*No Updates
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down.
Unit 1 (Shut down)
- Explosive sound and white smoke were confirmed after the big quake
occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
- At approximately 2:30 am on March 23, seawater injection to the reactor
through the feed water system was initiated.
- From 3:37 pm on March 25, we started injecting freshwater and are now
injecting fresh water by a motor driven pump powered by the off-site
transmission line.
- As it is suspected that hydrogen gas is accumulated inside Primary
Containment Vessel, we commenced the valve opening operation concerning
injection of nitrogen gas into the primary containment vessel at 10:30 pm
April 6 and commenced injection at 1:31am April 7.
- At 11:50 am on May 17, we have decreased the amount of freshwater
injected into the reactor from approximately 10 m 3/h to approximately
6 m 3/h, since we have finished monitoring the trend shift of parameters
of the Reactor Pressure Vessel as well as the primary containment vessel,
the shift which would be resulted from the increase of the amount of
injected freshwater.
Unit 2 (Shut down)
- At approximately 6:00 am on March 15, an abnormal noise began emanating
from nearby Pressure Suppression Chamber and the pressure within the
chamber decreased.
- From 10:10 am on March 26, we started injecting freshwater to the
reactor and are now injecting fresh water by a motor driven pump powered
by the off-site transmission line.
Unit 3 (Shut down)
- Explosive sound and white smoke were confirmed at approximately 11:01am
on March 14. It was assumed to be hydrogen explosion.
- From 6:02 pm on March 25, we started injecting fresh water to the
reactor and are now injecting fresh water by a motor driven pump powered
by the off-site transmission line.
- At 4:53 pm on May 12, as a part of work to switch the water injection
line to the reactor from the fire extinction system to the reactor feed
water system, we started water injection through the reactor feed water
system in addition to through the fire extinction system.
- At 5:39 am on May 20, we have decreased the amount of water injection
through fire protection system from approximately 9 m 3/h to
approximately 8 m 3/h, at 8:43pm further decreased from approximately
8 m 3/h to approximately 7 m 3/h, and at 11:54 from approximately
7 m 3/h to approximately 6 m 3/h.
- The current rate of water injection is approximately 6 m3/h through the
fire protection system piping arrangement and approximately 12 m3/h
through the reactor feed water system piping arrangement .
Unit 4 (Outage due to regular inspection)
- At approximately 6:00 am on March 15, we confirmed the explosive sound
and the sustained damage around the 5th floor rooftop area of Reactor
Building.
- At this moment, we do not consider any reactor coolant leakage inside
the primary containment vessel happened.
Unit 5 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19, we started the Residual Heat Removal System Pump
(C) in order to cool the spent fuel pool.
- At 2:30 pm on March 20, the reactor achieved cold shutdown.
- At this moment, we do not consider any reactor coolant leakage inside
the primary containment vessel happened.
Unit 6 (Outage due to regular inspection)
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19, we started the Residual Heat Removal System Pump
(B) of Unit 6 in order to cool the spent fuel pool.
- At 7:27 pm on March 20, the reactor achieved cold shutdown.
- At this moment, we do not consider any reactor coolant leakage inside
the primary containment vessel happened.
Operation for cooling the spent fuel pools
- At 3:06 pm on May 20, we started water spray to Unit 1 by a concrete
pumping vehicle, however, since there was a possibility that the water
was not properly poured into the spent fuel pool due to the wind and
other factors, we stopped spray at 4:15pm.
- We will continuously conduct further water spray depending on the
conditions of spent fuel pools, if needed.
Others
- At 1:30 pm on April 26, we started spraying the dust inhibitor inside the
site.
- At 10:08 am on April 19, we started transfer of high level radioactive
wastewater from the vertical shaft near the turbine building of Unit 2
to the Centralized Radiation Waste Treatment Facility.
- At 2:00 pm on May 1, we started transferring the accumulated water in
turbine building of Unit 6 to temporary tanks.
- At 11:00 am on May 10, we started transferring the accumulated water
from the underground level of reactor building to the radiation waste
treatment facility of Unit 6.
- At 6:04 pm on May 17, we started transfer of high level radioactive
waste water from the underground level of the turbine building of Unit 3
to the Centralized Radiation Waste Treatment Facility.
- On May 20, we have conducted improvement of monitoring environment to
some of the 8 detectors (No. 8) set at the boundaries of the power
station by implementing decontamination and putting shield to the lower
part of the detector.
- At 9:35 am on May 21, Mega Float which is planned to be used for storing
low level radioactive waste liquid arrived at the shallow draft quay.
- We will continue to take all measures to ensure the safety and to
continue monitoring the surrounding environment around the power station.