search



Corporate Information

 
Press Release (Jun 02,2011)
Plant Status of Fukushima Daini Nuclear Power Station (as of 3:00 pm, June 2)
 
On March 11 2011, turbines and reactors of Fukushima Daini Nuclear Power
Station Units 1 to 4 (Boiling Water Reactors, rated output 1,100
Megawatts) that we had been constantly operating at rated thermal output
were automatically shut down at 2:48 pm due to the 
Tohoku-Chihou-Taiheiyou-Oki Earthquake (previously announced on March 11).

At 7:15 pm on March 15, the reactor of Unit 4 achieved cold shutdown. As a
result, all reactors of Units 1 to 4 at Fukushima Daini Nuclear Power
Station achieved cold shutdown (previously announced on March 15).  

As of 3:00 pm on June 2, the reactors of Unit 1 to 4 are in cold shutdown
(please refer to the appendix). We continue to make our endeavors to
stabilize each plant.

·There is no update from the previous press release. 
 Appendix: TEPCO Plant Status of Fukushima Daini Nuclear Power Station 
                                                          (PDF 17.1KB) 
back to page top


to TOP