Press Release (Jun 16,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 3:00 pm, June 16)
*Updates are underlined 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1 (Shut down)  
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- At approximately 2:30 am on March 23, seawater injection to the reactor 
  through the reactor feed water system was initiated.
- From 3:37 pm on March 25, we started injecting freshwater by a motor 
  driven pump powered by the off-site transmission line. We are now 
  injecting freshwater by a motor driven pump powered by the off-site 
  transmission line. Current injected water amount is approx. 4.5 m3/h 
  through feed water system.
- As it was suspected that hydrogen gas had been accumulated inside Primary 
  Containment Vessel, in order to prevent increase in density of oxygen, we 
  commenced the valve opening operation concerning injection of nitrogen 
  gas into the primary containment vessel at 10:30 pm on April 6 and 
  commenced injection at 1:31am April 7. 
Unit 2 (Shut down)  
- At approximately 6:00 am on March 15, an abnormal noise began emanating 
  from nearby Pressure Suppression Chamber and the pressure within the 
  chamber decreased. 
- From 10:10 am on March 26, we started injecting freshwater to the reactor 
  and are now injecting freshwater by a motor driven pump powered by the 
  off-site transmission line. 
  The current rate of water injection is approx. 5 m3/h through the reactor 
  feed water system piping arrangement. 
Unit 3 (Shut down)  
- Explosive sound and white smoke were confirmed at approximately 11:01am 
  on March 14. It was assumed to be hydrogen explosion.
- From 6:02 pm on March 25, we started injecting fresh water to the reactor 
  and are now injecting fresh water by a motor driven pump powered by the 
  off-site transmission line.
  The current rate of water injection is approx. 11.5 m3/h through the 
  reactor feed water system piping arrangement. 
Unit 4 (Outage due to regular inspection)  
- At approximately 6:00 am on March 15, we confirmed the explosive sound 
  and the sustained damage around the 5th floor rooftop area of Reactor 
  Building.
- At this moment, we do not consider any reactor coolant leakage inside the 
  primary containment vessel has occurred. 
Unit 5 (Outage due to regular inspection) 
 - Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System Pump 
  (C) in order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved cold shutdown. 
- At this moment, we do not consider any reactor coolant leakage inside the 
  primary containment vessel has occurred. 
Unit 6 (Outage due to regular inspection)  
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System Pump 
  (B) of Unit 6 in order to cool the spent fuel pool.
- At 7:27 pm on March 20, the reactor achieved cold shutdown. 
- At this moment, we do not consider any reactor coolant leakage inside the 
  primary containment vessel has occurred. 
Operation for cooling the spent fuel pools  
- At 5:21 pm on May 31, we started cyclic cooling of the spent fuel pool in 
  Unit 2 using alternative cooling system for fuel pool cooling and 
  filtering system. 
- At 1:14 pm on June 16, we started injecting water to the spent fuel pool 
  of Unit 4 by temporary water spraying equipment (At 1:48 pm, additional 
  injection of hydrazine (corrosion inhibitor) was started).   
- We will continuously conduct further water spray depending on the 
  conditions of spent fuel pools, if needed. 
Others  
- At 1:30 pm on April 26, we started spraying the dust inhibitor inside the 
  site. On May 27, we started spraying dust inhibitor to Turbine Building 
  of Units 1. We will implement spraying the dust inhibitor to other 
  turbine and reactor buildings of Units 1 to 4.
- At 2:00 pm on May 1, we started transferring accumulated water in the 
  turbine building of Unit 6 to temporary tanks.
- At 11:00 am on May 10, we started transferring accumulated water from the 
  underground level of reactor building to the radiation waste treatment 
  facility of Unit 6.
- From 6:39 pm on June 4 to 8:40 am on June 16, transfer of accumulated 
  water from vertical shafts (trenches) of turbine building of Unit 2 to 
  Process Main Building was conducted.
- At 12:42 pm on June 11, we started to operate local exhausters in order 
  to improve inside environment of Unit 2 Reactor Building.
- At approximately 10:00 am on June 13, we started the operation of the 
  circulating seawater purification facility installed at the screen area 
  of Unit 2 and 3.
- From 10:05 am on June 14 to 8:46 am on June 16, transfer of accumulated 
  water in the Unit 3 turbine building to the centralized radiation waste 
  treatment facility was conducted. 
- From 10:33 am on June 15 to 9:52 am on June 16, transfer of accumulated 
  water in the Unit 1 condenser to condenser storage tank was conducted. 
- At 11:05 am on June 15, it was confirmed that a worker from a partner 
  company in charge of crane assembling work for the preparing the 
  installation of the cover in Unit 1 reactor building at shallow draft 
  quay was smoking without his full mask. However, the result of whole body 
  counter examination showed a slight amount of internal exposure dose and 
  we confirmed that the amount has no adverse effect on the body.
- We will continue to take all measures to ensure the safety and to 
  continue monitoring the surrounding environment around the power station. 