search



Corporate Information

 
Press Release (May 02,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:30 am, May 2)
*New updates are underlined 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1 (Shut down) 
-Explosive sound and white smoke were confirmed after the big quake 
 occurred at 3:36 pm on March 12. It was assumed to be hydrogen explosion.
-At approximately 2:30 am on March 23, seawater injection to the nuclear 
 reactor through the feed water system was initiated.
-From 3:37 pm on March 25, we started injecting freshwater and are now 
 injecting fresh water by a motor driven pump powered by the off-site 
 transmission line. From on April 27, we have increased the amount of 
 injecting freshwater from approximately 6 m3/h to approximately 14 m3/h. 
 At 10:14 am on April 29, we put the amount of injecting freshwater back 
 to approximately 6 m3/h.
-As it is suspected that hydrogen gas is accumulated inside reactor 
 containment vessel, we commenced the valve opening operation concerning 
 injection of nitrogen gas into the reactor container vessel at 10:30 pm 
 April 6th and commenced injection at 1:31am April 7. 
Unit 2(Shut down) 
-At approximately 6:00 am on March 15, an abnormal noise began emanating 
 from nearby Pressure Suppression Chamber and the pressure within the 
 chamber decreased. 
-From 10:10 am on March 26, we started injecting freshwater to the reactor 
 and are now injecting fresh water by a motor driven pump powered by the 
 off-site transmission line. 
Unit 3(Shut down) 
 -Explosive sound and white smoke were confirmed at approximately 11:01am 
 on March 14. It was assumed to be hydrogen explosion.
-From 6:02 pm on March 25, we started injecting fresh water to the reactor 
 and are now injecting fresh water by a motor driven pump powered by the 
 off-site transmission line. 
Unit 4 (outage due to regular inspection) 
 -At approximately 6:00 am on March 15, we confirmed the explosive sound 
 and the sustained damage around the 5th floor rooftop area of the Nuclear 
 Reactor Building.
-At this moment, we do not consider any reactor coolant leakage inside the 
 reactor happened. 
Unit 5 (outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 5:00 am on March 19, we started the Residual Heat Removal System Pump 
 (C) in order to cool the spent fuel pool.
-At 2:30 pm on March 20, the reactor achieved reactor cold shutdown. 
-At this moment, we do not consider any reactor coolant leakage inside the 
 reactor happened. 
Unit 6 (outage due to regular inspection) 
-Sufficient level of reactor coolant to ensure safety is maintained.
-At 10:14 pm on March 19, we started the Residual Heat Removal System Pump 
 (B) of Unit 6 in order to cool the spent fuel pool.
-At 7:27 pm on March 20, the reactor achieved reactor cold shutdown. 
-At this moment, we do not consider any reactor coolant leakage inside the 
 reactor happened. 
Operation for cooling the spent fuel pools 
-From 10:05 am, May 2, water injection to Unit 2 by a temporary motor 
 driven pump was started. 
-We will continuously conduct further water spray depending on the 
 conditions of spent fuel pools, if needed. 
Others 
-Regarding the transfer of high level radioactive wastewater in Unit 2 to 
 the Centralized Radiation Waste Treatment Facility, while we temporarily 
 suspended transfer due to the inspection of transferring facilities at 
 9:16 am on April 29, transfer was restarted at 2:05pm on April 30.
-The transfer of accumulated water in Unit 6 turbine building to a 
 temporary tank was conducted from 2:00 pm to 5:00 pm on May 1 and the 
 transfer was started from 10:00 am, May 2. 
-We will continue to take all measures to ensure the safety and to 
 continue monitoring the surrounding environment around the power station. 
back to page top


to TOP