accurate information. 
back to page top


to TOP