search



Corporate Information

 
Press Release (Apr 28,2011)
Plant Status of Fukushima Daiichi Nuclear Power Station (as of 10:00 am, April 28)
*Updates are underlined 
All 6 units of Fukushima Daiichi Nuclear Power Station have been shut down. 
Unit 1 (Shut down)  
- Explosive sound and white smoke were confirmed after the big quake 
  occurred at 3:36 pm on March 12th. It was assumed to be hydrogen 
  explosion.
- At approximately 2:30 am on March 23rd, seawater injection to the nuclear 
  reactor through the feed water system was initiated.
- From 3:37 pm on March 25th, we started injecting freshwater and are now 
  injecting fresh water by a motor driven pump powered by the off-site 
  transmission line.
- At 10:02 am on April 27th, in order to examine an appropriate amount of 
  water to make nuclear reactor flooded, the gradual operation to change 
  the amount of injecting freshwater from 6 m3/h to approximately 14 m3/h 
  was initiated
- As it is suspected that hydrogen gas is accumulated inside reactor 
  containment vessel, we commenced the valve opening operation concerning 
  injection of nitrogen gas into the reactor container vessel at 10:30 pm 
  April 6th and commenced injection at 1:31am April 7th. 
Unit 2 (Shut down)  
- At approximately 6:00 am on March 15th, an abnormal noise began emanating 
  from nearby Pressure Suppression Chamber and the pressure within the 
  chamber decreased. 
- From 10:10 am on March 26th, we started injecting freshwater to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
Unit 3 (Shut down)  
- Explosive sound and white smoke were confirmed at approximately 11:01am 
  on March 14th. It was assumed to be hydrogen explosion.
- From 6:02 pm on March 25th, we started injecting fresh water to the 
  reactor and are now injecting fresh water by a motor driven pump powered 
  by the off-site transmission line. 
Unit 4 (outage due to regular inspection)  
- At approximately 6:00 am on March 15th, we confirmed the explosive sound 
  and the sustained damage around the 5th floor rooftop area of the Nuclear 
  Reactor Building.
- At this moment, we do not consider any reactor coolant leakage inside the 
  reactor happened. 
Unit 5 (outage due to regular inspection)  
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 5:00 am on March 19th, we started the Residual Heat Removal System 
  Pump (C) in order to cool the spent fuel pool.
- At 2:30 pm on March 20th, the reactor achieved reactor cold shutdown. 
- At this moment, we do not consider any reactor coolant leakage inside 
  the reactor happened. 
Unit 6 (outage due to regular inspection)  
- Sufficient level of reactor coolant to ensure safety is maintained.
- At 10:14 pm on March 19th, we started the Residual Heat Removal System 
  Pump (B) of Unit 6 in order to cool the spent fuel pool.
- At 7:27 pm on March 20th, the reactor achieved reactor cold shutdown. 
- At this moment, we do not consider any reactor coolant leakage inside 
  the reactor happened. 
Operation for cooling the spent fuel pools  
- From 12:18 pm to 3:15 pm on April 27th, water spray to the spent fuel 
  pool of Unit 4 by the concrete pumping vehicle was conducted.  
- We will continuously conduct further water spray depending on the 
  conditions of spent fuel pools, if needed. 
Others  
- From 1:30 pm on April 26th, we started spraying dust inhibitor in order 
  to prevent diffusion of radioactive materials.
- At 10:08 am on April 19th we started transferring high level radioactive 
  wastewater to the Centralized Radiation Waste Treatment Facility.
- We will continue to take all measures to ensure the safety and to 
  continue monitoring the surrounding environment around the power station. 
back to page top


to TOP