We are announcing the status of major inspections and restoration works
and nonconformances at TEPCO's Kashiwazaki-Kariwa Nuclear Power Station
after the Niigata-Chuetsu-Oki Earthquake.
Inspection/ Restoration Status
◇ Inspection and restoration completed between June 17 to June 23, 2011
(Completed on the following date)
- No notable activity during this week.
◇ Inspection and restoration to be commenced between June 24 to June 30,
2011
(To be commenced on the following date)
- Unit 4 Seismic reinforcement (Seismic reinforcement works such as pipe
supports; reinforcement work for attached structure of reactor pressure
vessel):
June 27
◇ Work Schedule of Major Inspection and Restoration from June 19 to July
16, 2011
- Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) ...Appendix
(Reference)
Nonconformances Found in the Inspection and Restoration Works Performed
after the Niigata-Chuetsu-Oki Earthquake
Based on the "Public Announcement Regarding Nonconformance Found in the
Inspection and Restoration Works Performed after the Niigata-Chuetsu-Oki
Earthquake", the Tokyo Electric Power Company, Incorporated (TEPCO)
provides this announcement containing incidents information reported from
June 16 to June 22, 2011.
◇ Incidents Information (relating to the Chuetsu-Oki Earthquake)
| |
<Reports from June 16 to June 22, 2011>
◇ Other Findings
- Nothing to disclose to this week.
Appendix: Work Schedule of the Main Inspection/ Restoration of the Kashiwazaki-
Kariwa Nuclear Power Station in Response to the Niigata-Chuetsu-Oki
Earthquake (during 4 Weeks) (PDF 68.3KB)